SOW_Preventative Maintenance for the Blast Cabinet_1.23.25.pdf
PDF 88 KB Posted
- Solicitation number
- N00174-25-SIMACQ-D1-0031
About this file
This Statement of Work (SOW) outlines requirements for service and repair of blast cabinets at the Naval Surface Warfare Center Indian Head Division (NSWC IHD). The contractor, as the Original Equipment Manufacturer (OEM), must service and repair two specific units: the Titan 7272RPD blast cabinet and the Clemco Pulsar VI-P blast cabinet.
The work requires OEM-authorized engineers to perform services according to industry standards during normal business hours (8:00 AM - 4:00 PM Monday-Friday). Key requirements include coordinating with Government POC for base access, cleaning work sites, providing electronic service reports detailing completed work, and offering standard commercial warranty coverage for modified components. The work is unclassified but requires contractor personnel to pass background checks for facility access. No government-furnished materials are required for this effort.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Service and Repair of the Blast Cabinet
Naval Surface Warfare Center Indian Head Division
1.0 SCOPE
The Naval Surface Warfare Center Indian Head Division (NSWC IHD) has a requirement for the service and repair of the Blast Cabinet.
2.0 DESCRIPTION OF SERVICES
The Contractor shall provide service and parts to service and repair the Titan and Clemco Blast Cabinet.
• Service and Repair the Titan 7272RPD blast cabinet
• Service and Repair the Clemco Pulsar VI-P
As the Original Equipment Manufacturer (OEM), the Contractor shall perform to industry standards in accordance with the OEM procedures while mitigating unscheduled downtime. All work completed on any of the instruments listed above shall be completed by an engineer who is authorized by the manufacturer of each instrument. All residues shall be removed, and the work site cleaned at the completion of the task.
3.0 SCHEDULING OF SERVICES
The Contractor shall coordinate with the Government Point of Contact prior to performing onsite service to ensure the base passes have been established for the engineers. All work shall be performed between the hours of 8:00 am and 4:00 pm, Monday through Friday, excluding Federal holidays. After the services have been completed, a designated user will confirm that the instrument is performing satisfactorily and sign the service call ticket. Any disputes between the engineer and the designated user regarding satisfactory performance will be immediately referred to the Contracting Officer.
4.0 ACTIVITY SUMMARY
The Contractor shall provide the Government with a report that details the service accomplished.
The report shall be submitted electronically to the Government POC. The report shall summarize the actions completed to include:
a) Type of Service
b) Instrument/Components
c) Verification
5.0 WARRANTY
All components modified shall be covered by the Contractor’s standard commercial warranty.
6.0 GOVERNMENT FURNISHED MATERIAL
No Government furnished material is required for this effort.
7.0 SECURITY
All tasks associated with this Statement of Work are unclassified. Contractor personnel must be able to pass the background checks required for access to the Government facility.
File details come from the government source that posted it. Updated .