This is a Statement of Work (SOW) for the replacement of roll-up doors at the U.S. Coast Guard Maintenance Augmentation Team (MAT) facility in Pascagoula, Mississippi, with work scheduled for August 2026.
The contractor shall remove, dispose of, and replace one 12' x 12' steel roll-up door and associated components located in Building 100. The replacement door must be steel, non-insulated, wind-loaded, primed white rolling service door curtains with operator that meets all specifications of the current door, along with all necessary associated hardware for proper long-term industrial operation. The contractor must furnish all labor, tools, materials, transportation, equipment, supervision, and personnel required to complete the work. Personnel performing the work must have knowledge and working experience in roll-up door operation, maintenance procedures, and regulatory requirements. All on-site work shall be performed between 8:00 AM and 4:00 PM, Monday through Friday (excluding federal holidays), unless otherwise approved by the Contracting Officer. Following installation, a full operational test must be performed in the presence of a U.S. Coast Guard representative prior to final acceptance. Site visits must be scheduled with the Contracting Officer and Facilities Engineer, and all personnel require a TWIC, military, or REAL ID. The contractor is liable for all damages to Government equipment and property resulting from contractor fault or negligence and must adhere to all safety procedures and provide required personal protective equipment (PPE) to personnel. The point of contact is Mike Ackiss at Carlton.M.Ackiss@uscg.mil.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SF1442 ROLL UP DOOR.pdf | ||
| Wage Determination Pascagoula MS.pdf | ||
| Construction Clauses Roll up Door.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF HOMELAND SECURITY
UNITED STATES COAST GUARD
U.S. Coast Guard MAT Pascagoula
104 USS Vicksburg Way Pascagoula, MS 39595
STATEMENT OF WORK FOR THE
REPLACEMENT OF ROLL UP DOORS
AUG 2026
GENERAL REQUIREMENTS
PART 1 GENERAL
1. INTENT: The intent of this project is to remove, dispose of, and replace one (1) roll up doors and associated components on Building 100 and ensure proper operation.
2. SCOPE OF WORK: Contractor shall furnish all labor, tools, materials, transportation, equipment, supervision, and personnel to remove existing, dispose of, and replace one roll-up door located at U.S. Coast Guard Maintenance Augmentation Team (MAT), Building 100, Pascagoula, MS. No repairs outside of the Statement of Work criteria are authorized without permission from the contracting officer or their representative.
3. QUALIFICATIONS: Contractor shall provide personnel who have the knowledge, qualifications, and working experience to perform the functions outlined in the Performance Requirements. All personnel shall have at a minimum an understanding of operation, maintenance procedures, and regulatory requirements associated with roll-up doors.
4. CONTINUITY OF FACILITIES OPERATION: Schedule work to minimize interference with the facilities normal operations. Perform all on-site work between the hours of 8:00 AM and 4:00 PM, Monday through Friday (federal holidays excluded), unless otherwise approved by the Contracting Officer or Contracting officer’s representative.
5. GOVERNMENT FURNISHED MATERIALS: None
PART 2 PERFORMANCE STANDARDS
1. PERFORMANCE REQUIREMENTS: Contractor shall provide services to remove, dispose of, and replace one steel, 12’ x 12’, roll up door at USCG MAT Pascagoula, MS, as identified below. All replacements shall be in kind with current door and shall comply with manufacture’s specifications. All maintenance will be completed IAW the Manufactures requirements.
1) Removal:
a. Remove one 12’ x 12’ roll up steel curtains and all associated equipment.
b. Dispose of all equipment off-site.
2) Replacement: Provide and Install:
a. One (1) 12’ x 12’ steel, non-insulated, wind loaded, Primed White rolling service door curtains with operator. Replacement will meet all specifications of current door.
b. All other associated hardware necessary for proper, long term, industrial operation.
3) Testing:
a. Full operational test will be performed in the presence of U.S. Coast
Guard representative prior to final acceptance of work.
2. SITE VISIT: All site visits should be scheduled with the Contracting Officer, Facilities Engineer and/or their representative and are highly encouraged. All personnel coming on site require a TWIC, military or REAL ID.
3. PERFORMANCE STANDARDS. Proper adherence to all safety procedures is required prior, during and after work being performed. The contractor shall furnish all personnel with and require donning of required personal protective equipment (PPE). The contractor shall safeguard the public and Government personnel, property, materials, supplies, and equipment exposed to contractor operations and activities, and avoid interruptions of Government operations in the performance of services.
4. POINT OF CONTACT:
Mike Ackiss Carlton.M.Ackiss@uscg.mil
5. LIABILITY OF DAMAGES. The contractor shall be liable for all damages to
Government equipment and property when such damage is due to fault or negligence of the contractor. The contractor shall be responsible for all damages or injury to persons that occur as a result of the contractor’s fault or negligence. The contractor shall take proper safety and health precautions to protect the work the workers, the public, and the property of others.
END OF SECTION