SOW NORTHLAND Fuel System Offload and Cleaning.pdf
PDF 184 KB Posted
- Solicitation number
- 52000QR270000042
- Issued by
- Not on record
About this file
This is a Statement of Work (SOW) for fuel tank emptying and cleaning services on the CGC NORTHLAND, a 270-foot WMEC 'B' Class Coast Guard vessel.
The Contractor must remove approximately 20,200 gallons of marine grade diesel fuel from five tanks (four storage tanks and one service tank) and clean two designated tanks (Diesel Storage tank 4-82-2-F and Diesel Service tank 4-165-4-F), while the remaining three tanks require only emptying. The work includes furnishing and installing all protective measures, managing known interferences (fuel, piping, and tank access covers), and following Coast Guard Technical Spec D-123-2049 for fluid handling to maintain vessel stability. The Contractor must document a complete chain of custody record for all removed fluids and dispose of all removed materials in compliance with Federal, state, and local regulations. Tank cleaning must remove all foreign materials including residual fuel, water, sediment, sludge, rust, and biological growth without damaging existing coating systems. Tank closure requires notification to the Contracting Officer at least 24 hours prior, accomplished in the presence of a Coast Guard Inspector, with new gasket material conforming to AMS-C-6183 and renewal of 100% of nuts and washers. The Contractor must witness initial and post-repair operational tests of tank level indicators and vent check valves, maintain plug logs for each tank entered, and submit Contractor Furnished Reports (CFRs) documenting all operational tests. Work is scheduled for October 20-23, 2026, at CGC NORTHLAND, 4000 Coast Guard Boulevard, Portsmouth, Virginia 23703. Coast Guard personnel will operate all shipboard machinery and equipment throughout the project.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 52000QR270000042 FAR CLAUSES.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
12300_ESD_1022_FLT
REC_12311_FLT_270’ WMEC ‘B’ Class (ALL) (1022)
WORK ITEM 1: Tanks, MP Fuel Stowage and Service, Empty and Clean
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to remove approximately 20,200 gallons of marine grade diesel and clean 02 tank(s):
TANK GROUP
TYPE OF TANK LOCATION
CURRENT LEVEL
(GALLONS)
Diesel Storage 4-82-1-F 3,960
Diesel Storage 4-82-2-F 3,670
Diesel Service 4-165-3-F 2,050
Diesel Service 4-165-4-F 2,480
Diesel Storage 4-207-2-F 7,960
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 901 WMEC 113-001, Rev E, Tank Top PL & FR Fwd FR 101
Coast Guard Drawing 901 WMEC 113-002, Rev A, Tank Top Pltg & Framing Aft 182
Coast Guard Drawing 901 WMEC 116-001, Rev D, CVK Fwd 101 & Girder Long 2
Coast Guard Drawing 901 WMEC 116-002, Rev B, CVK Aft 182
Coast Guard Drawing 901 WMEC 121-001, Rev D, Long Tank Bhds Aft 182
Coast Guard Drawing 901 WMEC 122-002, Rev H, Transv Bhds 47, 78 & 82
Coast Guard Drawing 901 WMEC 122-004, Rev F, Transv Bhds 165, 169, 151.6
Coast Guard Drawing 901 WMEC 122-005, Rev F, Transv Bhds 186 & 190
Coast Guard Drawing 901 WMEC 122-006, Rev F, Transv Bhds 196, 207, 228, 242
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and Allied Processes
OTHER REFERENCES
Federal Specification (Fed Spec) QQ-N-281, Oct 1985, Nickel-Copper Alloy Bar, Rod, Plate, Sheet, Strip, Wire, Forgings, and Structural and Special Shaped Sections
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C-6183B, 2019, Cork and Rubber Composition Sheet; for Aromatic Fuel and Oil Resistant Gaskets
3. REQUIREMENTS
3.1 General.
3.1.1 CIR.
Not applicable.
3.1.2 Tech Rep.
Not applicable.
3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).
3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the below-listed:
• Fuel
• Piping
• Tank access cover
3.1.4.1 The Contractor must follow the fluid handling plan in accordance with Coast Guard Technical
Spec D-123-2049 when moving fluid between tanks to ensure adequate stability of the vessel.
3.1.4.2 Remove up to a total of 20,200 gallons of fuel. Document a complete chain of custody record of the removed tank contents from the vessel to the point of final destination or delivery. Submit document to the COR upon completion of work.
3.1.4.3 Dispose of removed fluids in accordance with all applicable Federal, state, and local regulations.
NOTE
Coast Guard personnel will operate all shipboard machinery and equipment.
3.2 Operational test, initial. Prior to commencement of work, the Contractor must witness Coast Guard personnel perform an initial operational test of the equipment listed below to demonstrate existing operational condition. Submit a CFR.
• TLI for tanks
3.3 Plug log. The Contractor must keep a written record of all plugs put in any tank vents. A separate list must be kept for each tank being entered.
3.3.1 Ensure that all plugs are removed from each tank upon completion of work in the tank.
3.3.2 The plug log must be available to the Coast Guard Inspector when the inspector is performing his close-out inspection on each tank.
3.4 Cleaning requirements. The Contractor must refer to the Coast Guard Drawings listed under Section
2 (References) for guidance in accomplishing this work. The Contractor must remove tank cover(s) and clean tank interior surfaces free of all foreign materials, such as residual fuel or water, sediment, sludge, rust, or biological growth, taking care not to damage the coating system (if applicable). Remove cleaning media and residues continuously during the washing process. Remove any residual wash media; and wipe up residual moisture with clean lint-free cloths.
3.5 Tanks to be cleaned. Only the flowing tanks have to be cleaned. All other tanks listed in the tank group need to be emptied.
Tanks to be Cleaned
Diesel Storage 4-82-2-F
Diesel Service 4-165-4-F
3.5 Tank content and waste disposal. The Contractor must dispose of residual tank contents and any cleaning fluids in compliance with all applicable Federal, state, and local laws, ordinances and regulations. Document a complete chain of custody record of the removed tank contents and generated wastes, from the vessel to the point of final destination or delivery. Submit document to the COR upon completion of work.
3.6 Tank closing. Notify the COR at least 24 hours prior to closing the tank(s) and ensure tank closure is accomplished in the presence of the Coast Guard Inspector. After satisfactory inspection by the Coast
Guard Inspector, close tank manhole cover(s) with new gasket material conforming to AMS-C-6183.
Chase threads on studs to ensure even installation of the access covers.
3.6.1 The Contractor must renew 100% of nuts and washers.
3.7 Operational test, post repairs. After completion of work and in the presence of the Coast Guard
Inspector, the Contractor must thoroughly test and demonstrate the equipment listed below to be in satisfactory operating condition. Submit a CFR.
• Designated tank TLIs
• Vent check valves
NOTE
Coast Guard personnel will operate all shipboard machinery and equipment.
4. NOTES
4.1 Tank inspection. The Coast Guard Inspector will visually inspect the tank interior immediately prior to closing.
4.2 Tank content restoration. The Ship’s force will procure new fluids and refill all tanks at the appropriate time.
4.3 Work location. The work will be performed at the following address:
CGC NORTHLAND
4000 Coast Guard Blvd
Portsmouth, VA 23703
4.3 Period of performance. Work is to be conducted between 20 Oct and 23 Oct 2026.
4.5 Point of contract. Please contact LTJG Nate Pierce at Nathan.R.Pierce@uscg.mil with questions regarding this SOW.