SOW_Sitka_Replace_Carpet_Housing_AIRSTA 3 bedrooom unit 9C (1).docx
DOCX document 34 KB Posted
- Attached to
- USCG AIRSTATION SITKA CARPET AND INSTALLATION
- Solicitation number
- 70Z04524-Q-KODI0029
About this file
This document is a Statement of Work (SOW) for replacing the carpet in a 3-bedroom housing unit at the U.S. Coast Guard Air Station (AIRSTA) in Sitka, Alaska. The contractor is required to purchase and install new carpet, padding, and transitions in the stairway, upstairs hallway, and three bedrooms, covering approximately 630 square feet. The government will remove and dispose of the existing carpet and prepare the substrate for the new installation. The contractor must complete the work within 90 days of contract award. The work must be scheduled to minimize interference with the facility's normal operations. The contractor will be liable for any damages to government equipment or property and must follow all relevant safety and environmental regulations. The Point of Contact for this work is the AIRSTA Sitka Public Works Officer.
The related federal contract opportunity is a Request for Quotation (RFQ) for the USCG AIRSTATION SITKA CARPET AND INSTALLATION, with a Solicitation Number of 70Z04524-Q-KODI0029. The government estimate for this requirement is less than $8,000. The acquisition is set aside 100% for small businesses, and the NAICS code is 238330 Flooring Contractors. Quotes are due by 2 pm Alaska Time on February 10, 2024, and should be submitted via email to the Contracting Specialist.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Service Contract Act WD 2015-5685.txt | TXT text file | |
| RFQ SF-18 Sitka carpet.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF HOMELAND SECURITY
UNITED STATES COAST GUARD
USCG AIRSTA SITKA, AK
SITKA, ALASKA 99835
Units 9C Lifesaver Dr.
DAY MONTH 2024
STATEMENT OF WORK
FOR
SITKA, REPLACE CARPET, HOUSING AIRSTA
PART 1 GENERAL
1.01 INTENT: Installation of carpet and carpet padding unit(s) 9C Lifesaver Dr. Sitka AK 99835
1.02 SCOPE: Contractor shall meet the desired outcome listed below and perform to the standards indicated.
A. Contractor is to purchase the carpet, padding, and transitions.
B. Contractor is to install new padding, carpet, and transitions without damaging baseboards, cove base, walls, or baseboard heating.
C. After inspection, contractor /vendor shall receive payment.
1.03 REQUIREMENTS: Contractor shall provide personnel who have the knowledge; qualifications and experience to perform the functions outlined in the Statement of Work. Contractor shall follow all OSHA and state environmental regulation as pertaining to this statement of work.
1.04 Unit(s) ##: Provide and install 630 square feet of carpet with Hard at Play III 502 shadow or equivalent Carpet and 8# Rebond carpet padding or equivalent. Installation will be on stairway, upstairs hallway, bedroom one, bedroom two, and bedroom three. Provide and install brushed nickel finished metal transitions from hallway to all bordering rooms.
1.05 GOVERNMENT FURNISHED: The government shall provide the following.
A. Remove and dispose of existing carpet.
B. Prepare substrate for new carpet installation.
1.06 CONTRACTOR FURNISHED: The contractor shall provide the following:
A. All labor, materials, and supervision in order to accomplish the below requirements for removal installation of new carpet, padding, and transitions.
1.07 CONTRACT TIMELINE:
A. All materials ordered within 14 days of award.
B. Contract will be completed 90 Days, or less after award.
1.08 CONTINUITY OF FACILITIES OPERATION: Schedule work to minimize interference with the facilities normal operations. Notify the Facility Engineer 24 hours in advance of any shutdowns. Perform all on-site work between the hours of 8:00 AM and 4:00 PM, Monday through Friday (Federal Holidays excluded), unless otherwise approved by the Contracting Officer or Contracting officer’s Representative.
1.09 LIABILITY OF DAMAGES. The contractor shall be liable for all damages to Government equipment and property when such damage is due to fault or negligence of the contractor. The contractor shall be responsible for all damages or injury to persons that occur, as a result of the contractor’s fault or negligence. The contractor shall take proper safety and health precautions to protect the workers, the public, and the property of others.
1.010 POINT OF CONTACTS.
(a) AIRSTA Sitka Public Works Officer (COR): CWO Justin Critcher 619-727-0894, Justin.D.Critcher@uscg.mil UNIT POC: DCC Logan Hughes 618-641-7484, Logan.W.Hughes@uscg.mil
(b) Contracting Officer as listed in award.
PART 2 INSPECTIONS AND ACCEPTANCE
2.01 Inspection: DCC Logan Hughes, contact number 618-641-7484, will accompany Contractor for duration of service visit. Contractor will provide all required documentation for service visit at the conclusion of servicing.