This is a Scope of Work (SOW) document for the United States Coast Guard Sector San Diego, located at 2170 N. Harbor Drive, San Diego, California, addressing comprehensive renovations to the Aircrew Duty Berthing Room in Building D. The project encompasses multiple renovation phases including lighting system upgrades with LED fixtures featuring dimmable and red-light modes across six sleeping rooms, one central hallway, and one bathroom; complete bathroom renovation including installation of commercial-grade fixtures, new sheet vinyl flooring, and waterproofing; installation of approximately 590 square feet of Luxury Vinyl Plank flooring throughout crew berthing spaces with new baseboards and trim; and interior painting of six sleeping rooms and common passageways. The contractor is responsible for all demolition of existing materials, disposal, installation of new fixtures, electrical modifications, plumbing connections, wall repairs, and finishing work while ensuring compliance with local and federal building codes.
The contract is a Total Small Business Set-Aside in the Residential Remodelers category (NAICS 236118) and requires the contractor to provide all necessary personnel, equipment, supplies, transportation, tools, materials, and supervision. A critical asbestos safety note indicates that no asbestos was detected in the berthing room during environmental assessment (AESS Job No. 26-092), though the document references that lead was detected at very low concentration, with additional safety protocol information appearing to be incomplete in the provided documentation.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOW FOR SECTOR SAN DIEGO:
AIRCREW DUTY BERTHING
RENOVATIONS
1.0 GENERAL
1.1 Scope of Work
The contractor shall provide all personnel, equipment, supplies, transportation, tools, materials, and supervision necessary to perform complete renovations of the
Aircrew Duty Berthing Room in Building D at Sector San Diego.
1.2 Place of Performance
USCG Sector San Diego: 2170 N. Harbor Drive, San Diego, California 92101
2.0 SPECIFIC REQUIREMENTS/TASKS
2.1 Itemized List of Work
The table below specifies both the removal/demolition scope and the new installations to be executed within the Aircrew Duty Berthing Room:
Phase / Category
Task Type Itemized Description Location / Quantity
Lighting Renovation
Demolition Remove and properly dispose of all existing light fixtures.
6 Sleeping Rooms, 1 Central Hallway, 1 Bathroom
Lighting Renovation
Installation Replace previous light fixtures with new LED fixtures (fully dimmable, selectable red-light mode).
6 Sleeping Rooms, 1 Hallway, 1 Bathroom
Lighting Renovation
Electrical Install required switches, controls, wiring modifications, and associated hardware.
All designated spaces
Lighting Renovation
Finishing Repair and finish any wall or ceiling surfaces disturbed during installation.
All designated spaces
Lighting Renovation
Verification Verify proper operation of white-light, dimming, and red-light functions.
All designated spaces
Bathroom Renovation
Demolition Remove toilet, sink/vanity, mirror, shower pan, tile flooring, and vinyl splash guards.
Bathroom
Bathroom Renovation
Installation Furnish and install new commercial-grade toilet, sink/vanity (with enclosed under-sink storage), mirror, shower pan, new low-maintenance sheet vinyl flooring
Bathroom
Bathroom Renovation
Finishing Repair and refinish wall surfaces where splash guards were removed; seal and waterproof all surfaces.
Bathroom
Bathroom Renovation
Verification Ensure all plumbing fixtures are operational and free of leaks.
Bathroom
Flooring Installation
Demolition Remove existing carpet throughout crew berthing spaces.
~590 sq ft
Flooring Installation
Installation Install Luxury Vinyl Plank (LVP) flooring material.
~590 sq ft
Flooring Installation
Finishing Install new baseboards and trim as required.
Throughout berthing spaces
Interior Painting
Finishing Prepare and paint interior walls and trim.
6 Sleeping Rooms, Common Passageway
Ensure that all new fixtures are properly connected to existing water, sewage, and electrical systems, adhering to local and federal building codes.
2.2 Demolition & Hazardous Material Handling
• CRITICAL ASBESTOS SAFETY NOTE:
No asbestos was detected in the Berthing Room in Building D (AESS Job No.
26-092).
• LEAD SAFETY NOTE: AL ASBESTOS SAFETY NOTE:
Lead was detected at a very low concentration of <0.00146% by weight for the NW floor, <0.0039% by weight for the NW wall, and <0.00349% by weight for the N wall of the Berthing Room in Building D (AESS Job No. 26-
092). While these concentrations are well below the EPA/HUD threshold for
Lead-Based Paint (LBP) of 0.5% (5,000 ppm), any detectable level of lead triggers Cal/OSHA Lead in Construction Standard (8 CCR § 1532.1) compliance.
Final Clean-up & Waste Characterization
Maintain clean containment zones daily. Upon completion, perform a final detailed cleanup of all work areas.
• Surface Protection: The contractor shall protect all adjacent surfaces, hallways, pathways, and building furniture during all prep, painting, and construction phases.
• Debris Removal: The contractor shall remove all construction debris, empty paint cans, masking materials, and surplus tools from the site immediately upon project completion.
• Paint & Splatter Prevention: The contractor shall leave the final work area professionally cleaned and completely free of grout haze, dust, adhesive spills, or paint drips, runs, splatters, and residue.
• LEAD DEBRIS NOTE: Debris and waste generated from the removal of the lead-containing material must be evaluated for appropriate disposal classification (such as Toxicity Characteristic Leaching Procedure (TCLP) or
Total Threshold Limit Concentration (TTLC) waste characterization) prior to disposal, consistent with California hazardous waste regulations. All waste must be legally disposed of off-site. Government dumpsters shall not be used.
2.3 Unexpected Hazardous Materials Protocol
If, during the performance of work under this contract, the contractor encounters any previously unidentified material that is suspected to be hazardous (including, but not limited to, lead, asbestos, heavy metals, or toxic chemical residue) outside of the areas already documented in the provided survey report (AESS Job No. 26-092), the contractor shall:
1. Immediately halt work in the affected area and secure the immediate vicinity to prevent personnel exposure or disturbance of the suspect material.
2. Implement appropriate local controls to isolate the area.
3. Notify the Unit Point of Contact (POC) and the Contracting Officer (KO) verbally within four (4) hours, followed by written notification within twenty-four (24) hours.
4. Do not resume work in the affected area until the material has been formally tested, characterized, and certified safe, or until proper abatement is completed and the Contracting Officer issues written authorization to proceed.
3.0 CONTRACTOR PERSONNEL
3.1 Qualifications
All plumbing, electrical, tile-setting, and mechanical work must be performed by licensed, qualified professionals in accordance with California state and local codes.
3.2 Base Access
Contractor personnel must comply with all USCG Sector San Diego security requirements and maintain a professional demeanor. All personnel must have a
REAL ID Act compliant form of identification to enter the facility. Vehicles must have valid registration and insurance, and vehicle operators must have a valid driver license.
3.3 Safety Requirements
The contractor shall strictly adhere to all applicable safety standards, including:
• Implementation of proper active mechanical ventilation to safeguard both workers and station personnel.
• Full compliance with federal and state OSHA regulations.
• Mandatory and correct use of task-specific Personal Protective Equipment
(PPE), including but not limited to respiratory protection, safety goggles, gloves, and protective suits.
3.4 Contractor Responsibilities
The contractor shall:
• Provide valid proof of business insurance (general liability, workers' compensation) and all applicable professional and trade licenses to the
Contracting Officer prior to contract award.
• Mobilize all necessary equipment, supplies, and personnel to the work site to safely execute the bathroom remodeling project.
• Ensure all on-site workers are fully certified, trained, and qualified for the specific tasks they are assigned.
• Communicate regularly with the designated Project Manager (PM) regarding project milestones, timeline progression, and any issues or field changes.
4.0 PERIOD OF PERFORMANCE
The period of performance shall be 60 days from the date of the Notice to Proceed
(NTP).
5.0 HOURS OF OPERATION / SCHEDULE
The contractor shall perform all work during normal Sector business hours (0800 to
1700, Monday through Friday, excluding Federal Holidays) unless authorized by the
Contracting Officer. Any disruption to water, power, or gas must be coordinated with the Facility Manager at least 72 hours in advance.
6.0 GOVERNMENT FURNISHED RESOURCES
Contractor will provide all materials to furnish and complete all necessary work required to perform this SOW. The government will provide electricity, parking, and laydown area as available from the unit.
7.0 GOVERNMENT ACCEPTANCE PERIOD
Upon completion, the Government and Contractor will conduct a joint walkthrough to inspect, and test installed fixtures, flooring, and tiles to verify compliance with project specifications and quality standards. The Government will have five (5) business days to inspect the space and issue a “Punch List.” Final acceptance occurs when the KO confirms all punch list items are resolved.
8.0 INVOICING
In conjunction with the subject award, proper invoices will be submitted through the Invoice Processing Platform (IPP) website (www.ipp.gov). IPP is a secure web-based electronic invoicing system provided by the U.S. Department of the Treasury’s
Bureau of the Fiscal Service in partnership with the Federal Reserve Bank of St.
Louis (FRSTL).
IPP is available at no cost to any commercial vendor or independent contractor doing business with a participating government agency.
http://www.ipp.gov/
Actions to Take:
• If you are already enrolled in IPP: If your company is already registered to use IPP, you will not be required to re-register and you do not need to contact IPP.
• If you are NOT already enrolled in IPP: The point of contact you provided in your SAM.gov registration will receive two emails from ipp.noreply@mail.eroc.twai.gov:
1. The first email will have the IPP Logon ID and a link to the IPP application.
2. A second email, sent within 24 hours of the first, contains a temporary password.
Once registered, your company may submit invoices electronically, receive email notifications when requests are paid, view payment history, and access remittance downloads.
• Support & Training: Vendor training materials, including a first-time login tutorial, are available on the IPP website (www.ipp.gov).
• Toll-free number: 866-973-3131
• Email address: IPPCustomerSupport@fiscal.treasury.gov
• Hours of operation: Monday through Friday (excluding bank holidays) from 8:00 am - 6:00 pm ET
9.0 ADDITIONAL NOTES
• Written Scope Changes: Any changes, alterations, additions, or deductions to this Scope of Work must be formally approved in writing by the Contracting
Officer (KO) and the Project Manager (PM) through official contract modification.
• Disruption Minimization: The contractor shall coordinate all utility disruptions, dust-heavy work, or loud operations with the Facility Manager in advance, and make every concerted effort to ensure minimal disruption to the building occupants, active-duty personnel, and daily emergency response operations of USCG Sector San Diego.