This is a Statement of Work (SOW) for roof replacement services at a U.S. Coast Guard facility. The project involves replacing an existing single-ply roof system with a new EPDM (ethylene propylene diene monomer) rubber membrane roofing system at 5378 Lindberg Street, USCG Base Cape Cod, in Bourne, Massachusetts 02542. The work must be completed within 45 calendar days of the Notice to Proceed issuance. The contractor must provide all personnel, equipment, tools, materials, and supervision necessary for complete installation.
Key scope requirements include: removing and disposing of existing roofing materials in compliance with federal, state, and local regulations; installing ½" perimeter edge nailer and tapered insulation board system; applying a fully adhered .060" EPDM membrane; installing new drain covers, fascia system, and drip edges; replacing chimney aluminum flashing and flues; fabricating and installing .032" thickness 5" white aluminum edge metal; and completing 192 square feet of plywood sheathing repair and 20 linear feet of soffit vent repair with unit pricing provided for additional work. Work hours are 7:00 A.M. to 4:00 P.M. Monday through Friday, excluding federal holidays, unless written permission is granted for extended hours. All contractor personnel must pass National Crime Information Center (NCIC) background checks, submit personnel information seven calendar days prior to access, and maintain valid Real ID driver's licenses. The contractor must comply with OSHA regulations, fire safety standards, hazardous materials procedures, and environmental disposal requirements including submission of bills of lading and landfill receipts. The contractor provides a one-year warranty on all work performed from the date of final acceptance.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| DBA WAGES BARNSTABLE COUNTY.txt | TXT text file | |
| FAR CLAUSES TO INCORP.docx | DOCX document | |
| SF1449-21 SOLICITATION.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK FOR 5378 LINDBERG ROOF REPLACEMENT
BASE CAPE COD
JULY 16, 2026
SECTION 01010
GENERAL REQUIREMENTS
PART 1 – GENERAL
SCOPE: The Contractor shall provide all personnel, equipment, tools, materials, supervision, and other items and services necessary to install a new EPDM roof system over the existing roofing systems at 5378 Lindberg Street at USCG Base Cape Cod Housing units in Bourne, MA 02542.
1.1.2 REQUIRED WORK: This list should not be considered complete. It represents the general items needed to complete the contract requirements.
The Contractor shall replace the existing single ply roof system with new EPDM roofing systems.
The Contractor shall verify the roofing square footage prior to procurement of any materials.
The Contractor shall protect the building, property, and occupants during demolition and construction.
The Contractor shall remove and dispose of all roofing materials in accordance with all Local, State, and Federal regulations.
The Contractor shall install ½” perimeter edge nailer.
The Contractor shall include 192 square feet of plywood sheathing repair and provide square foot unit pricing for additional.
The Contractor shall include 20 linear feet of soffit vent repair and provide linear foot unit pricing for additional.
The Contractor shall install all new tapered insulation board system mechanically fastened with deck plates and screws.
The Contractor shall install a new fully adhered .060 EDPM rubber membrane roofing system to the existing deck.
The Contractor shall install all new drain covers, fascia system, drip edges, and other accessories and components needed for a complete watertight installation.
The Contractor shall replace all chimney aluminum flashing, and flues.
The Contractor shall flash around all penetrations in accordance with manufacturers specifications.
The Contractor shall fabricate and install .032 thickness 5” white aluminum edge metal along the perimeter of the roof.
1.2 SITE VISITS: Bidders are strongly recommended to inspect the site where work is to be performed to satisfy them regarding all general and local conditions that may affect the cost of contract performance, to the extent that the information is reasonably obtainable.
In no event shall failure to inspect the site constitute grounds for a claim after contract award. Arrangements for such visits shall be made by contacting the COR, any questions regarding this specification or the work shall be addressed in writing and directed to the Contracting Officer.
1.3 LOCATION: Work will be performed at 5378 Lindberg Street, located on Joint Base Cape Cod, Buzzards Bay, MA 02542.
1.4 HOURS OF WORK: Normal working hours for the contract are 7:00 A.M. to 4:00 P.M., Monday through Friday (excluding Federal Holidays). If the Contractor desires to work other than normal duty hours, on weekends or federal holidays, he/she must request written permission from the Contracting Officer at least 36 hours in advance of such work and approval must be received prior to the requested work time. The Contractor shall coordinate the work schedule and all work with the COR. The Contractor shall not make any attempt to access any work areas without prior arrangements with the COR.
1.5 PRECONSTRUCTION CONFERENCE: Upon award of the contract and prior to starting the project, the Contractor shall attend a pre-construction conference with the Contracting Officer to ensure a complete understanding of the project. The Contractor shall pay for all expenses incurred by him in this regard. All questions shall be resolved and confirmed in writing if required.
1.6 SECURITY REQUIREMENTS: All Contractor personnel scheduled to work on JBCC shall be subject to a National Crime Information Center (NCIC) background check to gain access through the Base security gates. To process the NCIC background check, all Contractors shall provide the following information: name, citizenship, drivers’ license state and number, and date of birth. The NCIC form shall be filled out by the Contractor, listing all personnel that require access to JBCC; form shall be submitted to the COR for processing at least 7 calendar days prior to the date of access.
1.6.1 Contractor’s vehicles shall have a valid and current proof of insurance and vehicle registration. The drivers and passengers shall have a valid Real ID driver’s license. All Contractor vehicles must enter the Base through the main gate on the Bourne side of the Base property.
1.7 REMOVAL OF CONTRACTOR EMPLOYEES: All employees of the Contractor in the performance of this contract, or any representative of the Contractor entering the worksite, shall abide by all applicable regulations and shall submit to security checks as may be deemed necessary. The Government reserves the right to direct the Contractor to remove from the performance under this contract, any employee, for misconduct or security reasons. This shall not relieve or constitute an excuse from the contract performance.
Upon dismissal the employee shall render all identification for entry to the worksite.
1.8 SCHEDULE OF WORK: After receiving the notice to proceed, the Contractor shall submit a Schedule of Work on the Government furnished form or other form approved by the Contracting Officer. The Contractor shall not commence work under this contract without receiving a copy of the signed, approved schedule.
1.9 LABOR & DAILY LOGS: All personnel shall be skilled and have sufficient knowledge and experience necessary to perform work assigned to them. The Contractor shall complete the Base Cape Cod daily log form at the end of each working day and deliver weekly to the COR. The Government will attest to its accuracy by initialing the form and providing a copy back to the Contractor.
1.10 SAFETY: The Contractor shall take all necessary precautions to meet proper safety standards and regulations of the State and Federal Codes. OSHA regulations apply to all work performed on site. In addition, the Contractor shall conform to any restrictions as may be outlined by the Base Safety Officer and Fire Department during the contract. Prior to doing any welding or burning with a torch the Contractor shall obtain a “hot work” permit from the USCG FED Safety Office.
1.10.1 FIRE SAFETY: All requirements per Joint Base Cape Cod Fire Prevention Standard 911-1 shall be followed. A copy of the instruction will be provided upon request.
1.11 ON SITE SUPERVISION: The Contractor shall provide qualified supervision when work is being conducted by Contractor employees or Sub-Contractor employees. Prior to commencing work, the Contractor shall submit a letter to the Contracting Officer designating an employee from his/her company as the foreman or supervisor. The supervisor shall be on site any time work is being performed. The supervisor shall be able to read, write, speak English, and have the authority to approve and accept delivery orders and minor (under $2000.00) modifications to delivery orders.
1.12 PROTECTION OF PROPERTY: The Contractor shall comply with the requirements of Paragraph 52.236-9 and 52.236-10 of the Federal Acquisition Regulation and the following:
All existing grounds, fences, utilities, equipment, building components and adjacent property, including vehicles, shall be protected from any damage resulting from contract operations. Contractors will be responsible for any damage to Government property.
Damaged property (done by the Contractor) shall be repaired by the Contractor, at Contractor’s expense, to meet previous existing conditions.
1.13 HAZARDOUS MATERIAL: The Contractor shall be solely responsible for all Contractor generated or owned hazardous materials. While performing work Specific herein, if potentially hazardous materials are utilized a SD will be submitted to the COR prior to its use. If the hazardous materials are encountered, the Contractor shall notify the COR immediately. The Contractor’s responsibility for handling hazardous material is incidental to work performed, i.e., the Contractor shall handle, remove, and properly dispose of only those hazardous materials necessary to complete the contract work.
1.13.1 Any commercial adhesives, sealants, adhesive primers, sealant primers, and associated surface preparation and cleanup solvents in containers greater than a net volume of 16 fluid ounces, or a net weight of one pound shall not exceed volatile organic compounds (VOC) limits as established in the Massachusetts Department of Environmental Protection promulgated Adhesives and Sealants regulations, 310 CMR 7.18(30)."
1.14 DISPOSAL OF REMOVED MATERIALS: Dumpsters placed on site require a permit.
Permits are obtained from the USCG FED Safety Office. All material removed by the Contractor that is not indicated to be salvaged by the Government shall become the property of the Contractor. This material shall be disposed of legally off Joint Base Cape Cod property. The Contractor shall not cause, suffer, or permit the handling, transportation, or storage of any material in a manner which results, or may result in emissions that cause or contribute to a condition of air pollution, any debris which could create air-borne dust must be shipped in a closed container or wet down and securely tarped over. The Contractor is responsible to comply with all applicable federal, state, and local environmental and disposal regulations. The Contractor shall submit to the COR the following:
1.14.1 Bill of lading for all disposed materials.
1.14.2 Copy of landfill receipts.
1.14.3 Recyclers operating permit.
1.15 SUBMITTAL DESCRIPTION: Samples, catalog cuts, shop drawings, and other information shall be submitted by the Contractor as required by the list of submittals on the Submittal Register Form(s) which is included in this specification. No other forms shall be used or will be accepted by the COR
1.15.1 The Contractor shall submit a list of all hazardous materials with Safety Data Sheets (SDS) to the COR for approval prior to work commencement on this project. Storage of hazardous materials will not be permitted on Joint Base Cape Cod property.
1.15.2 All materials used by the Contractor shall comply with VOC Emission limits for use in the Commonwealth of Massachusetts (310 CMR 7.00). Cleaning and maintenance of the Contractor's and Sub-Contractor's equipment shall not be conducted on Joint Base Cape Cod property.
1.15.3 The Contractor shall ensure that adequate protective measures are taken to minimize personnel exposure to harmful substances. If protective measures are required, the Contractor shall include them in a Safety Plan, and they shall be reviewed by the Contracting Officer prior to the start of any contract work involving use of the harmful substance.
1.16 RESTORATION AND CLEAN-UP: All areas disturbed by construction shall be restored to match the condition and material that existed prior to the start of work. The Contractor shall always keep the work areas clean of trash and debris. The Contractor shall not allow trash or debris to blow from the work area.
1.17 GOVERNMENT INSPECTION: The Contractor shall keep the COR informed of contract operations and plans so that they may arrange to be present at the various times that work is being performed.
1.18 PERFORMANCE PERIOD: All work under this contract including site cleanup, punch list, acceptance by the COR and required submittals shall be completed within (45) calendar days of issuance of the Notice to Proceed (NTP) by the Contracting Officer unless stated otherwise.
1.19 WARRANTY: The provisions of the entire warranty clause from paragraph 52.246-21
(April 84) and Federal Acquisition Regulation are incorporated into this contract. The clause is written, in part, as follows:
“In addition to any other warranties set out elsewhere in this contract, the Contractor shall warrant that work performed under this contract conforms to the contract requirements and is free of any defect of equipment, material, or design furnished or workmanship performed by the Contractor or any of his Sub-Contractors or suppliers at any tier. Such warranty shall continue for a period of one year from the date of final acceptance of the work.”
END OF GENERAL SECTION