SOW_South Moorings_Fender_installation.docx

DOCX document 37 KB Posted

Attached to
Remove existing, prep area and install new pier side fenders
Solicitation number
70Z028-23-Q-MIAM0051
Issued by

View the file

Other files

File Type Posted
Enclosure (1) Fenders drawing.pdf PDF
Construction Clauses and Provisions.pdf PDF
fl139.txt TXT text file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF HOMELAND SECURITY

UNITED STATES COAST GUARD

U.S. Coast Guard Sector St. Petersburg 600 8th Ave SE St. Petersburg, FL 33701

STATEMENT OF WORK FOR THE

INSTALLATION OF MARINE FENDERS

AT

USCG SECTOR ST. PETERSBURG

ST. PETERSBURG, FL

April 11th, 2023

GENERAL REQUIREMENTS

PART 1 GENERAL

1. INTENT: The intent of this project is to replace 03 of the primary fenders, replace eye bolts and repair concrete as defined in this scope of work, located at US Coast Guard Sector St. Petersburg, 600 8th Ave SE, St. Petersburg, FL 33701

2. SCOPE OF WORK: Contractor shall provide all services necessary to install three (03) Fenders and associated hardware, remove and replace up to twenty-five (25) eye bolts, re-install secondary “D” type fenders and repair designated sections of concrete at the South Moorings of Sector St. Petersburg.

3. QUALIFICATIONS: Contractor shall provide personnel who have the knowledge, qualifications, and working experience to perform the functions outlined in the Performance Requirements and shall be licensed and certified marine contractors.

4. CONTINUITY OF FACILITIES OPERATION: Schedule work to minimize interference with the facility’s normal operations. Perform all on-site work between the hours of 8:00 AM and 4:00 PM, Monday through Friday (federal holidays excluded), unless otherwise approved by the Contracting Officer or Contracting officer’s representative.

1) GOVERNMENT FURNISHED MATERIALS (GFM):

Fenders: Government shall provide three (03) foam filled, standard capacity fenders that are 5 feet in diameter and 8 Feet long.

Hardware: Government shall provide the following associated hardware:

(a) QTY 4 per fender: 1” BTA Shackles

(b) QTY 2 per fender: 1” Stud link Chain HDG X 10’ long

(c) QTY 2 per fender: 12.5” X 12.5” Dock plate HDG

(d) QTY 8 per fender: 1-1/8” Anchor Rods, hex nuts and washers 5.

PART 2 PERFORMANCE STANDARDS

2. PERFORMANCE REQUIREMENTS: Contractor shall provide all services, labor and materials (in addition to GFM) to install 03 fenders as described above at the Coast Guard Sector St. Petersburg South Moorings. Installation shall comply with manufacturer’s specifications and be in accordance with all applicable local and international building codes and be in accordance with enclosure (1).

3. Contractor shall provide all services labor and materials, to prepare the surface of the wharf to receive the installation of the new fenders and hardware, including but not limited to the following: removal of existing hardware, repair of concrete surfaces and installation of any additional necessary hardware. All parts requiring replacing shall be appropriately sized, rated and designed use in a marine environment and shall meet the fender manufacturer’s recommended tolerances for mounting hardware.

4. Contractor shall provide services, materials, and labor to remove up to ten (10) existing damaged, missing, or unserviceable eye bolts. Contractor shall remove existing/remaining eye bolts, prepare, and repair the mounting surface and install new eyebolts.

A. Replacement eye bolts shall be installed in accordance with enclosure (1) B. Replacement eye bolts shall be ¾” Marine 316-Grade Stainless Steel

5. Contractor shall provide all materials labor and services to repair 03 locations of cracked and spalling concrete on the bulkhead cap to be identified onsite.

6. SITE VISIT: All site visits should be scheduled with the Contracting Officer, Facilities Engineer and/or their representative.

7. PERFORMANCE STANDARDS. Proper adherence to all OSHA and Industry safety procedures is required prior, during and after work being performed. The contractor shall furnish all personnel with and require donning of required personal protective equipment (PPE). The contractor shall safeguard the public and Government personnel, property, materials, supplies, and equipment exposed to contractor operations and activities, and avoid interruptions of Government operations in the performance of services.

CWO Jon Ruffner Email: Jonathan.d.ruffner@uscg.mil

(727) 824-7609

DCC Tim Bakels Email: timothy.g.bakels@uscg.mil

(772) 579-0587

8. LIABILITY OF DAMAGES. The contractor shall be liable for all damages to Government equipment and property when such damage is due to fault or negligence of the contractor. The contractor shall be responsible for all damages or injury to persons that occur as a result of the contractor’s fault or negligence. The contractor shall take proper safety and health precautions to protect the work the workers, the public, and the property of others.

END OF SECTION