Statement of Work
Overhaul of Chiller #1 at BLDG. #1 Asset ID: 640200B001
USDA-ARS
Stoneville, Mississippi
Prepared by:
Scott Feutz 26 April 2022
Reviewed by:
Kevin Magee 2 May 2022
Table of Contents
Location Map Page 3
Statement of Work Page 4
Contractor Responsibility Page 5
Project Schedule/Contacts Page 6
Location Map
Statement of Work: Contractor is to recover refrigerant and oil, pull compressors and overhaul including installation of new high and low speed bearings, cleaning oil sump, and installing recovered and filtered refrigerant, new oil filter and refrigerant filters. Reinstalling compressor and motor and performing startup.
Project Objective: The objective of this Project is to overhaul compressor for chiller no. 1 at Bldg.1 This Project is located at USDA-ARS JWDSRC, 141 Experiment Station Road and 59 Lee Road in Stoneville, MS.
Contractor must be registered in System for Award Management, (SAM), prior to submitting a bid. Registration can be obtained through:
https://www.beta.sam.gov
Site Visit: Bidders are encouraged to visit the site and be escorted by a government representative to confirm locations, dimensions, and conditions of the project before a bid is submitted. The site visit shall be for the purpose of observing firsthand any conditions relevant to the completion of this project. No consideration will be given to claims based on lack of knowledge of existing conditions, except where contract documents make definite provisions for adjustment in cost or extension due to existing conditions not readily foreseeable. This project is located at USDA-ARS in Stoneville, MS.
Utilization of Bio-Based Products: The contractor shall utilize products and material based from bio-based materials, (e.g. bio-based greases; bio-based hydraulic fluids, bio-based absorbents), to the maximum extent possible without jeopardizing the intended end use or detracting from the overall quality delivered to the end user.
All supplies and materials shall be of a type and quality that conform to the applicable Federal Specifications and Standards. All supplies and materials to be used in the performance of work described herein are subject to the approval of the Contracting Officer Representative (COR). Products can be found at:
https://www.biopreferred.gov
Safety: The contractor will submit a Site Safety Specific Plan/Accident Prevention Plan in industry recognizable format to the Contracting Officer within 7 days of contract award. The Plan shall include phone numbers and maps to the local Dr. Office and nearest Hospital.
Base Bid: Provide all equipment, labor, and materials necessary to Overhaul existing #1 Compressor to include:
1) Recovery of refrigerant and oil.
2) pull compressors and overhaul including installation of new high and low speed bearings.
3) cleaning oil sump and installing recovered and filtered refrigerant.
4) new oil filter and refrigerant filters.
5) Reinstalling compressor and motor and performing startup https://www.beta.sam.gov/ https://www.biopreferred.gov/
Contractor Responsibility:
1. Contractor will verify all dimensions and site conditions prior to beginning work.
2. Contractor will perform the work as listed in the above outlined Base Bid.
3. Contractor shall keep work area clean daily and take measures to control debris while work is being performed onsite.
4. Contractor is required to manage the project and consult with the Government prior to beginning all work phases. And, to work in a manner that minimizes the impact of the work on Government operations, research, and functions.
5. All work must be performed in such a manner as to not adversely affect daily operations of the facility, its workers, and the onsite facility operations.
6. Contractor must always have a Foreman on the job while working onsite on this project.
Material / Submittals:
The Contractor shall supply all materials necessary to successfully complete the project and deliver a functioning system as required. Submittals on all material incorporated into the work, including shop drawings and specifications, used on this project shall be submitted to the EPM and Contracting Specialist as noted in this document. Electronic submittals are acceptable otherwise three written submittals are required.
Demolition Procedure:
Contractor will verify all dimensions and site conditions prior to beginning work. Contractor will schedule the work between working hours as listed below. Contractor is required to provide labor, specified material, equipment, and other tools required to perform the job fully and completely. No Government equipment will be available for use by the contractor. The contractor shall always be responsible for protecting his work and ensuring the safety of his crew and ARS employees. Upon completion of the project, the contractor shall remove from the premises all accumulated materials and rubbish caused by the project. Premises shall be left in a clean, orderly, and acceptable condition.
Damage to Property:
Any damage to the Government buildings, utilities, etc. caused as the result of the contractor’s activities shall be repaired or replaced to the satisfaction of the Government.
Inspection and Acceptance:
A government representative shall inspect and approve the work performed on this project. The Contractor shall schedule inspection a minimum of 3 days in advance, in writing, to the Contracting Officer.
Project Schedule:
The completion of this project shall not exceed 60 days from date of Notice to Proceed. A request for time extension must be submitted to the Contracting Specialist in writing. Each request must include specific and detailed reasons in support of the schedule alteration.
Work Hours:
Contractor work hours shall be Monday through Friday, seven (7) A.M. to four (4) P.M. with the exception of Government holidays. Any changes to work schedule shall be submitted to Contacting Officer for written approval prior to schedule change.
Project Contacts:
Administrative Officer (AO)--TBA
Engineering Project Manager (EPM)--TBA
Location (POC)--TBA
To Be Determined, Contract Specialist USDA, ARS, Southeast Area Administrative Office Acquisitions, Personal Property & Fleet Management
| Site Visit: Bidders are encouraged to visit the site and be escorted by a government representative to confirm locations, dimensions, and conditions of the project before a bid is submitted. The site visit shall be for the purpose of observing first... |
| Site Visit: Bidders are encouraged to visit the site and be escorted by a government representative to confirm locations, dimensions, and conditions of the project before a bid is submitted. The site visit shall be for the purpose of observing first... |
| Material / Submittals: |
| Demolition Procedure: |
| Damage to Property: |
| Any damage to the Government buildings, utilities, etc. caused as the result of the contractor’s activities shall be repaired or replaced to the satisfaction of the Government. |
| Inspection and Acceptance: |
| Project Schedule: |
| Work Hours: |
| Project Contacts: |
| Administrative Officer (AO)--TBA |