SOW_Pile_Appendix2.docx

DOCX document 18 KB Posted

Attached to
EAGLE RIDGE II Federal contract opportunity
Solicitation number
140L6221Q0036
Issued by
Department of the Interior Bureau of Land Management Wyoming Region

View the file

Other files for this federal contract opportunity

Other files attached to EAGLE RIDGE II, newest first.
File Type Posted
Sol_140L6221Q0036.pdf PDF
Statement_of_Work_EagleRidgeII.docx DOCX document
BatesHoleJuniper_EagleRidgeII_4_8_21topo.pdf PDF
BatesHoleJuniper_EagleRidgeII_4_8_21.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Appendix 2

Bates Juniper

Eagle Ridge II

SPECIFICATIONS FOR PILING

Minimum Distance: Locate piles centrally and as far as possible from all leave trees, with the minimum distance from the edge of the pile to the perpendicular edge of the nearest branch or tree of approximately fifteen (15) feet. All piles will be located within the unit boundary.

Pile Height: Maximum pile height is six (6) feet.

Pile Diameter: Maximum pile diameter is six (6) feet.

Pile Shape: Pile shape can be “teepee”, triangular, mounded, or decked. If using a non-“teepee” method, stack fine materials (one inch in diameter or less) in the lower center with bigger material on top. Making sure there are no large air pockets.

Material Size: Surplus material should be piled. Piled material will be cut to lengths of six feet or less, and will not be in contact with any ground fuels greater than three inches in diameter.

Hazardous Fuel processing: The contractor will pile a minimum of 80% of the “green” surplus material having a basal diameter in excess of two (2) inches.