This Statement of Work (SOW) details a garage door replacement project for the United States Coast Guard Station in Freeport, Texas. The contract requires removing and replacing two existing garage doors in the MK Shop and Civil Bay, including installation of new electric door openers, complete functional testing, and proper disposal of old hardware. The work must be performed during normal operating hours (8:00am to 4:00pm, Monday through Friday), with mandatory notification one week prior to project commencement and coordination with designated Coast Guard representatives.
Key requirements include adhering to OSHA safety standards, wearing company identification, field verifying utility locations, and obtaining government acceptance contingent on product and workmanship verification. The contractor is responsible for providing all necessary labor, materials, and equipment, with no materials supplied by the government. Site visits are recommended before submitting a proposal, and a pre-conference will be held after contract award. The primary point of contact is MKC Zachery Buris, who can be reached at zachery.w.buris@uscg.mil or (757) 788-1923.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 70Z02925QGALV0008_0_US.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF HOMELAND SECURITY
UNITED STATES COAST GUARD
USCG STA FREEPORT
SPECIFICATIONS
FOR
Garage Doors Replacement
General: United States Coast Guard Station Freeport is accepting proposals for qualified individuals or firms to remove Garage door to MK Shop and Garage Door to Civil Bay and install new garage doors and associated hardware. Prior to submitting a quote, it is mandatory to examine the scope of work, and it is highly recommended to visit the facility to take field measurements, evaluations, etc., and become familiar with existing conditions under which the work will be performed. After the award of contract, a pre-conference will be held prior to starting the work at Coast Guard Station Freeport.
Location:
United States Coast Guard Station Freeport 823 Coast Guard Dr.
Freeport, TX 77541
I. Continuity of Facilities Operation: Schedule work to minimize interference with the facility’s normal operations. Normal operating hours are from 8:00am to 4:00pm Monday thru Friday except federal holidays. Any work during other hours unless otherwise instructed or permitted shall be scheduled and approved with the Contracting Officers Representative.
II. Notification of Start and Completion of Work: The Contractor shall notify Coast Guard one week prior to start of work.
III. Coast Guard Contracting Officers Representative: The Contractor shall contact the COR to coordinate all construction efforts onboard Coast Guard Facilities.
| MKC Zachery Buris |
| zachery.w.buris@uscg.mil |
| (757) 788-1923 |
| MK1 Terence Totten |
| Terence.L,Totten@uscg.mil |
| 713-805-4339 |
| MK2 Matthew Santini |
| Matthew.g.santini@ucg.mil |
| 757-618-4623 |
IV: Recycling and Disposal of Refuse: All disposals shall be done in accordance with federal, state, and local laws and regulations. All bulk materials shall be disposed of by contractor. Contractor is responsible for removal and disposal of all old garage doors and hardware.
V: Safety: During the execution of this contract, the Contractor shall conform to the rules and regulations as set forth by OSHA Safety and Health Standards, 29 CFR Part 1926 - Safety and Health Regulations for Construction. The contractor shall have a written safety plan as required in FAR 5.236-13. The plan shall unequivocally assign responsibility and authority for safety to the superintendent by name. Immediate notification to the Contracting Officer’s Representative of lost time due to accidents is required. Provide two copies of workman’s compensation accident reports by noon of the day following the accident. The Coast Guard reserves the right to bar any workers or supervisors from the premises should they be documented as violating set safety standards and regulations.
VI. Inspection: The Contracting Officer’s Representative has the right to reject defective workmanship or materials or work not performed as per the project specifications. Only the Contracting Officer or his/her representative may accept work performed by the contractor.
VII. Operations and Storage: The contractor is to take whatever steps necessary to ensure that his materials are protected. The Coast Guard has no responsibility for receipt, storage, or protection of contractor’s materials. All equipment, materials and supplies shall be addressed to the contractor. The Coast Guard will not accept shipments. The contractor is responsible for the protection of existing structures, utilities, work and vegetation. Any damage shall be repaired at the contractor’s expense.
VIII. Contractor Identification: The contractor and subcontractor personnel shall, at all times, wear company identification.
IX. Existing Utilities: The Contractor shall field verify all utility locations before commencing work. This shall include, but not be limited to, the use of visual, sonic, electronic or magnetic detection devices. Contractor shall be responsible for repairing any utilities damaged during construction at no additional cost to the Government.
VIII: SCOPE OF WORK: Contractor shall provide all labor, materials, and equipment necessary to complete the following unless noted below:
ITEM NAME
Remove Garage door to MK Shop and Garage Door to Civil Bay and install new like kind garage doors and associated hardware Complete function test of new garage doors and associated hardware.
LOCATION:
USCG STA FREEPORT
823 Coast Guard Dr.
Freeport, TX 77541 All Materials and Labor as provided by contractor must be complete, comparable to existing and approved by Contracting Officer.
REQUIREMENTS:
SCOPE
Remove the Garage door and opener in MK Shop, Garage Door to Civil Bay and install new garage doors and associated hardware. both doors will have new electric door openers installed. Complete function test of new garage doors and associated hardware. Remove and dispose of old doors and hardware off property.
Government-The government is not providing any materials for this project.
2. REFERENCES
COAST GUARD DRAWINGS None.
OTHER REFERENCES None.
3. REQUIREMENTS
3.1 General.
MANUFACTURER: N/A
CHARACTERISTICS:
MK shop and Civil Bay garage door replacement.
WARRANTY:
A. Standard Manufacturer's Warranty for all replacement parts and materials
GOVERNMENT ACCEPTANCE:
Acceptance will be made at destination by a Government representative.
Acceptance will be contingent upon the representative's verification of product and workmanship.
FOR OFFICIAL USE ONLY