SOW Painting 4 Units Sturgeon Bay FYCOM 2025.docx

DOCX document 524 KB Posted

Attached to
US Coast Guard Sturgeon Bay Housing Painting
Solicitation number
31050PR250000153
Issued by

About this file

This Statement of Work (SOW) details painting services for four United States Coast Guard housing units located in Sturgeon Bay, Wisconsin. The contract requires comprehensive interior painting for three-bedroom, two-bathroom units totaling approximately 9,595 gross square feet, with work to be completed within five working days per unit on a varied timeline. Specific requirements include surface preparation, wall and trim repairs, priming, and painting using Sherwin Williams PrepRite ProBlock and ProMar 200 in Extra White, with semi-gloss finish for bathrooms, utility rooms, and kitchens.

The solicitation (Number 31050PR250000153) is set aside for small businesses with a size standard of 500 employees, using a firm fixed-price contract type. Contractors must submit quotes on business letterhead detailing materials, labor, man-hours, and workforce, with quotes to be emailed to Jordan Drew. Vendors must be registered in the System for Award Management (SAM.gov) and will submit invoices through the Invoice Processing Platform (IPP). The Department of Homeland Security US Coast Guard will award the purchase order to the most advantageous responsible contractor, with work to comply with federal, state, and local regulations.

View the file

Other files

File Type Posted
SF 30 - AMENDMENT OF SOLICITATION.MODIFICATION OF CONTRACT 00001.pdf PDF
Question 1 25APR2025.docx DOCX document
Wage Deteminations.pdf PDF
RFQ for Construction_Sturgeon Bay Housing.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Department of Homeland Security United States Coast Guard Base Cleveland Housing Division

Scope of Work (SOW)

Housing Site Coast Guard Housing:

Sturgeon Bay WI 54235 For Interior Prep, prime, and paint

Point of Contact (POC) DC2 Michael Curtis (920)-510-3602 DCC Coyet Carter (614)-787-7309 Site Address 110 N 16th Drive Sturgeon Bay WI 54235 221 N 17th Drive Sturgeon Bay WI 54235 231 N 16th Place Sturgeon Bay WI 54235 337 N 16th Place Sturgeon Bay WI 54235

Scope of Work

1.1 The contractor is to prepare all surfaces to protect from paint spatter, drips, or accidental contact with the brush or roller, using drop cloths, masking tape or other appropriate means.

1.2 Remove any interference, (i.e., electrical cover plates, window cranks, window treatments, towel bars, stair handrails, light covers, smoke detectors, etc.). Stoves and refrigerators should be moved out far enough to facilitate painting behind them, but should remain hooked up to power, water, and gas connections.

1.3 All surfaces to be painted shall be properly prepared, (i.e., cleaned, sanded, feathered, puttied, primed, etc.) as necessary. Surface preparations will include the repair of damage to walls and ceilings, (i.e., splits, cracks, nail holes, chips, indentations, and holes less than eight inches in diameter). Damage greater than two inches in size shall be repaired by means of wall board plug with backer, taped and mudded, filled, sanded, and smooth; all other damaged areas will be repaired with wall mud as needed. All surfaces shall be free of dirt, grease, loose debris, and any other foreign matter that would adversely affect the appearance.

1.4 Where caulking is required, such as the kitchen/bathroom counters, trim work, and wall to ceiling joints, should be accomplished along with all other preparation work. Caulk will be furnished by the contractor and will be white in color and made of siliconized latex.

1.5 Contractor shall notify the POC listed upon completion of all preparation work before applying paint. After the POC has inspected and accepted the preparation work, paint may be applied.

1.6 A primer coat will be required on walls with different finishes or color change before any finish paint can be applied. Example: homes that have a semi-gloss finish will need a primer coat before applying an eggshell paint finish. The old color scheme was tan / beige walls with white trim, the new colors are Extra White without pigment all around.

1.7 Contractor shall paint all previously painted surfaces which include, but not limited to, walls, ceilings, and the trim around doors, windows, stairways, and baseboard heater covers with a minimum of two coat of paint for any area that has a paint color change and one coat for any area where the paint being applied matches existing color of the walls. Paint shall be applied carefully with clean rollers and brushes to produce a complete and even coverage with a smooth finish, free of runs and other defects. Window sashes should be removed and/or positioned to ensure no contact with the window frames until the paint is cured.

1.8 Spraying paint to surfaces is not allowed except for baseboard heat covers and trim pieces, this is not to be performed within the home.

1.9 After painting is completed, the POC needs to be notified to inspect and approve job completion is satisfactory prior to any items being reinstalled.

1.10 The contractor shall ensure that each home painted is left in a clean and orderly condition. All hardware, electrical, and plumbing accessories, to include items listed in 1.2, shall be reinstalled.

1.11 The contractor shall dispose of all waste materials properly and IAW EPA regulations at the contractor’s expense.

1.12 Approximate unit sizes are as listed with Gross and Net Square Ft.

· 110 N 16th Drive: 3 Bedroom, 2 Bath, Gross: 2,208 Sq Ft, Net: 1,200 Sq Ft.

· 221 N 16th Drive: 3 Bedroom 2 Bath, Gross: 2,328 Sq Ft, Net: 1,248 Sq Ft.

· 231 N 16th Place: 3 Bedroom 2 Bath, Gross: 2,328 Sq Ft, 1,248 Sq Ft.

· 337 N 16th Place: 3 Bedroom 2 Bath, Gross: 2,731 Sq Ft, 1,200 Sq Ft.

1.14 All units will become available on a VARIED TIMELINE; all units WILL NOT be available at the same time for work to be performed and contractor cannot wait until all units are available before starting work. There is currently 1 unit (110 N 16th Drive Sturgeon Bay WI 54235), is available for immediate work. All contractors work in the unit must commence within five days of notice from the units to the contractor. Each unit must be completed within a one-week (five working days) timeframe from the start date of that unit. If possible, the POC will give the contractor a 30-day notice prior to the availability date.

1.15 A site visit is highly encouraged to provide valuable insight into homes. Allowing the assessment of needs and condition of each unit to ensure quality and precise work. To schedule a site visit prior to commencing work and to accurately quote work needed, please contact the POC listed.

CG Personnel to complete

2.1 Moving the stove and refrigerator back into its normal operating position.

Material/ Part Information

3.1 All paint and tools shall be supplied by the Contractor. (Paint and Primer is Sherwin Williams brand: PrepRite ProBlock & ProMar 200 – Egg Shell finish for majority of the home and Semi-gloss or similar if above product is discontinued for bathrooms, utility rooms and kitchens. All Full Paint areas are transitioning to the color Extra White without pigment added.)

References

4.1 All work is to be completed shall comply with Federal, State and Local Laws, Codes and Regulations.

4.2 Manufactures’ requirements and recommendations shall be followed for all products used.

Liabilities

5.1 The contractor will be financially responsible for damages incurred while working on Government property. There will be a pre-work walkthrough with each contractor at each job site prior to the contract start and contractor must identify any damages in their work area that are pre-existing, or along their access route to their work area. (Doorways, Doors, Walls, Jambs, Flooring, etc.) Contractor must identify the pre-existing damage to the Local Housing Representative in writing and provide a copy of the signed document by both the contractor and the local housing representative dated for the start date of the work performed in said unit or they can be held liable for the damages.

Coordination

6.1 All communications will go through the Local POC listed. No work can be modified or changed without their permission.

6.2 Work to be completed should have minimal impact on the unit’s operation. In the event any of the utilities need to be secured, these items should be well planned out.

6.3 Normal work hours for the unit is 8:00 AM to 4:00 PM, Monday-Friday, excluding all Federal Holidays. Any work outside these times needs to be worked out ahead of time with any change in cost being highlighted upfront and confirmation by contracting officer will have to be approved as an amendment to the contract.

6.4 All required License, Certificates, Accreditation Card, etc. will be submitted with the quote or bid. There is also a minimum of two references being requested for submission with these documents.

Project Completion

7.1 All work completed must meet the local POC’s standard and be in accordance with this SOW. The site is to be at a minimum as clean of a condition it was found in. All trash, debris, materials removed, etc. should be properly disposed of by the contractor.

7.2 All units will become available on a VARIED TIMELINE; units WILL NOT be available at the same time for work to be performed and contractor cannot wait until all units are available before starting work. There is currently 1 unit (110 N 16th Drive Sturgeon Bay WI 54235), is available for immediate work. All contractors work in the unit must commence within five days of notice from the units POC to the contractor of the unit’s availability. All work must be completed within a one-week (five working days) timeframe from the start date of that unit. If possible, the POC will give the contractor a 30-day notice prior to the availability date.

Painting Locations References:

image3.jpeg image4.jpeg image5.jpeg image6.jpeg image7.jpeg image8.jpeg image1.png image2.png