This announcement is for a solicitation from the US Army Corps of Engineers Europe District seeking design-build proposals for renovation of the Riga Fire and Rescue Station in Riga, Latvia. The project includes renovating the existing basement into showers and lockers, renovating the former canteen into an equipment maintenance area, and resurfacing asphalt surfaces. Interested offerors must attend an optional pre-proposal site visit on January 13, 2023 and submit both price and non-price proposals by the deadline specified in the solicitation. The project is located at the provided latitude and longitude in Riga. The solicitation and its attachments on SAM.gov contain the design criteria and full statement of work. Companies must be registered in SAM to be eligible for award.

View the file

Other files

File Type Posted
Att11_Commitment Letters.docx DOCX document
Att6_Dedication Plaque.pdf PDF
Att5_Structural Calculations Guideline.pdf PDF
Att4_Existing Elevations.pdf PDF
Att12_Price and Bid Schedule.docx DOCX document
W912GB23R0018 Riga Fire Station_final.pdf PDF
Att3_Proposed Floor Plans.pdf PDF
Att2_Conceptual Site Plan.pdf PDF
Att9_BLA Template.docx DOCX document
Att7_Specs Binder IEU-23-0004 Riga Fire Station.pdf PDF
Att1_Project Location Map.pdf PDF
Att10_BLG Template.docx DOCX document
Att8_Site Visit Registration Spreadsheet.xlsx XLSX spreadsheet
Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Army Corps of Engineers Europe District

APO AE 09049

lt19

Statement of Work Project Number:

Project No.: 67225 Fiscal Year: 2022

Renovate Fire and Rescue Station Riga, Latvia

Prepared by:

Design Section

Engineering Branch

04NOV2022

01 10 10 Statement of Work Renovate Fire and Rescue Station

4-Nov-22 Page 2 of 49

SECTION 01 10 10

STATEMENT OF WORK

SECTION TABLE OF CONTENTS:

1 GENERAL

2 CIVIL AND GEOTECHNICAL

3 ARCHITECTURAL

4 STRUCTURAL

5 ELECTRICAL & COMMUNICATIONS

6 MECHANICAL & PLUMBING

ATTACHMENTS

Attachment # 1 Location Map Attachment # 2 Conceptual Site Plan Attachment # 3 Conceptual Floor Plans Attachment # 4 Existing Elevations Attachment # 5 Structural Calculations Guideline Attachment # 6 Dedication Plaque

1.0 GENERAL

1.1 PROJECT DESCRIPTION

The Request for Proposal (RFP) provides parameters for a design-build project for renovation of Riga Fire and Rescue Station in Riga, Latvia; UTM Latitude 56°55'19.6"N, Longitude 24°11'24.3"E (Refer to the attached Location Map.)

Renovate of the basement to allow for showers and locker storage for the existing and future fire fighters. Renovate existing canteen to create a storage, repair, and maintenance area for protective equipment.

The project includes the following general items of work, detailed requirements are contained elsewhere in this Statement of Work:

a. Renovate existing basement for showers and lockers

b. Renovate former canteen/cafeteria for equipment maintenance

c. Resurface existing asphalt drive and parking areas

1.2 GENERAL REQUIREMENTS

The Contractor must deliver fully functional, turnkey type facilities (without mobile furniture) as described in this document. The work includes - but is not limited to - design, demolition, fabrication, delivery, installation, construction, and site work.

The facility in this project must be complete and usable to meet codes and technical and functional requirements per this Statement of Work (SOW). The proposal price must include all design, calculations, approvals, certificates, fees, labor, material, equipment, direct overhead, indirect overhead, general and administrative expenses (G&A) and general conditions to complete this project as described in the SOW.

These design and product requirements are minimum requisites. Compliance with the provisions of this section by subcontractors is the responsibility of the Contractor.

1.2.1 BASE ITEMS AND OPTIONAL ITEMS

This Statement of Work addresses the technical requirements necessary to complete all work associated with this project. For information and requirements regarding

4-Nov-22 Page 3 of 49 the allocation of pricing between elements of the work, refer to Specification Section 01 22 00 PRICE AND PAYMENT PROCEDURES. The Schedule of Items identifies the breakdown between the individual base items and optional items for all work identified in this Statement of Work, associated drawings, and attachments. All work as described in these documents is included in either the Base or Optional Items. Consider all items not specifically identified in the Optional Items as part of the Base Items.

1.3 FUNCTIONAL AREAS

Refer to the attached drawings for a depiction of the required functional areas and spatial adjacencies for the site and new facilities/structures.

1.4 SUBMITTALS

Designer of Record approval is required for submittals with a “DA” designation.

Government approval is required for submittals with a “G” or “GA” designation.

Submittals having an “FIO” designation are for Contractor Quality Control approval. Submit the following to the Contracting Officer (KO) in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Demolition Plan; G

Sequencing Plan; G

SD-05 Design Data

65% Pre-Final Design; DA/GA

95% Final Design; DA/GA

100% Corrected Final Design; DA/GA

SD-06 Test Reports

Test Results and Reports; FIO

1.4.1 DESIGN SUBMITTALS

Provide a complete design package at each milestone, as described in RFP Section 01 33 16-DESIGN AFTER AWARD. The milestones for this project are indicated above in Section 1.4 SUBMITTALS. The specific requirements of each milestone are described in each discipline-specific section of this Specification.

1.4.2 TEST REPORTS

Provide all test results and reports identified in this SOW to the Government as a submittal in accordance with RFP Section 01 33 00-SUBMITTAL PROCEDURES. Submittals will be considered for information only (FIO) submittals unless specifically identified as a submittal requiring government approval. Coordinate with the KO after award for the specific items to be included in the submittal register.

1.5 MATERIALS AND EQUIPMENT

Materials and products used must be durable, heavy duty, industry standard. The equipment must be the manufacturer’s standard quality and must be compatible with all other equipment and materials within the system or assembly. Equipment and materials must include all connections and accessories necessary to ensure operability and correct installation according to manufacturer’s requirements.

4-Nov-22 Page 4 of 49

Provide a nameplate secured to each major piece of equipment. Each nameplate must have the manufacturer’s name, address, contact information, type or style, model or serial number, and catalog number. The definition of a “major piece of equipment” is at the discretion of the KO.

1.5.1 LIFE-SPAN

The facility and the installed equipment must be permanent construction with an expected lifespan of more than 25 years.

1.5.2 MAINTAINABILITY

Provide low maintenance materials and systems appropriate for the project climate and location.

1.5.3 OPERABILITY

Systems (including but not limited to architectural, electrical, communications, and mechanical systems) must be simple to operate and easy to maintain.

1.5.4 STANDARDIZATION

Provide standardized materials, products, equipment, and systems to minimize the requirements for replacement parts, storage facilities, and service requirements.

1.6 DESIGN DIMENSIONS

Develop the design using the metric system.

1.7 DESIGN CRITERIA

Project design, site facilities, utility systems and material standards must be in accordance with Host Nation building codes (current versions as of the date of RFP, unless otherwise indicated). In the absence of Host Nation building codes, use the International Building Code (IBC) and the codes, technical standards, and regulations referenced in this RFP.

While this RFP references various source standards and specifications, all design documents must meet Host Nation codes and requirements. It is the designer's responsibility to demonstrate that the Host Nation standard is equal to the cited standard or specifications being supplanted. Apply the more restrictive standards when conflicts arise between the requirements of this RFP and any referenced or other applicable codes, standards, or regulations. If equivalency cannot be met, use the more stringent requirement and quote both codes verbatim in correspondence to the KO. The designer is responsible to determine the required material and execution standards where specific standards are not indicated.

Provide an electronic copy of the local Host Nation standards and building codes in their original language as related to facility design and construction.

1.8 SPECIAL CONSTRUCTION REQUIREMENTS

1.8.1 DEMOLITION

The Contractor is responsible for all required demolition as indicated in this scope.

Submit a Demolition Plan to be tracked via the submittal register indicating all demolition, abatement, and disposal methods.

1.8.1.1 ABATEMENT AND DISPOSAL

All demolished materials, including hazardous materials identified below, must be abated, and disposed of in accordance with local laws, codes, and regulations. The Contractor is responsible for all required testing before, during and after demolitions as well as for all required compliance with safety standards.

4-Nov-22 Page 5 of 49

1.8.1.2 LOCATION OF HAZARDOUS MATERIAL

The Contractor is responsible to survey the site and determine if hazardous materials exist. If hazardous materials are found to exist, immediately notify the KO and provide the results of the relevant sampling and testing. Provide the hazardous material report no later than 30 days after Notice to Proceed (NTP) for information and approval.

1.8.2 PROTECTION OF WORK AREA

1.8.2.1 DUST AND DEBRIS CONTAINMNET

Seal the project area with construction barriers and dust partitions in order to contain construction dust and debris and maintain a clean environment outside of the work area. In addition to protections within the work area, provide temporary protection for all finishes from the entrance of the facility to each area of work. Patch and repairing any damage caused during construction. Coordinate the locations of barriers with the Government prior to the start of work.

1.8.2.2 PROTECTION OF FURNITURE, FIXTURES, AND EQUIPMENT

Protect all existing furniture, fixtures, and equipment that remain within the work area. Coordinate with the Government for any special protection measures required for sensitive equipment. The Contractor is responsible for repairing or replacing any damage caused during construction. The Contractor must conduct a preconstruction survey of furniture, fixtures, and equipment with a Government representative present.

1.8.2.3 NOISE AND VIBRATION CONTROL

Employ demolition and construction methods that minimize the production of sound and vibration. Coordinate the schedule of especially loud or disruptive activities with the KO prior to the start of work.

1.8.2.4 PROTECTION OF EGRESS AND LIFE SAFETY

The Contractor must not take actions that hinder existing egress paths or disrupt operation of life safety systems without prior coordination with the KO and all applicable authorities having jurisdiction (AHJ). The Contractor is responsible for supplying signage or other protective measures as required by the KO or AHJ prior to impeding the egress path or life safety system.

1.8.3 SEQUENCING OF CONSTRUCTION WORK

The Contractor must sequence construction to allow the facility to remain occupied during construction. Do not block access to occupied areas during construction.

Utility and communication services must remain functional in all occupied areas.

Some relocation of equipment and/or personnel may be required to comply with this requirement.

The Fire Station must remain fully operational during construction. Submit detailed sequencing Plan – including a construction schedule – to the KO for approval prior to the start of construction activities. Construction on the vehicle garage can only occur during the spring/summer when freezing temperatures and snow are not expected so that the vehicles can be operational if parked outside. The Contractor must inform the KO of any variances in the schedule during construction.

Provide a Sequencing Plan with the 95% Final Design Submittal. The Sequencing Plan must describe the proposed performance of construction operations to comply with the stated sequencing requirements. The Sequencing Plan must include a graphical depiction of the sequencing of each work area and mobilization/staging area. The Sequencing Plan is in addition to the requirements of RFP Section 01 32 01-PROJECT SCHEDULE or 01 32 16-SMALL PROJECT PROGRESS SCHEDULES (NOTE: Only one of these

4-Nov-22 Page 6 of 49 specifications applies to this contract, refer to other documents for the section applicable to this project).

END OF SECTION

4-Nov-22 Page 7 of 49

2.0 CIVIL AND GEOTECHNICAL

Provide and perform civil engineering design and construction services as required to provide a complete, accessible, functional, and usable project. The Contractor is required to extensively coordinate civil design and construction work with the scope of the other disciplines described in this SOW.

2.1 SCOPE SUMMARY

Civil works for this project include, but are not limited to demolition and pavement. Refer to the bid schedule for which of these are base bid or optional.

2.2 EXISTING CONDITIONS

2.2.1 TOPOGRAPHY

There is no known topographic survey for the project site. The existing site contains buildings, pavement, utilities, and vegetation as shown on the attached Conceptual Site Plan. The site is generally flat. The existing information shown on the attached Conceptual Site Plan was compiled from Google Earth, and site photos.

2.2.2 UTILITIES

The existing facility is connected to power, district heat, municipal domestic water, municipal sanitary sewer, and municipal storm water systems. Exterior utility connections are adequate and not included in the scope of the project.

Refer to the other sections of this SOW for additional details of these existing utilities. Contractor must verify all utility locations (surface and subsurface) in the field prior to the first design submittal.

2.2.3 GEOTECHNICAL

There is no geotechnical information available for the project site.

2.2.4 ENVIRONMENTAL

There are no known environmental protection areas or archeological preservation areas on the project site.

There is no prior knowledge of any hazardous or contaminated materials in the site’s soil or pavement.

2.2.5 EXISTING CONDITIONS INVESTIGATION

Prior to bid, investigate the general and local conditions which can affect the work and/or its cost, including but not limited to:

a. Weather or similar physical conditions at the site.

b. Surface and subsurface materials or obstacles to be encountered insofar as this information is reasonably ascertainable from an inspection of the site and due diligence research of as-built drawings, geotechnical reports, environmental reports, and publicly available information on the site.

c. Mobilization and staging constraints.

2.3 DESIGN SUBMITTALS

Provide civil design submittals in accordance with RFP Section 01 33 16-DESIGN AFTER AWARD and in compliance with SOW Section 1.0 – GENERAL.

65% Design Submittal:

a. Pre-Final Design Analysis of civil features

b. Final Existing Conditions Plan

c. Pre-Final Demolition Plan

d. Pre-Final Site Layout Plans

e. Pre-Final Pavement Plans, Profiles, Cross Sections, and Details

f. Preliminary Civil Specifications

4-Nov-22 Page 8 of 49

95% Design Submittal:

Update all items from the 65% Design Submittal to 95% (Final) Design. Incorporate all 65% design comments.

100% Submittal:

The 100% Submittal provides a complete and final set of contract documents ready for construction. Update all Final submittals from 95% to a corrected Final submittal. Address all previous government review comments before submitting.

As-Built Drawing Submittal:

Provide as-built drawings of the site per the requirements discussed in RFP Section 01 78 00-CLOSEOUT SUBMITTALS. Include existing utility lines or structures (both modified and unmodified) encountered in the construction footprint that were not located on the original Site Survey.

2.3.1 DESIGN ANALYSIS

Submit a Design Analysis in accordance with RFP Section 01 33 16-DESIGN AFTER AWARD. Provide a Design Analysis for all Civil features that documents significant design choices and substantiates design compliance with contract requirements, applicable codes, and standards. Documentation includes narrative, calculations, photographs, sketches, and catalog cut sheets. Reference all applicable regulations, standards, and criteria for the design. Reference sources are subject to Government approval. Provide design assumptions. For design choices, discuss alternative systems considered, and provide rationale for the selected alternative.

a. Discussion of Site Layout constraints and design decisions, including but not limited to, land use, vehicle and pedestrian access, orientation of features on-site, and setbacks from site features.

b. Discussion of Demolition constraints and design decisions. Include discussion on how access will be provided during construction, and how each utility will be maintained and operated during construction.

c. Discussion of Pavement constraints and design decisions. Provide the design vehicle(s) specifications. Provide calculations for the pavement section.

Include pertinent geotechnical information that affects the pavement design.

2.3.2 DESIGN DRAWINGS

Provide Civil design drawings of sufficient detail to address the requirements of each design submittal. Civil drawings include plans, profiles, cross sections, and details of Civil features for the project. Civil drawings also include temporary construction plans/methods that affect the design and construction of the project.

These temporary plans include mobilization, traffic control, erosion control, dewatering, shoring, construction sequence, etc. Design drawings include all necessary information (labeling, dimensioning, legend, details, notes, etc.) to allow for complete understanding and constructability of all proposed features.

Provide comprehensible differentiation between features that are proposed, existing, future, or proposed to be demolished by use of appropriate choice of line styles, line weights, and/or colors. Reference USACE A/E/C Graphics Standard for graphic requirements.

2.3.3 SPECIFICATIONS

Provide Civil specifications of sufficient detail to address the requirements of each design submittal. Specifications, when combined with the design drawings, allow for complete understanding and constructability of all proposed Civil features.

4-Nov-22 Page 9 of 49

2.4 DESIGN CRITERIA

Provide civil design in accordance with Host Nation codes. In the absence of Host Nation codes, use the latest release of the International Building Code (IBC) and the following codes and technical standards:

a. Uniform Facility Criteria (UFC) 3-201-01, Civil Engineering

b. UFC 3-220-01, Geotechnical Engineering

c. UFC 3-250-01, Pavement Design for Roads, and Parking Areas

d. USACE A/E/C Graphics Standard (ERDC/ITL TR-19-6)

2.5 GEOTECHNICAL INVESTIGATION AND REPORT

Geotechnical survey is not a direct requirement of this project. Perform geotechnical investigations necessary for the design and construction of project features. Provide any geotechnical investigations and reports to the Government that are performed. Provide geotechnical information and assumptions in the Design Analysis to support design decisions. In the absence of Host Nation standards, perform the geotechnical scope of work per UFC 3-220-01, Geotechnical Engineering and IBC.

2.6 SITE SURVEY

A topographic survey is not required for this project.

2.7 SITE LAYOUT

Locate the proposed improvements as indicated on the attached Conceptual Site Plan. Amend the site layout as determined by the site-specific constraints, the owner’s preferences, accessibility, future expansion, and opportunities that are identified and evaluated as part of the Contractor’s scope of work

The Contractor is responsible for all aspects of the project whether they are shown on the conceptual plan or not.

2.8 DEMOLITION

Remove existing pavement, vegetation, and any other features to construct the proposed improvements. Provide straight, neat sawcuts at limits of pavement removal. All contaminated soils discovered require special testing and disposal per Host Nation requirements.

2.8.1 CONSTRUCTION LIMITS

Do not disturb the project site beyond necessary for installation of proposed construction. Do not disturb any areas past the site’s property line. Show demolition work and limits of disturbance in the drawings. Stake-out the limits of disturbance on-site with temporary fencing before beginning construction.

2.8.2 ITEMS TO REMAIN IN PLACE WITHIN CONSTRUCTION LIMITS

Take necessary precautions to avoid damage to existing items to remain in place, to be reused, or to remain the property of the Government. Repair or replace damaged items as required by the KO. Construct and maintain shoring, bracing, and supports as required. Ensure that structural elements are not overloaded. Provide new supports and reinforcement for existing construction weakened by demolition, deconstruction, or removal work. Repairs, reinforcement, or structural replacement require approval by the KO prior to performing said work.

2.8.3 UTILITIES

Any existing utilities encountered that are impacted by this project must be protected, or relocated if protection is not feasible. Remove existing and abandoned utilities under or within 3.0 m of the foundation of any proposed facility or building foundation. Reroute existing utilities to remain in accordance with SOW Section 2.10-UTILITIES. Abandoned utilities must be removed up

4-Nov-22 Page 10 of 49 to the utility main (or next utility main junction) and capped. Manholes or underground structures to be abandoned must be removed to a minimum depth of 50 centimeters below finish grade. Fill abandoned manhole or structure per Section 2.9-EARTHWORK requirements.

2.8.4 DUST, DEBRIS, AND EROSION CONTROL

Prevent the spread of dust, debris, and erosion from the project site. Install erosion control measures before beginning construction. Sweep pavements as often as necessary to control the spread of debris. Do not use water if it results in hazardous or objectionable conditions such as, but not limited to, ice, flooding, erosion, or pollution. Remove snow, dust, dirt, and debris from work areas daily.

Remove and transport the debris in a manner that prevents spillage on streets or adjacent areas. Apply local regulations regarding hauling and disposal.

2.8.5 ADDITIONAL REQUIREMENTS

Reference RFP Section 00 74 01-SPECIAL CONDITIONS, 00 74 18-SUPPLEMENTAL CONDITIONS FOR PROJECTS IN ROMANIA, and 01 30 00-GENERAL REQUIREMENTS for additional demolition, protection, and permitting requirements.

2.9 EARTHWORK

Perform all earth work necessary for the installation of the proposed improvements.

2.9.1 PLANS AND SPECIFICATIONS

Define earthwork requirements in the plans and specifications. Include requirements for satisfactory material, borrow material, structural fill, topsoil, utility trenches, replacement and improvement of on-site soils, soil compaction (for subgrades of structures, paving, and landscaped areas), compaction for utility trenches, maximum lift depths, density testing frequency, maximum temporary and permanent slopes, and engineered support systems.

2.9.2 UNEXPLODED ORDNANCE (UXO) CLEARANCE

UXO survey is not required.

2.9.3 CONTAMINATED SOIL

Inspect and test all soil according to Host Nation requirements. If hazardous materials are discovered, cease excavation, secure the area, and notify the KO for further guidance.

2.9.4 CULTURAL RESOURCES

Cultural resources, such as archaeological remains, may be uncovered during excavation operations. If suspected cultural remains are found, cease excavation, secure the area, and notify the KO for further guidance.

2.9.5 TOPSOIL

Remove and save topsoil (approximately first 20 centimeters of excavation).

Separate out subsoil, brush, litter, weeds, roots, stones larger than 25 mm in diameter, and other materials that would interfere with planting and maintenance operations. When restoring the site to finish grade, place topsoil back in excavated areas that do not include proposed paving or structures.

2.9.6 SATISFACTORY MATERIAL

Excavated material (below topsoil), if satisfactory for reuse per the Contractor’s Geotechnical Engineer, may be used on the project site where fill is required.

Unsatisfactory material, and surplus excavated material not required for fill, must be disposed of offsite, and is the responsibility of the Contractor. Borrow material may be required for construction from sources off site. Borrow materials

4-Nov-22 Page 11 of 49 are to be free of hazardous materials and contaminants. Any soil brought in from off-site sources must be certified clean.

2.9.7 BACKFILL COMPACTION

In the absence of Host Nation requirements and geotechnical recommendations, fill and backfill must be placed in layers of 20 centimeters loose thickness and compacted to a minimum 95% of the maximum dry density as determined by Host Nation test method equivalent to ASTM D-1557 (Modified Proctor test). Provide density tests on all lifts at a frequency of 1 test per 40 square meters for foundations and parking, and 1 test per 30 meters of road and utility trench. Round up to nearest whole number (i.e. a 25 square meter foundation requires one test). The location of all tests must be selected by the Contractor’s geotechnical engineer, and copies of all test results must be furnished to the KO. All structure foundation excavations must be inspected and approved by the Contractor’s Geotechnical Engineer prior to placing concrete. Repair earthwork areas as recommended by the Contractor’s Geotechnical Engineer, and approved by the KO.

2.9.8 ENGINEERED SOIL SUPPORT SYSTEMS

Provide engineered soil support systems (i.e. shoring) as required for the construction of the proposed improvements. The Contractor is responsible for all dewatering necessary for earthwork.

2.9.9 SITE GRADING

Provide site grading that directs storm water runoff away from buildings and structures by grading as follows:

a. Finished grades of paved surfaces adjacent to buildings and structures must slope away from all exterior edges with a minimum slope of 2% for the first 2 meters.

b. Finished grades must not create stagnating water or ponding anywhere on the project site, nor create ponding on adjacent properties. Provide storm improvements if ponding is unavoidable.

Site grading around the building must meet Host Nation accessibility guidelines.

The Contractor must limit proposed landscape slopes to a maximum 4H:1V for grass areas requiring mowing and 2H:1V for non-grass areas, which require non-erodible surface (i.e. rock, shrubs with mulch).

2.10 UTILITIES

This section applies to all project underground utilities located outside the building, including but not limited to, sanitary sewer, water supply, storm drainage, electrical, communications, and heat. Exterior utility connections are adequate and intended to remain as is. Refer to Section 2.8.4-UTILITIES if existing exterior utilities are impacted by this project. See Sections 5.0- ELECTRICAL & COMMUNICATIONS, Section 6.0-MECHANICAL, and Section 7.0-FIRE PROTECTION for additional utility requirements.

Provide horizontal and vertical separation between new and existing utilities for rehabilitation, maintenance, repair, or replacement. Provide utility line depths, bedding, and backfill as required by applicable requirements and geotechnical recommendations. Minimum cover over pipes is 0.6 meters; greater than frost penetration; or sufficient to support imposed dead and live loads for the pipe materials used; whichever is more stringent. Place plastic warning tape along the route of the buried pipe after installation at a height of 0.3 meters above the pipe.

Coordinate all required installation, relocation, improvement and protection of utilities held by third party (e.g. public or private utility). This includes coordination of any work to be performed by the utility owner. Choice of materials

4-Nov-22 Page 12 of 49 and products for utility installation must be coordinated with the utility owner (customer or third party) to ensure proper integration and compliance with existing systems and allow for easy maintenance and repair of the utilities in the future.

Provide utility materials per IBC requirements. Provide corrosion protection for utilities that provides the minimum life expectancy specified in Section 1.0- GENERAL. Any piping or equipment exposed to sunlight must be coated with protective coatings suitable for UV exposure with a minimum expected coating life of 10 years before recoating.

2.11 PAVEMENT

Mill and resurface the existing paved drive, parking, and garage apron areas in front of the Fire and Rescue Station with new bituminous asphalt pavement as indicated in the attached Conceptual Site Plan. The existing paved area to be resurfaced is approximately 2150 square meters. For bidding purposed assume full depth pavement section replacement will be required for 5% of the area. Existing manhole frames and covers and drainage structures must be adjusted to grade.

Provide site access to allow the facility to be operable at all times.

For asphalt concrete, provide compaction and pavement density tests, as well as thickness and evenness tests, at the frequency listed in Section 2.9 - EARTHWORK.

For PCC, reference SOW Section 4.0 - STRUCTURAL for concrete requirements. The location of all tests must be selected by the Contractor’s Geotechnical Engineer, and copies of all test results must be furnished to the KO.

2.12 LANDSCAPING

Provide grass seed and 20 centimeters of topsoil on the site in areas that do not have pavement or a building within the limits of disturbance. Seeds must be locally sourced from a certified plant nursery, and native to the area. Provide seed coverage density per manufacturer/supplier’s recommendations. Provide watering, weeding, and any other necessary care to establish growth. Limit planting to times of the year per local codes and/or manufacturer/supplier’s recommendations. Replace topsoil and seeds, at Contractor’s expense, in areas which do not have new growth coverage of 75% before the warranty period ends.

4-Nov-22 Page 13 of 49

3.0 ARCHITECTURAL

3.1 PROJECT DESCRIPTION

Provide and perform architectural design and construction services to provide a complete, accessible, functional, and usable fire station.

Renovate designated areas in a multi-story, solid masonry / concrete building that serves as fire station. See areas of renovation on the attached conceptual floor plans.

The existing basement will be renovated into a shower, bathroom, sauna, and locker room. The current basement is being utilized as a workout room. The bathroom and showers will require installation of new plumbing. The basement was constructed to be a fallout shelter, and the existing structure will not be altered. Demolition will include removal of the fallout shelter support items to include blast doors and an abandoned generator. The existing cafeteria will be renovated into a maintenance and storage space for oxygen tanks and other protective equipment. The space will include two single occupancy restrooms and an area for washing equipment. In the room #101, on the south elevation, the façade windows will be removed and replace with a solid block wall. In the room #101, on the west elevation, the façade windows shall be removed and replaced. The existing windows are floor to ceiling. The window heights will be reduced, but visual contact with the courtyard shall be maintained.

Extensive coordination is required between the architectural work and the work of other disciplines described in this SOW.

3.1.1 DESIGN

Provide a design and construction package that uses the space allocations, functional adjacencies, design details, and features given or referenced in this RFP. The design must incorporate all referenced codes and regulations. The Contractor is responsible for creating additional details as required to complete a full design. All details must conform to the requirements of this RFP and are subject to the approval of the KO. A schematic design has been attached for reference. The schematic plans are provided for diagrammatic purposes only and do not necessarily represent an approved floor plan or design. The Contractor is responsible for providing a design that meets all requirements of the User and the codes and criteria referenced in this Statement or Work.

3.1.2 DESIGN SUBMITTALS

Provide all architectural submittals after contract award in accordance with RFP Section 01 33 16-DESIGN AFTER AWARD and 01 33 00-SUBMITTAL PROCEDURES. Prepare and submit the documents listed below at the submittals indicated.

3.1.2.1 65% DESIGN SUBMISSION

Include the following drawings and reports as applicable to the project:

a. Code Summary – Provide a tabular code compliance summary indicating Host Nation and/or IBC life safety requirements for all new facilities.

b. Life Safety Plans – Provide plans depicting smoke/fire resistance ratings, egress routes, dead-end corridors, exits, and other aspects of life safety pertaining to the design.

c. Demolition Plans – Provide existing floor plans, indicating all demolition required.

d. Floor Plans – Provide all floor plans, indicating room names, areas, and basic dimensions, scale 1:50.

e. Ceiling Plans – Provide reflected ceiling plans for all rooms, indicating ceiling materials and fixtures, scale 1:50.

f. Building Elevations – Provide all building elevations indicating all exterior materials.

4-Nov-22 Page 14 of 49

g. Roof Plan – Provide a plan of all roof areas, indicating direction of slope and method of drainage.

h. Building Section – Indicate heights of critical building elements.

i. Wall Section - Provide a typical interior and exterior wall section for each building – describe wall materials.

j. Interior Elevations – Provide interior elevations of all bathrooms and built-in casework, indicate critical heights of surfaces and plumbing fixtures, and describe all materials and finishes.

k. Pre-Final Design Analysis – Provide a narrative explaining the design and indicating how the design and materials meet the requirements of this SOW.

l. Pre-Final Specifications – Provide detailed explanations of requirements for all performed work or provide product specific manufacturer information (brochures, technical information, cut sheets) for all materials and products to be provided/installed.

3.1.2.2 95% DESIGN SUBMISSION

The 95% Submittal provides a complete and final set of contract documents essentially ready for construction by the D/B Contractor. All previous government review comments must have been addressed. Include the following drawings and reports as applicable to the project:

a. All documents from the 65% submittal updated to incorporate 65% review comments.

b. Floor Plans – Provide all floor plans, indicating room names, areas, and dimensions, scale 1:50.

c. Building Elevations – Provide all building elevations indicating all exterior materials.

d. Roof Plan – Provide a plan of all roof areas, indicating direction of slope and method of drainage.

e. Building Section – Indicate heights.

f. Wall Sections – Provide sufficient wall section(s) to indicate all materials and different conditions.

g. Section and Plan Details – Provide details of critical building intersections.

h. Window and Door Schedule – Provide a schedule of all windows and doors, indicating sizes, hardware, and operation.

i. Finish Schedule – Indicate all proposed finishes.

j. Final Design Analysis – Provide a finalized narrative describing all work to be performed on the project and how it meets the functional and code requirements of the project. Provide product specific manufacturer information (brochures, technical information, cut sheets) for all materials and products to be provided/installed.

k. Final Specifications – Provide line items and detailed descriptions of all work to be performed.

3.1.2.3 100% DESIGN SUBMISSION

The 100% Submittal provides a complete and final set of contract documents ready for construction by the D/B Contractor. All previous government review comments must have been addressed. Include all drawings, specifications and calculations from the 95% Submittal updated to incorporate all previous review comments.

3.2 TECHNICAL CRITERIA AND STANDARDS

Design and construct the project in accordance with the requirements outlined in Section 1.7 DESIGN CRITERIA.

3.2.1 LIFE SAFETY REQUIREMENTS

The Design must meet all Host Nation and local Fire Suppression System codes and requirements. All new structures must have exits and means of egress that comply with current Host Nation codes and standards. In the absence of Host Nation codes

4-Nov-22 Page 15 of 49 and standards, for individual concerns of Life Safety the Contractor must follow the International Building Code (IBC).

3.2.2 HANDICAPPED ACCESSIBILITY REQUIREMENTS

Handicapped accessibility requirements do not apply to this facility.

3.3 GENERAL SCOPE OF WORK

Design the architectural elements of this facility to withstand all site-specific environmental conditions such as wide seasonal temperature swings, local wind, rain, snow, and earthquake conditions. All architectural features must be appropriately braced for anticipated seismic activity. The Contractor may propose alternate building materials to meet the facility’s requirements, but final selection of materials is subject to the approval of the KO. Consider economics not only in the initial acquisition, but also in the future maintenance of the materials, when selecting materials and building systems to be incorporated into the project. When requested, the Contractor must provide documentation demonstrating that a chosen alternative material is life cycle cost effective.

3.4 DETAILED SCOPE OF WORK

The Contractor is responsible for the following specific tasks required for the construction of this facility. All work described below applies to areas of renovation only.

3.4.1 DEMOLITION

Demolition applies to areas of renovation only. Demolition work includes, but is not limited to, the following items:

a. Demolish and remove existing interior and exterior doors.

b. Demolish and remove existing exterior windows.

c. Demolish and remove existing floor, wall, and ceiling finishes.

d. Demolish and remove existing electrical and lighting systems.

3.4.2 BUILDING SYSTEM AND MATERIALS

The intent of this RFP is to allow the Contractor the maximum flexibility to design and construct this facility in an economical manner without sacrificing good engineering practices, quality materials and systems. The Government requires low or no maintenance finish materials to the greatest extent possible. Provide a design informed by the modular size of selected materials. Building materials as described herein are minimum requirements and may require revision based on code compliance and criteria.

3.4.2.1 FIRE PROTECTION RATINGS OF INTERIOR FINISHES

All interior finishes must conform to Host Nation fire protection standards/requirements.

3.4.2.2 ACOUSTICAL DESIGN

Doors, walls, floors, and ceilings must meet the minimum sound protection per Host Nation requirements.

3.4.2.3 THERMAL INSULATION

Provide thermal insulation in accordance with Host Nation and local requirements.

3.4.2.4 CORROSION PREVENTION

All exterior materials and finishes must be appropriate for continuous exterior exposure. All materials susceptible to UV degradation must contain UV inhibitors.

Provide corrosion resistant coatings on all materials susceptible to corrosion.

Coatings must be applied in the factory prior to delivery to the maximum extent practicable. Physically separate dissimilar metals with non-conductive hardware.

Do not install aluminum in direct contact with concrete. Treat all wood with

4-Nov-22 Page 16 of 49 preservatives where it is contact with concrete or exposed to the exterior. Cover all exterior wood with metal flashing or exterior grade paint. Do not install wood in contact with soil.

3.4.3 EXTERIOR CONSTRUCTION WORK

Provide the following exterior architectural systems.

3.4.3.1 EXTERIOR WALLS

Design and construct new exterior walls in accordance with (IAW) the requirements of this SOW. Refer to Section 4.0 STRUCTURAL. Exterior walls must have smoke/fire resistance ratings as required by Host Nation, and local fire and life safety codes. Provide exterior wall finishes appropriate for the wall structure as required below.

3.4.3.1.1 STUCCO FOR NEW EXTERIOR WALLS

Install stucco and paint for new exterior wall surfaces. New stucco and paint must match existing. Provide all necessary expansion joints, base and corner rails, diagonal fiberglass-reinforcing fabric at the window corners, and flashing. Use products from a single system, by a single manufacturer, which are certified by the manufacturer to be suitable for the purpose. This also applies to the paint.

Apply products in accordance with the manufacturer's instructions. Provide all necessary sealing e.g. at windowsills. Submit a sample along with the manufacturer's catalog data including installation instructions, typical details, and product data for approval.

3.4.3.2 EXTERIOR DOORS

Provide new exterior doors in accordance with the functional requirements of this facility. Exterior door to be replaced is in first floor room 104.

3.4.3.2.1 EXTERIOR PERSONNEL DOORS

Provide new factory finished, insulated aluminum or steel exterior doors and frames to include new exit / escape doors. All main entry doors must be half glazed. Provide all necessary hardware for all doors including panic hardware locking mechanisms. All hardware must be heavy-duty metal and have a brushed chrome finish. Mount all door frames flush with surrounding walls and seal all seams. Exterior doors must include a commercially manufactured threshold with a vinyl or silicone rubber weather stripping insert in the face of the stop. Weather stripping must be held in an extruded non-ferrous metal housing. All doors must have heavy-duty closers. Size closers in accordance with the specific door application and size, and with manufacturer's recommendations. Coordinate key system with the KO and end user.

Each door must have the following hardware as a minimum:

a. Three hinges on each leaf.

b. One floor or wall mounted doorstopper, as appropriate.

c. Lever latch handles.

d. Fully mortised lockset compatible with existing keying system.

e. Fully adjustable hydraulic door closer (mounted on building interior);

f. Door coordinator on all door pairs.

g. Panic push bar in compliance with Host Nation criteria on each leaf, as required.

h. Weather seals and gasketing.

3.4.3.3 EXTERIOR WINDOWS

Provide exterior windows in room #101 in accordance with the functional requirements of this facility and as shown on the first-floor conceptual plan.

3.4.3.3.1 EXTERIOR WINDOW FRAMES AND GLAZING

4-Nov-22 Page 17 of 49

Provide new PVC windows and frames. Window frames must be 5-chamber PVC factory finished commercial grade with surround frame. All windows must be 100% operable with tilt and turn functionality and meet life safety requirements. Provide all accessories and hardware including drip sills, hinges, lever handles and latch lock. Anchor and secure window frames to structure as recommended by the manufacturer to meet the wind and seismic loads. Caulk all joints between window frames and building with sealant to provide a watertight installation and proper finish. All windows must have double pane, insulated glazing at a minimum. Windows must have a maximum assembly U-factor in accordance with applicable codes and standards. Windows must have a minimum width of 1500 mm and a minimum height of 1220 mm.

3.4.3.3.2 EXTERIOR WINDOWSILLS

Install new exterior factory-coated galvanized steel windowsills at all new windows. The windowsills must match the color of window frames. Caulk all joints between window frames and building with sealant to provide a watertight installation and proper finish.

3.4.4 INTERIOR CONSTRUCTION WORK

Provide the following interior architectural systems.

3.4.4.1 INTERIOR WALLS

Provide new interior partition walls IAW functional requirements. Provide penetration openings (for example for ventilation, piping, and cables) as required by other sections and drawings of this RFP. All interior walls must be full height between floor and roof/ceiling structure.

3.4.4.1.1 INTERIOR CONCRETE/MASONRY WALLS

Provide new masonry or concrete walls as required. Unless specified otherwise, provide two-layers of interior plaster and new paint on all masonry walls in normally occupied areas. Install plaster IAW manufacturer's guidelines. Refer to Section 4.0 STRUCTURAL for additional requirements for masonry and concrete construction.

3.4.4.2 INTERIOR WALL FINISHES

Provide new interior wall finishes as described below. Submit data sheets, color, and pattern of all wall finishes for review and approval.

3.4.4.2.1 INTERIOR PAINT

Paint all interior walls with a minimum of two coats of latex enamel paint over compatible primer. Paint must be lead free, water resistive and open to vapor diffusion. All paint must be low VOC and washable after drying.

3.4.4.2.2 CERAMIC WALL TILE

Provide glazed ceramic wall tiles from floor to ceiling in all toilet and bathrooms. Protect all walls in toilet and bathrooms with elastomeric waterproofing membrane half meter high above floors. Provide ceramic wall tiles on windowsills in all rooms / areas to receive ceramic wall tiles. Install tiles according to manufacturer’s instructions with appropriate grout-filled joints.

3.4.4.3 CEILINGS

Provide new ceilings as described below. Install ceilings to provide a clear room height in accordance with US, HN, and local building codes, but not less than 2.5 m above finished floor surface in any room. Do not use combustible materials for ceiling construction. Submit data sheets, color, and pattern of all ceiling finishes for review and approval.

4-Nov-22 Page 18 of 49

3.4.4.3.1 SUSPENDED ACOUSTIC CEILINGS

Provide new suspended acoustic ceilings for room #101. Acoustic tile ceilings must be level and flat. Provide and install all required components for a suspended acoustic tile ceiling system including mounting and supports of light fixtures.

Integrate all light fixtures and mechanical grilles in the ceiling grid.

3.4.4.3.2 GYPSUM BOARD CEILINGS

Provide suspended gypsum board ceilings with primer and paint in rooms #102-104 and #001-003 and #005-008. Gypsum board ceilings must be level and flat and appear seamless once finished. Provide all necessary trim and edge beads. Coordinate location of light fixtures and mechanical grilles. Provide moisture resistant gypsum board in rooms #001-003 and #005-008. Provide multiple layers of gypsum board as necessary to meet required acoustic and/or fire resistance ratings IAW manufacturer's guidelines. Provide fire resistance rated gypsum board where required. All fire resistance rated gypsum board must be labeled by an approved independent testing laboratory and installed per testing laboratory instructions.

3.4.4.3.3 EXPOSED CONCRETE CEILINGS

Paint exposed concrete ceilings in room #004. Provide a minimum of two coats of latex enamel paint over compatible primer.

3.4.4.4 FLOOR SLABS

Provide floor slabs in accordance with the requirements of Section 4.0 STRUCTURAL and the following.

3.4.4.4.1 HORIZONTAL WATERPROOFING AGAINST MOISTURE FROM OUTSIDE

Apply waterproofing on all new floor slabs in the building. Apply liquid proof coating with fabric reinforcement corner strips in accordance with manufacturer guidelines. Apply on floors before installing new screed. Provide photographic documentation to the KO showing the application of the waterproofing material.

3.4.4.4.2 SCREED AND FLOOR SLABS

Provide thermal insulation and floating cement screed in all rooms / areas.

3.4.4.5 FLOOR FINISHES

Provide new interior floor finishes as described below. Submit data sheets, color, and pattern of all floor finishes for review and approval.

3.4.4.5.1 CERAMIC TILE FLOORING

Provide new non-slip ceramic tile flooring (minimum DIN 51130 Group B, R11) and baseboards. Provide ceramic tile flooring for all areas to be renovated Protect ceramic tile flooring in wet rooms/areas with elastomeric waterproofing membrane on the concrete slabs and turn up half meter high above floor. Tiles wet rooms/areas must have a minimum slip resistance of Group B/R11. Tiles must be size 30x30 cm with joints of 3mm width. Fill joints with water resistive grout. Do NOT fill joints between wall and floor with grout, but with permanent elastic silicone. Color of grout and silicone must match. Install proofing layer suited for the application. Install ceramic tile baseboards in all rooms that receive ceramic tile flooring but not ceramic wall tile.

3.4.4.5.2 INTERIOR ENTRANCE GRATING

Provide interior entrance gratings at all entrance doors. Entrance gratings must be recessed, heavy duty type designed for easy removal for maintenance and cleaning. Provide manufacturer’s standard entrance grating system made from corrosion resistant metals with slip resistant surface. Provide all accessories including cast-in-place frames, supports, and fasteners. Recess slab as required so that walking surface of entrance grating is flush with the finish floor of the building interior.

4-Nov-22 Page 19 of 49

3.4.4.6 INTERIOR DOORS

Provide new single and double wooden doors and steel frames. All hardware must meet the fire rating assemblies for the doors and frames. Provide standard door 45mm thickness. Provide moisture resistant doors and door frames in the basement.

Paint all interior doors and frames using one coat primer and two coats of a finish paint. Submit color for review and approval. Provide moisture resistant sauna door and door hardware. Interior doors to be replaced are in first floor rooms 101, 102, 103, and 104; and in basement rooms 001 through 008.

3.4.4.6.1 DOOR HARDWARE

All hardware must be heavy-duty and have a brushed chrome finish. Install all hardware in accordance with the manufacturer’s instructions. All doors into toilet and bathrooms must have solid kick-plates on both sides.

Each door must have the following additional hardware as a minimum:

a. Three hinges on each leaf.

b. One floor or wall mounted doorstopper, as appropriate.

c. Lever latch handles.

d. Fully mortised lockset compatible with existing keying system.

e. Fully adjustable hydraulic door closer.

f. Door coordinator on all door pairs.

g. Panic push bar in compliance with Host Nation criteria on each leaf, as required.

h. Acoustic gasketing, as required.

All doors must have a mortise lockset. All locksets must be keyed to one master key system. Provide panic hardware and smoke tight fire rated doors in egress routes as required by the Life Safety Code.

3.4.4.7 INTERIOR WINDOW ACCESSORIES

Provide the following accessories on all windows.

3.4.4.7.1 INTERIOR WINDOWSILLS

Provide laminated interior windowsills at all windows except walls with ceramic tiles.

3.4.4.8 BATHROOM AND TOILET ACCESSORIES

Provide bathroom and toilet accessories as described below. All bathroom and toilet accessories must be made from corrosion resistant materials and have corrosion resistant, concealed fasteners. All bathroom and toilet accessories made from the same material must be finished to match. For toilet and plumbing fixtures, see Section 6.0 MECHANICAL.

This is the start of the file's text. The full file is on GovTribe.