SOW - Replace Door Frames Building 104 D-B.docx

DOCX document 344 KB Posted

Attached to
Z1DA--595-24-105 Replace Door Frames Bldg 104 DB (VA-26-00010058)
Solicitation number
36C24425R0151
Issued by

About this file

This is a Statement of Work (SOW) for a Design-Build (DB) project to replace door frames in Building 104 at the Lebanon VA Medical Center in Pennsylvania. The project involves replacing four door frames (one 2-hour rated, one 1-hour rated, and two non-rated), reinforcing metal stud walls to support automatic door operators, and upgrading wall partitions from a 1-hour to a 2-hour rated wall. The Design-Build team will be responsible for providing professional architectural, engineering, and construction services, including site investigations, design development, construction documents, and construction period services.

The project has a defined schedule with key milestones: construction documents are due 90 days after Notice to Proceed (NTP), and construction must be completed within 180 days of NTP. All work must be performed during second and third shift hours to minimize impact on patients and staff, and must comply with current codes and standards including IBC, NFPA, and OSHA regulations. The estimated contract will be a Firm-Fixed-Price, awarded on a Best Value basis, with the Design-Build team required to collaborate closely with the VA Contracting Officer's Representative (COR) and hospital maintenance shops throughout the project.

View the file

Other files

File Type Posted
013526 Lebanon Safety Requirements Spec 20221012.docx DOCX document
013526 Lebanon Safety Requirements Spec 20240516.docx DOCX document
36C24425R0151.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Design-Build (DB) Scope of Work Replace Door Frames Building 104 D-B 595-24-105 Construction Documents Ready by 90 days after Notice to Proceed (NTP) issued Construction Complete by 180 days after NTP issued Contracting Officer: TBD Contracting Officers Representative (COR): Matt Donmoyer

-- Services --

· Provide all labor, materials, tools and equipment, and the design-build services necessary for design and construction of a project described herein as well as other specific tasks as further defined by this Request for Proposal (RFP) the Design-Build Project No. 595-24-105, Replace Door Frames Building 104 D-B. This procurement shall provide required design completion of the aforementioned project and perform construction of completed design work. Project shall be designed and completed in accordance with VA Criteria, ASHRAE, and VA Specifications developed for the project.

· This Request for Proposal (RFP) document is intended to generally define the scope and design parameters to be included in this project. It is the responsibility of the Design-Build team to provide a complete set of approved design documents in a manner consistent with the VA guidelines, specifications, and design standards in order to complete construction within a 180-day schedule.

· Offeror shall be prepared for a 180-day schedule as indicated below in the Project Schedule. Offeror may propose an alternate schedule, in addition to the 180-day schedule, which will be reviewed by the VA. Schedules shall indicate the following:

· The design period which shall include provisions for VA reviews.

· Phasing plans

· All work to be completed during second shift hours

· Construction period services including:

· Mobilization

· Demolition

· Procurement and installation of equipment

· Provisions for overtime or shift work shall be included in the contract offer.

· Equipment unloading, placing, inspection, testing, commissioning, and reports

PROVIDE:

Professional Design-Build (DB) construction services to include but not limited to:

· Site investigation – mechanical/plumbing and any other engineering services as needed.

· Contract drawings and specifications for construction.

· Construction period services for DB A/E - review of shop drawing submissions, provide recommendations regarding contractor change proposals and requests for information (RFI), DB A/E shall visit site per VA's request, add to drawings as-built conditions from contractor's record drawings; DB A/E shall respond on site within a two-hour period when requested.

· Construction and Installation services of the doors replacement and 2-hour rated fire wall installation, including all Management, Supervision, Labor, Transportation, Equipment and Materials and to perform work to include demolition, general construction, alterations, mechanical and electrical work, and certain other items as required by project drawings and specifications to create a complete and useable facility.

-- Project Scope --

GENERAL:

Provide sufficient construction documents and construction for a project that shall replace (4) total 88” double door frames, (1) 2-Hour rated, (1) 1-Hour rated and (2) nonrated door frames and reinforce metal stud walls to decking to properly support and stabilize for automatic door operators at designated locations throughout Building 104 of the Lebanon VAMC campus. Existing doors, hardware and automatic door operators shall be reused. Offeror shall also provide sufficient construction documents and construction that shall upgrade wall partitions from a 1-hour rated wall to a 2-hour rated wall as designated on Attachment A. Replacement door frames and reinforcement shall be designed and installed as per the specifications and drawings approved through the Design and Project Design Team (PDT) process.

SPECIFICS:

The project is intended to properly support the door frames to the decking above to prevent wall cracking from door operator use at specified locations within Building 104 at the Lebanon VAMC campus. A floor plan of designated door frames as well as the upgraded 2-hour rated wall is part of Attachment A.

· Remove existing door frame, reconstruct wall, and fasten to decking above, install proper blocking for stability to reinforce wall to support automatic door operators. Replace door frame 14C2 with 2-hour rated door frame, utilize existing doors, hardware, and automatic door operator.

· Remove existing door frame, reconstruct wall, and fasten to decking above, install proper blocking for stability to reinforce wall to support automatic door operators. Replace door frame 11C7 with 1-hour rated door frame, utilize existing doors, hardware, and automatic door operator.

· Remove existing door frame, reconstruct wall, and fasten to decking above, install proper blocking for stability to reinforce wall to support automatic door operators. Replace door frame 14C7 and 15C1 with non-rated door frame, utilize existing doors, hardware, and automatic door operator.

· Modify existing wall shown on attachment “A” from a 1-hour smoke barrier to a 2-hour fire/smoke rated partition wall.

· All work must be completed to current codes and standards

· All on-site work must be performed during second and third shift hours. Installation will be required to occur during times that will minimize impact to the patients, staff and hospital in general, and outages shall be kept to an absolute minimum and scheduled at the convenience of the government.

· All work must comply with strict infection control standards

· Collaboration between Design-Build team, COR and Lebanon VAMC Carpenter shop and Electric Shop will be required during the project.

· All work shall comply with the IBC, National Fire Protection Association (NFPA) 70 (National Electrical Code), 70B, 70E, 72, 99, 101, 20, 24, 25 Occupational Safety and Health Administration (OSHA) regulations.

· All work must comply with OSHA and Lebanon VAMC lockout/tagout requirements Construction shall be addressed in phases to allow operations to continue during construction to the greatest extent possible. Phasing shall be determined during the 35% design review. Phasing must work within budget and allow the VA to continue operations at minimal interference.

The DB A/E is responsible for providing certified industrial hygiene services to perform asbestos survey investigations, bulk sampling, development of specifications and drawings, and construction period services. All designs shall be accomplished in accordance with VA guidelines and specifications, which are available on the Internet at http://www.cfm.va.gov/til/. DB A/E shall pay particular attention to NFPA, BOCA, VA Handbook 7610 space criteria and VA program guide PG-18-14. SPECIAL NOTE: Be reminded that the VA guidelines are just a guide, and the project is not bound by them. If current healthcare trends dictate a different design approach is needed, we shall follow that approach.

The DB A/E shall provide professional architectural and engineering and construction services for the project and is responsible for providing all services necessary for design of this project – i.e. mechanical/plumbing, electrical, structural, etc.

The DB construction contractor shall provide all Management, Supervision, Labor, Transportation, Equipment and Materials and perform work to include demolition, general construction, alterations, mechanical and electrical work, and certain other items as required by project drawings and specifications complete the Replace Door Frames Building 104 Project.

-- Site Investigations --

EXPECTATION: The DB A/E shall make site visits as necessary to survey existing conditions.

Make site visits as required to determine existing as-built conditions affecting this project. NOTE: Information including drawings and other documentation provided to the DB A/E is used as reference only. All additional references and specifications are available in VHA’s Technical Information Library at address: http://www.cfm.va.gov/til/. AutoCAD background drawings will be provided by the VA upon request. The DB A/E shall field verify all dimensions. The DB A/E shall field verify every aspect that relates to the project. Coordinate site visits with the Contracting Officer Representative (COR) as determined after award.

-- Project Schedule --

EXPECTATION: Submit review packages so they are received on the noted day

SUBMISSIONS:

Submit review packages so they are received on the noted day (calendar days after NTP) or earlier:

Initial PDT Meeting0 days
Design Development Documents (35%)27 days
(PDT Meeting)41 days
Design Development Documents (100%)62 days
(PDT Meeting)76 days
Construction Documents90 days
Begin Construction on or before120 days
Complete Construction on or before180 days

Note: The issuance of the Notice to Proceed (NTP) for design will be at the first Project Design Team (PDT) Meeting. The Design-Build Team Contractor shall be required to attend and take minutes of each PDT meeting. Minutes shall be submitted electronically to the Project Manager and Contracting Officer within three calendar days of each meeting for approval and to be added to the official contract file.

-- Design Requirements/Submissions --

EXPECTATIONS: Submit complete review package in accordance with the following requirements and guidelines outlined in http://www.cfm.va.gov/til/aeDesSubReq.asp Please pay specific attention to the schematic, design and construction submission requirements. As appropriate and depending upon the complexity of the design, the DB A/E may elect to delete individual submissions where not required (i.e. Do not address Site Development, Landscaping for interior renovation projects)

DELIVER:

Submit all design/bid submission packages directly to the Contracting Officer Representative on the established dates to allow the VA time to review. Include all information as follows and as outlined in the attachments for each submission. Information required for each submittal is outlined in Program Guide PG-18-15 Volume C November 2008. The manual is available at the following address: http://www.cfm.va.gov/til/aeDesSubReq.asp Area of Construction: See Attachment “A”.

Design Development 35%: Attachment “B” 35% Submission Requirements

· Requirements for the 35% Design Development Documents Submission.

· Define the design elements based on the presented option and submit all information required by the PG-18-15 (35% Design Development).

· Identify Working Drawings scope within the construction budget.

· Identify all design calculations.

· Identify impact of existing asbestos.

· Develop plans and marked up specifications to meet all applicable federal and state

· codes/requirements, including but not limited to IBC, OSHA, DEP, EPA, NEC, NFPA 20, 24, 25, 70, 72, 99, 101, 110.

· Identify all design calculations.

· Identify all existing utilities and utilities requirements.

· Identify all potential bid deduct alternatives.

· Identify all phasing requirements for construction.

· Develop Infection Control Risk Assessment (VA EC-43)

Design Development 100%: Attachment “C” 100% Submission Requirements

· Requirements for the 100% Design Development Documents Submission.

· Address all comments from the 35% review.

· Consolidate all necessary submittals by specification section on an Excel spreadsheet. Checklist to be utilized to track/monitor submittal process.

· Revise and update cost estimate.

· Finalize all design calculations.

· Finalize all phasing requirements for construction.

· Finalize impact of existing asbestos.

· Finalize Infection Control Risk Assessment (VA EC-43)

· Address all comments from the VISN Safety & Fire Protection Review.

Construction Documents (CD): Attachment “D” Construction Documents Submission Requirements Submit a complete set of documents of all contract requirements. The Cover Page shall be submitted for approval signatures. If necessary, update and submit until approved by the VA.

-- Construction Period Services --

Expectations: Respond to submittals and other requests in a timely manner.

PROVIDE:

· Review all shop drawing submissions and provide recommendations to the VA within five calendar days upon request.

· Make site visits on requests of the VA and prepare written reports to include agreed upon changes in design as determined necessary during the construction. Visits made based on errors and omissions in design shall be at no cost to the VA.

· Participate in partial and/or final acceptance inspections as scheduled and generate punch list items for completion. The punch list shall reference the contract documents for specific deficiencies (i.e. specification section, drawing detail, etc.)

· Prepare as-built drawings on original set with DB A/E’s stamp, based on record drawings that the contractor kept during construction. Transpose contractor’s as-built’s to AutoCAD 2007 – 2019 and in PDF form and provide a set of updated as-built’s on CD within 30 days to the COR

ATTACHMENT “A”

Drawing AE-100 Floor Plan – Fire Barrier Upgrade.pdf Drawing AE-101 Wall Types.pdf Drawing AE-102 Doors-Frames-Details.pdf

ATTACHMENT “B”

Design Development 35% Submission Requirements Deliver the following (labeled with 35% submission) and include this attachment as a checklist with your submission:

· 1 Copy of a narrative report forwarding the design develop 35% submission addressing items listed in the design requirements and any additional A/E recommendations. The report should include identifying potential bid deduct alternatives, recommended construction phasing based upon discussions with the program manager, and any design calculations or analysis.

· 3 sets of all drawings updating all previous comments required by project and produced in AutoCAD 2007 – 2019 and in PDF form.

· 1 Copy of updated itemized cost estimate by spec section or trade (labor, material and equipment) and also by VA criteria, NRM, Minor, BSER and BSEA.

· 1 Copy of custom edited VA Master Specifications of sections to be used for this project and a master submittal list identifying all the submittals required to be submitted by the contractor for review.

· 1 set of all drawings and specifications, to send for 3rd party Life Safety Review.

· 1 copy of drawings in AutoCAD 2007 – 2019 and in PDF form and specifications in Microsoft Word 2007 or higher on (CD) Lebanon VA Medical Center Lebanon, PA 17042

ATTACHMENT “C”

Design Development 100% Submission Requirements Deliver the following (labeled with 100% submission) and include this attachment as a checklist with your submission:

· 1 Copy of a narrative report forwarding the design develop 100% submission addressing items listed in the design requirements and any additional A/E recommendations. The report should include identifying potential bid deduct alternatives, recommended construction phasing based upon discussions with the program manager and any design calculations or analysis.

· 2 sets of all drawings updating all previous comments required by project produced in AutoCAD 2007 – 2019 and in PDF form.

· 1 Copy of the proposed construction schedule.

· 1 Copy of final itemized cost estimate by spec section or trade (labor, material and equipment) and also by VA criteria, NRM, Minor, BSER and BSEA.

· 1 Copy of final edited VA Master Specifications of sections to be used for this project and a master submittal list identifying all the submittals required to be submitted by the contractor for review.

· 1 CD containing

· All drawings in AutoCAD 2007 - 2019 and in PDF form.

· All specifications in Microsoft Word 2007 or higher on (CD)

ATTACHMENT “D”

Contract Document Submission Requirements

Expectation: Submit complete contract documents for final review prior to Notice to Proceed for Construction. Continue to submit contract documents until all changes are incorporated by the DB A/E for final signature prior to Notice to Proceed for Construction. Upon approval duplicate copies as required.

Deliver the following (labeled with Contract Documents Submission) and include this attachment as a checklist with your submission:

· 1 copy of the Cover Sheet (AutoCAD) for final VA signatures.

· 2 sets of all drawings updating all previous comments required by project, produced in AutoCAD 2007 – 2019 and in PDF form – for final VA review. If approved final sets to be submitted with signed off cover sheet.

· 1 Copy of final project specification (bound) prepared in Microsoft Word 2007 or higher. Include a master submittal list in the specifications.

· CD containing

· All drawings in AutoCAD 2007 – 2019 and in PDF form.

· All specifications in Microsoft Word 2007 or higher.

· Submittal Spreadsheet – identifying all the submittals required to be submitted by the contractor for review. The list shall be organized by division and specification.

Upon signature approval, provide three (3) sets of final Contract Documents (complete with VA signed Cover Sheet). Provide two (2), half (1/2) size sets of final drawings.

ATTACHMENT “E”

Contract Specifications

010000Lebanon General Requirements
013526Lebanon Safety Requirements