This Statement of Work (SOW) outlines requirements for installing Kraft Faced R-38 Fiberglass Batt Insulation in the attic of the USCG Station Fire Island Multi-Mission Building. The contractor must install insulation at the bottom chord of trusses in four attic wings, covering approximately 6,240 total square feet (1,560 SF per wing), with 12" thick, 23" wide, R-38 rated insulation. The scope includes removal and disposal of existing insulation, with some wings currently having no insulation.

The work must be completed within 30 calendar days of contract issuance, with normal working hours from 7:00 AM to 4:30 PM Monday through Friday at 1 Rescue Road, Babylon, NY. The contractor must provide their own sanitation facilities and transportation, designate an on-site English-speaking supervisor, and maintain a one-year warranty on all work. The Coast Guard facility will remain operational during the work, requiring coordination with government operations. Site visits are strongly encouraged and can be arranged through SCPO Christopher Holmes, the Quality Assurance Inspector.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

FOR

USCG Station Fire Island Multi-Mission Building Install Batt Insulation for Attic in MMB

PR #

STATEMENT OF WORK

FOR

USCG Station Fire Island Multi-Mission Building Install Batt Insulation for Attic in MMB

GENERAL REQUIREMENTS

PART 1 – GENERAL

1.1 SCOPE: The Contractor shall provide all personnel, equipment, tools, materials, supervision, and other items and services necessary to install Kraft Faced R-38 Fiberglass Batt Insulation at the bottom chord of the trusses in the four attic wings of STA Fire Island Multi-Mission Building (MMB).

1.1.1 Work shall include providing all transportation, materials, and labor. The awarded contractor shall complete the following:

- Install Kraft Faced R-38 Fiberglass Batt Insulation at the bottom chord of the trusses in the Four attic wings.

- Approximately, 1560 SF/wing (6,240 SF approx. total) 12” Thick, 23” Wide, R-38.

- Removal and disposal of old insulation.

1.2 EXISTING CONDITIONS: Old insulation in attic needs to be replaced. Some of the attic wings have no insulation at all.

1.3 SITE VISITS: Bidders are strongly encouraged to inspect the site where work is to be performed to satisfy them regarding all general and local conditions that may affect the cost of contract performance, to the extent that the information is reasonably obtainable. In no event shall failure to inspect the site constitute grounds for a claim after contract award. Arrangements for such visits shall be made by contacting Quality Assurance Inspector (QAI) SCPO Christopher Holmes. Any questions regarding this specification or the work shall be addressed in writing and directed to the Contracting Officer.

1.4 LOCATION: 1 Rescue Road Babylon, NY 11702-4600

1.5 HOURS OF WORK: Normal working hours for the contract are 7:00 A.M. to 4:30 P.M., Monday through Friday. If the Contractor desires to work other than normal duty hours, on weekends or federal holidays, he/she must request written permission from the QAI at least 24 hours in advance of such work and approval must be received prior to the requested work time.

1.6 COORDINATION OF CONTRACT WORK WITH GOVERNMENT WORK: The Government will continue to operate within its buildings and areas during the execution of the contract. The Government will keep interference with the Contractor’s operation to a minimum. The Contractor shall conduct his/her operations so as not to interfere with the Governments operation of the facility.

1.7 SANITATION FACILITIES: To be provided by the contractor.

1.8 ON SITE SUPERVISION. Prior to commencing work, the Contractor shall submit a letter to the QAI, designating an employee from his/her company as the foreman or supervisor. The supervisor shall be on site any time work is being performed. The supervisor shall be able to read, write, speak English, and have the authority to approve and accept delivery orders and minor (under $2000.00) modifications to delivery orders.

1.9 PROTECTION OF PROPERTY: The Contractor shall comply with the requirements of Paragraph 52.236-9 and 52.236-10 of the Federal Acquisition Regulation and the following: All existing grounds, fences, utilities, equipment, building components and adjacent property, including vehicles, shall be protected from any damage resulting from contract operations. Contractors will be responsible for any damage to Government property. Damaged property (done by the Contractor) shall be repaired by the Contractor, at Contractor’s expense, to meet previous existing conditions.

1.9.1 The Contractor shall take all necessary precautions to meet proper safety standards and regulations of the State and Federal Codes. OSHA regulations apply to all work performed on site. In addition, they shall conform to any restrictions as may be outlined by the Base Safety Officer and Fire Department during the course of the contract.

1.10 DISPOSAL OF REMOVED MATERIALS: All material removed by the Contractor that is not indicated to be salvaged by the Government shall become the property of the Contractor. This material shall be disposed of legally off of Coast Guard property. The Contractor shall not cause, suffer, or permit the handling, transportation, or storage of any material in a manner that result, or may result in emissions that cause or contribute to a condition of air pollution, any debris that could create air-borne dust must be shipped in a closed container or wet down and securely tarped over. The Contractor is responsible to comply with all applicable federal, state and local environmental and disposal regulations.

1.11 RESTORATION AND CLEAN UP: All areas disturbed by construction shall be restored to match the condition and material that existed prior to the start of work. The contractor shall keep the work areas clean of trash and debris at all times. The contractor shall not allow trash or debris to blow from the work area.

1.12 UTILTIES: Electrical 110/120 V outlets are available, contractor responsible for providing extension cords.

1.13 GOVERNMENT INSPECTION: The Contractor shall keep the QAI informed of contract operations and plans so that they may arrange to be present at the various times that work is being performed. Inspector must be present for operation testing and pressure testing.

1.14 DRAWINGS: None.

1.15 PERFORMANCE PERIOD: All work under this contract including site cleanup, punch list, acceptance by the QAI and required submittals shall be completed within 30 calendar days of issuance of the contract by the Contracting Officer unless stated otherwise.

1.16 WARRANTY: The provisions of the entire warranty clause from paragraph 52.246-21 (April 84) and Federal Acquisition Regulation are incorporated into this contract. The clause is written, in part, as follows:

“In addition to any other warranties set out elsewhere in this contract, the Contractor shall warrant that work performed under this contract conforms to the contract requirements and is free of any defect of equipment, material, or design furnished or workmanship performed by the Contractor or any of his subcontractors or suppliers at any tier. Such warranty shall continue for a period of one year from the date of final acceptance of the work.”

POC’s:

Sector SLIS Facilities Eng CWO Anthony Graziano 757-646-3940