SOW_RICE MILL_Clean and Flush Fire Main Supply_UPDATED.pdf

PDF 265 KB Posted

Attached to
USCG Base Charleston Fire Main Flush and Cleaning
Solicitation number
70Z036-26Q-FIREMAIN
Issued by

About this file

This is a Contract Specifications document for cleaning and flushing a fire main supply line at United States Coast Guard Base Charleston, located at 196 Tradd Street, Charleston, South Carolina 29401, with a scheduled completion date of August 2026.

The contractor must clean and flush approximately 60 feet of 6-inch underground cast-iron fire main supply line serving the Rice Mill Building. The work is necessary because debris, rust, and corrosion are restricting flow and resulting in inadequate suction pressure for the building's fire pump, which is designed to operate at 500 gallons per minute. Acceptable cleaning methods include hydroflushing, drain snake, chemical flushing, or equivalent techniques. The contractor must furnish all labor, tools, equipment, and materials, including incidental work items necessary for completion such as system draining and obstruction clearing. The contractor must provide photographic documentation of internal pipe conditions before and after work and conduct flow tests before and after completion to verify the required volume and pressure are achieved. The total contract performance period is 30 calendar days, and work must be performed during normal business hours (Monday through Friday, 7:00 a.m. to 3:00 p.m.) unless otherwise approved by the Coast Guard.

Contractor qualifications require that technicians hold NICET certifications in Inspection, Testing, and Repair of Water-Based Systems. Bidders are strongly encouraged to conduct site visits to verify existing conditions and determine the actual scope of work. The contractor must coordinate all staging and laydown areas with the Coast Guard prior to work initiation, comply with all federal environmental regulations and safety requirements, obtain required permits (confined space entry, hot work, and facility dig chits), and submit personnel rosters, project schedules, hazardous waste documentation, and product data sheets. The USCG Base Charleston Onsite Representatives are CWO Cody Wood and John DiFrancesco. The government will provide reasonable amounts of electricity and water from existing outlets and sinks.

View the file

Other files

File Type Posted
Site Plan and Fire Main Piping.pdf PDF
SF-1449 70Z036-26Q-FIREMAIN - NEW.pdf PDF
Provisions and Clauses SOLICITATIONS.pdf PDF
15-4427.txt TXT text file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT SPECIFICATIONS

RICE MILL_Clean and Flush Fire Main Supply

AT

UNITED STATES COAST GUARD

BASE CHARLESTON

196 TRADD ST, CHARLESTON, SC 29401

AUG 2026

Section 01 11 00

SECTION 01 11 00

SUMMARY OF WORK

1) GENERAL

The United States Coast Guard (USCG) seeks a qualified and experienced contractor to clean and flush approximately 60 feet of 6-inch underground cast-iron fire main supply line serving the Rice Mill Building at USCG

Base Charleston, SC 29401. Debris, rust, and corrosion are suspected to be restricting flow, resulting in inadequate suction pressure for the building’s fire pump to operate per its design intent of 500 GPM.

Base Charleston is a working Coast Guard unit and will remain in operation during the project.

Bidders are strongly encouraged to visit the site to field verify existing conditions and determine actual dimensions and the nature of the work required. Failure to visit the site does not relinquish the bidder from determining the extent and scope of the work required and estimating the difficulty and cost to complete the project.

The USCG Base Charleston Onsite Representative is CWO Cody Wood and John

DiFrancesco for this project.

General Work Requirements

a) Furnish all labor, tools, equipment, and materials to:

i) Clean and flush the fire main supply line to building.

(1) Acceptable methods include but not limited to: hydro-flushing, drain snake, chemical flushing, etc.

b) Incidental work items not listed in this scope, but necessary to complete the project shall be included. Examples include, but are not limited to; draining system, cleaning and clearing obstructions in the pipe, fittings, etc.

c) Contractor will provide pictures of the internal pipe condition before and after work to the USCG representatives.

d) Contractor shall provide flow tests before and after work is completed to ensure required volume/pressure is achieved.

2) Qualifications

a) Contractors shall be qualified and licensed whose technicians hold NICET certifications in Inspection, Testing, & Repair of Water-

Based Systems.

b) The Contractor shall provide qualified personnel to perform all requirements specified in this SOW.

3) SPECIAL WORK REQUIREMENTS

a) Coordinate all staging and laydown areas with the Coast Guard prior to work starting.

4) PROJECT PERFORMANCE PERIOD

a) The total contract performance period shall include not only the time needed to complete the base bid and approved option items, but it also includes the time needed to submit, review, and approve all material submittals, and complete all project record (closeout) documents. After work begins at the site, perform the work continuously during normal working hours and show daily progress until all work is complete.

b) The total contract performance period is 30 calendar days.

5) LOCATION

a) The work is located at:

U.S. Coast Guard Base Charleston

196 Tradd St, Charleston, SC 29401

6) SITE VISITS

a) Arrangements for visiting the site may be made by contacting:

Mr. John DiFrancesco

Email: John.DiFrancesco2@uscg.mil

7) DRAWINGS ACCOMPANYING SPECIFICATION

a) There are no drawings accompanying this specification.

8) WORK HOURS

a) Normal Working Hours

b) Perform all work at the site from Monday through Friday from 7:00am to

3:00 pm, unless otherwise approved. This project requires a special schedule to prevent operational interruptions during the installation process. Please refer to the scope section for detailed coordination of working hours. The contractor shall plan a schedule to minimize disruptions to building operations.

c) Performing the work beyond the listed working hours is at the discretion of the Coast Guard unit and the contractor must gain prior approval.

9) SPECIFIC ENVIRONMENTAL REQUIREMENTS

a) All contractors working on CG Base Charleston shall abide by all federal environmental regulations as published by the Environmental

Protection Agency, 40 CFR (series). Contractor written environmental management and pollution prevention programs shall be reviewed by the

Environmental Protection Specialist, Jeff Wachowski ((803) 465-1908 or

Michael.J.Wachowski@uscg.mil) prior to starting work and must be in accordance with ICSPORTSVA INSTM5090.2, the Unit Environmental Guide.

b) Written notification must be provided to the Environmental Protection Specialist of any activity that could potentially cause a permit violation on Base Charleston. Some examples of qualifying activities are any activity that could result in a spill or discharge into a waterway or introducing a hazardous material into the environment.

c) Copies of the following must be provided to the Environmental Protection Specialist prior to starting work in affected areas:

Material Safety Data Sheets, permits, and notices of intent.

d) Hazardous materials used by a contractor are required to be disposed of by that contractor. Disposal must be in accordance with federal, state, and local guidelines.

10) SAFETY PROGRAM

a) The Contractor is wholly responsible for work site safety. Implement a safety program that protects the lives and health of personnel in the construction area, prevents damage to property and avoids work interruptions. Provide appropriate safety measures including but not limited to barricades, signs and signal lights as well as complying with the requirements of all applicable federal, State and local safety laws, rules and regulations.

b) Written notification must be provided to the Base Safety Officer, John

DiFrancesco ((843) 610-8177 or John.DiFrancesco2@uscg.mil) in their capacity as Base Fire Marshal of any activity that could potentially cause fire or explosion or that changes or reduces the capability of fighting a fire or explosion. Some examples of qualifying activities are: a fire hydrant or fire suppression system that must be taken out of service for any reason, electrical work that affects fire alarm systems, introduction of hazardous or flammable material onto the Base, and blocking of any egress routes or emergency vehicle routes.

Inclusion of this information in the contract constitutes written notification as long as the outsource review sheet is signed by Base

Safety Officer.

c) Copies of the following must be provided to the Base Safety Officer prior to starting work in affected areas: Confined Space Entry Permits, Hot Work Chits, and Dig Chits. Confined space clearance must be conducted by a certified marine chemist and permit required spaces will have a copy of the permit posted on site during work. Hot work will only be conducted with permission and a fire watch must be posted during work. A facility dig chit is required in addition to a Miss

Utility dig chit. The systems on Base Charleston are not limited to what the City of Charleston has on file. In order to ensure electrical safety and integrity of systems, a facility chit is required.

d) Lock Out/Tag Out requires notification and coordination with facilities and will not be conducted by a contractor on Base Charleston. A

Facilities Division representative is required for all contractor Lock

Out/Tag Out needs.

11) AVAILABILITY OF UTILITY SERVICES

a) The Government will provide all utility services required in the performance of this contract, including reasonable amounts of electricity and water. Electrical power is provided at existing outlets for the Contractor to operate equipment necessary in the performance of work. Hot and cold water is provided at existing sinks and outlets limited to the normal water capacity of the building. No special heating or cooling of water will be provided.

b) The Government will not furnish any other resources to the Contractor in support of this contract.

12) UNDERGROUND AND CONCEALED UTILITIES

a) Any utility locations provided are diagrammatic, not exact.

b) Physically verify the location and elevation of the existing underground and concealed utilities local to the work area. Employ techniques to scan the construction site including electromagnetic and sonic equipment prior to commencing the work. Mark the surface of the ground where existing underground utilities are discovered.

13) UTILITY OUTAGES

a) Identify the utility, reason for interruption, proposed time of interruption, and duration of interruption. Do not interrupt utilities until authorized by the Contracting Officer’s Representative (COR).

14) CONTRACTOR USE OF PREMISES

a) The work shall be performed on a Coast Guard operational military installation. Become familiar with and obey station fire, traffic, and security regulations. Personnel shall not stray from the immediate area of work or direct avenues of ingress and egress unless authorized in advance by the COR. Isolate each construction area with temporary partitions and dust controls. Provide movable high-visibility safety fencing about all work areas and equipment laydown areas located outdoors. Provide temporary covers on excavations that remain open overnight.

15) CLEANUP

a) The Contractor shall keep the work area, including the laydown and storage area, free from accumulations of waste materials on a daily basis and comply with all federal, state, and local regulations pertaining to the storage, transport, and disposal of wastes. The

Contractor shall not use Coast Guard waste disposal facilities including garbage cans, trash piles, or dumpsters.

16) ENVIRONMENTAL

Protection of the Environment

a) The Contractor shall comply with all applicable federal, state, and local laws and regulations for the protection of the environment, including but not limited to the Endangered Species Act (ESA), Bald and

Golden Eagle Protection Act (BGEPA), the Migratory Bird Treaty Act

(MBTA), National Historic Preservation Act (NHPA), the Resource

Conservation and Recovery Act (RCRA), and Comprehensive Environmental

Response, Compensation, and Liability Act (CERCLA).

Generated Waste

b) Any waste generated because of the project shall either be recycled or be disposed of in accordance with RCRA requirements.

c) Any hazardous waste shall be manifested off site with the Coast Guard unit listed as the Generator and signatory. Any hazardous waste shall be analyzed, characterized, stored, and disposed of in accordance with

RCRA and all applicable federal, state, and local laws and ordinances.

d) Hazardous waste shall be properly transported and delivered to an appropriate facility. The Contractor shall submit for COR approval the proposed disposal facility, qualifications of the transporters, and the draft hazardous waste manifest.

17) DISPOSITION OF MATERIALS

a) All materials including construction debris and equipment shall be removed from Government property. The Government will not be responsible for the condition or loss of, or damage to, such property after notice to proceed. Materials and equipment shall not be viewed by prospective purchasers or sold on the site.

b) The Contractor shall submit the disposal receipt from the landfill within 10 working days of disposal (if needed).

18) STORM PROTECTION

a) The Contractor shall take every practicable precaution to minimize danger from storms to personnel, the work, and to adjacent property.

Precautions shall include, but not be limited to, closing all opening, removing all loose materials, tools, and equipment from exposed locations, and removing or securing scaffolding and other temporary work.

19) RECEIPT OF MATERIALS

a) The Contractor is responsible to receive all equipment, materials, and supplies.

20) DELIVERY AND STORAGE

a) The Contractor is responsible for the proper transport and storage of all equipment and materials.

21) SECURITY

a) Submit a list of the names of all personnel working on the project site prior to the preconstruction conference for approval. The roster shall be submitted via email, and at a minimum, include the first name, last name, job description, and company of employment.

b) Immediately submit a new list upon a change in on-site project personnel. Refer to the paragraph titled, Special Notice Prior

Notification, for notification requirements. Only personnel on the approved list are allowed onto the project site.

c) All approved personnel shall carry a valid, Government-issued identification while on Government property in conformance with the

Real ID Act of 2005. Non-compliant personnel shall be escorted off

Government property.

22) FINAL INSPECTION AND ACCEPTANCE

a) Electronically submit a written request for final acceptance to the

Coast Guard.

23) SUBMITTALS

The Contractor shall provide the Onsite Representative with:

a) ROSTER OF PERSONNEL

b) PROJECT SCHEDULE

c) Prepare a Construction Progress Schedule. It shall include all major milestones and events for the entire duration of the construction contract.

d) At least 5 days prior to the planned start of work.

e) Signed and fully executed originals of all hazardous waste profiles, test results, hazardous waste manifests and/or other shipping papers, and all other required documentation. The Contractor shall submit a copy of the waste shipment records within one day of the shipment leaving the project site (if applicable).

24) SAFETY PLAN

a) The Contractor is wholly responsible for work site safety. The

Contractor shall implement a safety program that protects the lives and health of personnel in the construction area and adjacent areas, prevents damage to property, and avoids work interruptions. The

Contractor shall provide appropriate safety barricades, signs, signal lights, etc. as well as complying with the requirements of all applicable Federal, State and Local safety laws, rules, and regulations.

25) PRODUCT DATA

a) Submit the product data sheet for each manufactured item. It shall include the manufacturer's descriptive literature of cataloged products, equipment drawings, diagrams, performance and characteristic curves and catalog cuts. Submit complete descriptive data for each type of material. Clearly mark data to indicate the type of material to be provided.

26) Documentation

a) Encl (1) Site and Work Area Plan

-- End of Section –