SOW_Sitka_Replace_fuel line.pdf
PDF 153 KB Posted
- Attached to
- Fuel Line Pipe Replacement Federal contract opportunity
- Solicitation number
- 20280PR240010154
About this file
This document is a Statement of Work (SOW) for the replacement of fuel lines at U.S. Coast Guard Air Station Sitka in Sitka, Alaska. The SOW requires the contractor to replace existing supply fuel lines with stainless steel fuel lines from the 9 housing fuel tanks that feed the housing boilers, and to cap/abandon the return lines. The contractor will replace pipe bungs, pipe, and pipe hangers, and establish prime on the tiger loop in the boiler room. The government will provide the stainless steel pipe, unions, couplings, valves, and pipe bungs. The contractor shall complete the work within 60 days of contract award. The work must be scheduled to minimize interference with the facility's normal operations, and the contractor will be liable for any damages due to their fault or negligence.
The related federal contract opportunity is a Request for Quotation (RFQ) for the Fuel Line Pipe Replacement project in accordance with the SOW. This is a combined synopsis/solicitation for commercial items, set-aside for small businesses under NAICS code 238220 with a $19M size standard. Quotes are due by September 3, 2024 at 1:00 p.m. Alaska time. All contractual and technical questions must be submitted in writing by August 23, 2024 at 1:00 p.m. Alaska time.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 20280PR240010154 Solicitation 20240819.pdf | ||
| WD 2015-5685 Rev 23 20240722.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF HOMELAND SECURITY
UNITED STATES COAST GUARD
USCG AIRSTA SITKA, AK
SITKA, ALASKA 99835
Lifesaver Dr.
16 July 2024
STATEMENT OF WORK
FOR
U.S. COAST GUARD AIR STATION SITKA OWNED FAMILY HOUSING, FUEL LINES
REPLACEMENT ON ALL BOILER SERVICE TANKS.
PART 1 GENERAL
1.01 INTENT: to replace existing Supply fuel lines with Stainless Steel fuel lines from the
9 housing fuel tanks that feed to the housing boilers and cap/abandoned the return lines (no longer in use)
1.02 SCOPE: Contractor shall meet the desired outcome listed below and perform to the standards indicated.
A. Contractor will replace existing pipe bungs with Stainless Steel pipe bungs (bungs provided by the unit)
B. Contractor will replace existing pipe with Stainless Steel pipe from the bung up to the flexible hose in the vault pipe chase. (Pipe and fittings will be provided by the unit, pipe over 6” will need to be cut and threaded.)
C. Contractor will replace and pipe hangers with cushioned pipe hangers.
D. Contractor will establish prime on the tiger loop in the boiler room.
E. 15 total supply lines will be replaced in total.
F. Contractor will coordinate and provide methods to drain the fuel tanks as needed if bungs cannot be removed by hand.
1.03 REQUIREMENTS: Contractor shall provide personnel who have the knowledge;
qualifications and experience to perform the functions outlined in the Statement of Work. Contractor shall follow all OSHA and state environmental regulation as pertaining to this statement of work. The contractor shall also replace fuel lines on servicing fuel tanks in the following order of precedence. The priority fuel lines needing to be replaced would start at the servicing tank at unit 11, Fuel lines servicing units 1 & 2, Fuel lines servicing units 3 & 4, Fuel lines servicing units 9 & 10, Fuel lines servicing units 7 & 8, Fuel lines servicing unit 14, Fuel lines servicing unit 15, Fuel lines servicing units 5 & 6, and Fuel lines servicing units 12 & 13.
1.04 Unit: Contractor will provide cushioned style pipe hangers and necessary material and tools for successful fuel line installation and operation.
1.05 GOVERNMENT FURNISHED: The government shall provide the following.
A. Stainless Steel pipe, unions, couplings, valves, and pipe bungs.
1.06 CONTRACTOR FURNISHED: The contractor shall provide the following:
A. All labor, materials, cushioned pipe hangers, and supervision in order to accomplish the below requirements for replacing the fuel lines on 9 fuel tanks.
1.07 CONTRACT TIMELINE:
A. Upon contract award. Contractor will have 60 days to complete the work.
1.08 CONTINUITY OF FACILITIES OPERATION: Schedule work to minimize interference with the facilities normal operations. Notify the Facility Engineer 24 hours in advance of any shutdowns. Perform all on-site work between the hours of 8:00 AM and 4:00 PM, Monday through Friday (Federal Holidays excluded), unless otherwise approved by the Contracting Officer or Contracting officer’s Representative.
1.09 LIABILITY OF DAMAGES. The contractor shall be liable for all damages to Government equipment and property when such damage is due to fault or negligence of the contractor. The contractor shall be responsible for all damages or injury to persons that occur, as a result of the contractor’s fault or negligence. The contractor shall take proper safety and health precautions to protect the workers, the public, and the property of others.
1.10 POINT OF CONTACTS.
(a) AIRSTA Sitka Public Works Officer (COR): CWO Justin Critcher
619-727-0894, Justin.D.Critcher@uscg.mil
UNIT POC: DCC Logan Hughes
618-641-7484, Logan.W.Hughes@uscg.mil
(b) Contracting Officer as listed in award.
PART 2 INSPECTIONS AND ACCEPTANCE
2.01 Inspection: DCC Logan Hughes, contact number 618-641-7484, will accompany
Contractor for duration of service visit. Contractor will provide all required documentation for service visit at the conclusion of servicing.