SOW - NG Rotors.docx

DOCX document 88 KB Posted

Attached to
41-0378 Sources Sought- Rotors, Overhaul Kits, Technical Support
Solicitation number
N64498-23-RFPREQ-PD-41-0378
Issued by

About this file

This Statement of Work (SOW) details a naval contract for High Pressure (HP) and Low Pressure (LP) turbine rotor procurement, overhaul, and technical support for LHD-1 through LHD-4 vessels, issued by the Naval Surface Warfare Center Philadelphia Division (NSWCPD) Code 412's Steam Critical Spares Program. The contract requires the contractor to provide new Northrop Grumman HP and LP turbine rotors, multiple 2SCOG overhaul kits for various turbine components, and refurbishment services including inspection, repair, and technical assistance.

Key deliverables include specific rotor part numbers (e.g., STBD HP Turbine Rotor P/N 615F848, Port HP Turbine Rotor P/N 615F781, LP Turbine Rotor P/N 6165294) and comprehensive overhaul kits with dozens of specialized components. The contractor must open and inspect government-provided rotors, provide repair assessment reports, and restore rotors to a minimum Condition "B" Ready for Issue (RFI) status. The work will be performed 100% at the contractor's facility, with on-site technical assistance required. The anticipated procurement is a sole-source award to Northrop Grumman Systems Corporation in Sunnyvale, CA, with market research responses due by 6:00 PM EST on 13 June 2025.

View the file

Other files

File Type Posted
Sources Sought_NG Rotors.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work (SOW)) for LHD-1 through LHD-4 High Pressure and Low Pressure Rotors, 2SCOG Overhaul Kits, Refurbishment, and Technical Assistance

1.0 INTRODUCTION

1.0.1 The Naval Surface Warfare Center Philadelphia Division (NSWCPD) is a Department of Defense entity responsible for research and development, test and evaluation, engineering and fleet support organization for the Navy’s ships, submarines, military watercraft and unmanned vehicles. This requirement is for NSWCPD Code 412, which is responsible for Steam Critical Spares Program.

1.0.2 This contract is for non-personal services. It does not create employment rights with the U.S. Government whether actual, inherent, or implied

1.0.3 Government/Contractor Relationship

1.0.3.1 The services to be delivered under this Contract are non-personal services and the parties recognize and agree that no employer-employee relationship exists or will exist under the Contract between the Government and the Contractor's personnel. Therefore, it is in the best interest of the Government to provide both parties a full understanding of their respective obligations.

1.0.3.2 The Contractor employees shall identify themselves as Contractor personnel by introducing themselves or being introduced as Contractor personnel and displaying distinguishable badges or other visible identification for meetings with Government personnel. In addition, Contractor personnel shall appropriately identify themselves as Contractor employees in telephone conversations and in formal and informal written correspondence.

1.0.3.3 Contractor personnel under this Contract shall not engage in any of the inherently Governmental functions listed at FAR Subpart 7.5 or DFARS Subpart 207.5.

1.0.4 Employee Relationship:

1.0.4.1 The services to be performed under this Contract do not require the Contractor or its personnel to exercise personal judgment and discretion on behalf of the Government. Rather the Contractor's personnel will act and exercise personal judgment and discretion on behalf of the Contractor.

1.0.4.2 Rules, regulations, directives, and requirements that are issued by the U. S. Navy and NSWCPD under its responsibility for good order, administration, and security are applicable to all personnel who enter a Government installation or who travel on Government transportation. This is not to be construed or interpreted to establish any degree of Government control that is inconsistent with a non-personal services contract.

1.0.4.3 Inapplicability of Employee Benefits: This Contract does not create an employer-employee relationship. Accordingly, entitlements and benefits applicable to such relationships do not apply.

1.0.4.4 It is the Contractor's, as well as the Government's, responsibility to monitor Contract activities and notify the Contracting Officer if the Contractor believes that the intent of this Section has been or may be violated.

1.0.4.4.1 The Contractor shall notify the Contracting Officer in writing via letter or email within three (3) calendar days from the date of any incident that the Contractor considers to constitute a violation of this Section. The notice should include the date, nature, and circumstances of the conduct; the name, function, and activity of each Government employee or Contractor official or employee involved or knowledgeable about such conduct; identify any documents or substance of any oral communication involved in the conduct; and the Contractor's estimated date when, absent a response, cost, schedule or performance will be impacted.

1.0.4.4.2 The Contracting Officer will, within five (5) calendar days after receipt of notice, respond to the notice in writing. In responding, the Contracting Officer will either:

(i)Confirm the conduct is in violation and when necessary direct the mode of further performance,
(ii)Countermand any communication regarded as a violation,
(iii)Deny that the conduct constitutes a violation and when necessary direct the mode of further performance, or
(iv)In the event the notice is inadequate to make a decision, advise the Contractor what additional information is required, and establish the date by which it should be furnished by the Contractor.

1.1 BACKGROUND

The Steam Systems Branch (Code 412) of the Naval Surface Warfare Center, Philadelphia Division (NSWCPD), provides Amphibious Surface Ship Steam Propulsion Plant Equipment Engineering, Inspection/Assessment, Procurement, Overhaul, Refurbishment, logistics support, and life cycle support to accomplish Life Cycle Engineering and Critical Spares Equipment Rotatable Pool Management.

1.2 SCOPE OF WORK

Work performed will support the Fleet and associated DOD Activities and focus on Steam Propulsion Plant Northrup Grumman High Pressure (HP) and Low Pressure (LP) rotors and associated components. This may include support for associated NAVSEA Program Manager- initiated tasking for NSWCPD supporting fabrication and creation of Ready for Issue (RFI) FDB rotors and associated overhaul kit equipment under Fleet steam critical spares and NAVSEA 2S COG Programs.

NSWCPD Code 107 will house and be responsible for RFI and Non-RFI Spares. The contractor shall provide temporary material staging areas for non-RFI items and critical spares in various conditions. The contractor shall provide equipment shipping and receiving services to CONUS destinations including NSLC warehouses located in Philadelphia, PA and Virginia Beach, VA. The contractor will perform identification, condition assessments, and labeling as per the direction of a Government representative. The contractor will provide list(s) of repair parts required to make equipment, systems and materials Ready for Issue (RFI).

The contractor shall provide skilled technical personnel who are capable of developing High Pressure and Low Pressure Propulsion Turbine Rotors and associated equipment work items for engineering, inspection, maintenance, overhaul, and repair, and fabrication.

2.0 APPLICABLE DOCUMENTS

2.1Port HP Turbine Drawing 851A367 and associated sub-drawings
2.2Stbd HP Turbine Drawing 851A358 and associated sub-drawings
2.3Port LP Turbine Drawing 851A368 and associated sub-drawings
2.4Stbd LP Turbine Drawing 851A359 and associated sub-drawings
2.5MIL-T-17523D, Turbine, Steam, Auxiliary (and Reduction Gear) Mechanical Drive
2.6S9234-G7-OMI-010, Main Propulsion Turbines Propulsion Unit
2.7NAVSEA S9074-AR-GIB-010/278, Requirements for Fabrication Welding and Inspection, and Casting Inspection and Repair for Machinery, Piping, and Pressure Vessels

The Contractor shall reference and utilize the latest version available when performing tasks within this PWS.

3.0. REQUIREMENTS

3.1HP and LP Turbine Rotor Procurement
3.1.1The Contractor shall provide new NG Model HP and LP Turbine Rotor units per reference 2.1 and 2.7. Associated part numbers are below.
3.1.1.1 STBD HP Turbine Rotor (P/N 615F848)
3.1.1.2 Port HP Turbine Rotor (PN 615F781)
3.1.1.3 LP Turbine Rotor (P/N 6165294)

3.2 HP and LP Turbine 2SCOG Overhaul Kits

3.2.1 The Contractor shall provide Condition “A” new 2SCOG PORT HP Turbine Overhaul kits (P/N 2007018643) to include the below material per references 2.1 through 2.7.

3.2.1.1 Parts Kit consist for the following material:

Part Number
Description
Qty
522C011680
GASKET
2
465313
BEARING, THRUSTASSEMBLY
1
42036
TERMINAL BLOCK, 2 CONDUCTOR, SOLDER TERM
2
615F843G01
BEARING
1
524C929H01
FILLER RING
1
524C930H01
FILLER RING (SOLID)
1
941C266H01
BAFFLE
1
524C920H03
GASKET 3.50 X 3.50 X .03 THK
3
360B893H01
BUSHING - NITRILE
3
523C592H01
LINER
4
615F809G01
BEARING TURBINE(T.E.)
1
615F510H01
RING, 15.25 OD X 7.62 ID X 1.62 THK
1
615F519H01
RING, 13.25 OD X 7.68 ID X 1.50 THK
1
615F511H01
RING, 13.25 OD X 7.50 ID X 2.00 THK
1
615F522H01
RING, 13.25 OD X 8.50 ID X 2.75 THK
1
615F723H01
RING, 13.25 OD X 8.50 ID X 4.85 THK
1
615F724H01
RING, 13.25 OD X 7.75 ID X 3.75 THK
1
849A710G01
SEAL RING GLAND
1
849A710G02
SEAL RING GLAND
1
849A710G03
SEAL RING GLAND
1
849A710G04
SEAL RING GLAND
1
849A710G05
SEAL RING GLAND
1
849A710G06
SEAL RING GLAND
1
849A710G07
SEAL RING, GLAND
1
387B155H01
BEARING DEPTH PLATE
2
522C615024
DRIVE SCREW TYPE U #2
16
522C706451
STUD,BOTMG TYPE .625 X 6.38 LG
2
522C707453
STUD, BOTTOMING, .750-10 X 6.62 LG
2
522C706423
STUD,BOTMG TYPE .625 X 2.88 LG
6
385B714H01
PLUG
2
522C900010
NUT, HEX, COARSE, .625 NOM
14
385B708H01
SPACER
2
385B715H01
NUT, SPECIAL (1.125)
2
522C710442
STUD BTMG TYPE,1.125- 8UN-2A X 5.25 LG
2
522C706051
STUD,BOTMG TYPE .625 X 6.38 LG
2
522C706071
STUD,BOTMG TYPE .625 X 8.88 LG
2
522C707024
STUD, BOTTOMING, .750-10 X 3.00 LG
12
522C507060
SCREW, HEX CAP, .750- 10UNC-2A X 2.00
8
522C012091
GASKET .75-900#
1
386B034030
SCKT HD CAP SCREW
4
386B084030
SCREW, CAP, SKT HD, .750- 10 X 2.00
6
524C759H02
PIN,TAPER SPCL, .62 DIA X 1.72 L
4
522C707025
STUD, BOTTOMING, .750-10 X 3.12 LG
16
522C900112
NUT, HEX COARSE, .750 NOM
30
522C011614
GASKET
2
386B055026
SCREW, CAP, SKT. HD., .750-10 X 2.00
6
524C759H04
PIN,TAPER SPCL, .62 DIA X 2.00 L
2
522C011621
GASKET
2
522C710240
STUD BTMG TYPE,1.125- 8UN-2A X 5.00 LG
8
522C306224
STUD-DOWELL BOTTOMING TYPE 1.500 DIA
4
522C900118
NUT, HEX, 8 THREAD, 1.125 NOM
48
526C541223
BOLT-STUD CONTINOUS THREAD 1.125-8UN-2A
8
522C348226
BOLT-DOWEL 1.500 DIA X 6.50 MAX LG
4
522C011602
GASKET,PART# ON DWG LIST 2 MATL TYPES.
1
522C900120
NUT, HEX, 8 THREAD, 1.250 NOM
12
386B204010
NUT, DOUBLE HEX, SLF LKG, .625-18
24
386B072024
SCREW, CAP, HEX SKT HD, .625-18UNF X 2.8
24
849A710G08
SEAL RING GLAND
1

3.2.2 The Contractor shall provide Condition “A” new 2SCOG STDB HP Turbine overhaul kits (P/N 2007018641) to include the below material per references 2.1 through 2.14.

3.2.2.1 Parts kits include the following material:

Part Number
Description
Qty
360B893H01
BUSHING - NITRILE
3
385B708H01
SPACER
2
385B714H01
PLUG
2
385B715H01
NUT, SPECIAL (1.125)
2
386B034030
SCKT HD CAP SCREW
4
386B055026
SCREW, CAP, SKT. HD., .750-10 X 2.00
6
386B072024
SCREW, CAP, HEX SKT HD, .625- 18UNF X 2.8
24
386B084030
SCREW, CAP, SKT HD, .750-10 X 2.00
6
386B204010
NUT, DOUBLE HEX, SLF LKG, .625-18
24
387B155H01
BEARING DEPTH PLATE
2
42036
TERMINAL BLOCK, 2 CONDUCTOR, SOLDER TERM
2
465313
BEARING, THRUST, ASSEMBLY
1
522C011602
GASKET,PART# ON DWG LIST 2 MATL TYPES..
1
522C011621
GASKET
2
522C011680
GASKET
2
522C012091
GASKET .75-900#
1
522C306224
STUD-DOWELL BOTTOMING TYPE 1.500 DIA
4
522C348226
BOLT-DOWEL 1.500 DIA X 6.50 MAX LG
4
522C507060
SCREW, HEX CAP, .750-10UNC- 2A X 2.00
8
522C615024
DRIVE SCREW TYPE U #2
16
522C706051
STUD,BOTMG TYPE .625 X 6.38 LG
2
522C706071
STUD,BOTMG TYPE .625 X 8.88 LG
2
522C706423
STUD,BOTMG TYPE .625 X 2.88 LG
6
522C706451
STUD,BOTMG TYPE .625 X 6.38 LG
2
522C707024
STUD, BOTTOMING, .750-10 X 3.00 LG
12
522C707025
STUD, BOTTOMING, .750-10 X 3.12 LG
16
522C707453
STUD, BOTTOMING, .750-10 X 6.62 LG
2
522C710240
STUD BTMG TYPE,1.125-8UN-2A X 5.00 LG
8
522C710442
STUD BTMG TYPE,1.125-8UN-2A X 5.25 LG
2
522C900010
NUT, HEX, COARSE, .625 NOM
14
522C900112
NUT, HEX COARSE, .750 NOM
30
522C900118
NUT, HEX, 8 THREAD, 1.125 NOM
48
522C900120
NUT, HEX, 8 THREAD, 1.250 NOM
12
523C592H01
LINER
4
524C759H02
PIN,TAPER SPCL, .62 DIA X 1.72 L
4
524C759H04
PIN,TAPER SPCL, .62 DIA X 2.00 L
2
524C920H03
GASKET 3.50 X 3.50 X .03 THK
3
524C929H01
FILLER RING
1
524C930H01
FILLER RING (SOLID)
1
526C541223
BOLT-STUD CONTINOUS THREAD 1.125-8UN-2A
8
615F510H01
RING, 15.25 OD X 7.62 ID X 1.62 THK
1
615F511H01
RING, 13.25 OD X 7.50 ID X 2.00 THK
1
615F519H01
RING, 13.25 OD X 7.68 ID X 1.50 THK
1
615F522H01
RING, 13.25 OD X 8.50 ID X 2.75 THK
1
615F723H01
RING, 13.25 OD X 8.50 ID X 4.85 THK
1
615F724H01
RING, 13.25 OD X 7.75 ID X 3.75 THK
1
615F809G01
BEARING TURBINE (T.E.)
2
849A710G01
SEAL RING GLAND
1
849A710G02
SEAL RING GLAND
2
849A710G03
SEAL RING GLAND
1
849A710G04
SEAL RING GLAND
1
849A710G05
SEAL RING GLAND
1
849A710G06
SEAL RING GLAND
1
849A710G07
SEAL RING, GLAND
1
849A710G08
SEAL RING GLAND
1
941C266H01
BAFFLE
1

3.2.3 The Contractor shall provide Condition “A” new 2SCOG STDB LP Turbine overhaul kits (P/N 2007018656) to include the below material per references 2.1 through 2.14.

3.2.3.1 Parts kits include the following material:

Part Number
Description
Qty
849A710G45- MOD
SEAL RING COMPLETE - UPDATED DESIGN
1
849A710G44- MOD
SEAL RING COMPLETE - UPDATED DESIGN
1
849A710G43- MOD
SEAL RING COMPLETE - UPDATED DESIGN
1
849A710G42- MOD
SEAL RING COMPLETE - UPDATED DESIGN
1
849A710G41- MOD
SEAL RING COMPLETE - UPDATED DESIGN
1
386B054042
SCREW, CAP, HEX SOCKET HEAD .625-11 X 4.
4
386B053034
SCREW, CAP, SKT. HD., .500- 13 X 3.00
24
523C717H01
PIN DOWEL SPECIAL
4
522C675178
SET SCREW OP .625 X 1.25
4
385B972H01
LOCK PLATE
16
386B012018
WASHER LOCK, 1.125 NOM.
4
386B012024
WASHER LOCK, 1.500 NOM.
8
616F275-01
RETAINER RING GLAND
1
849A710G22
SEAL RING COMPLETE
1
616F277H01
RETAINER RING GLAND
1
616F278H01
RETAINER RING GLAND
1
849A710G23
SEAL RING COMPLETE
1
849A710G24
SEAL RING COMPLETE
1
849A710G25
SEAL RING COMPLETE
1
849A710G21
SEAL RING COMPLETE
1
849A710G17
SEAL RING
2
616F281H01
RETAINER RING DUMMY
1
386B300020
SCREW, DIAPHRAGM RETAINING, .5-13 UNC-2A
2
1393F96H01
RETAINER RING GLAND
1
1393F98-01
RETAINER, GLAND RING
1
1393F97H01
RETAINER RING GLAND
1
386B073038
SCREW, SOC HD SPEC BODY, 3.75 LG.
12
386B204012
NUT, DOUBLE HEX, SLF LKG, .750-16
12
616F175G01
BEARING TURBINE
2
524C920H03
GASKET 3.50 X 3.50 X .03 THK
3
615F369H04
SEAL RING, OIL
2
524C929H03
FILLER RING
2
360B893H01
BUSHING - NITRILE
3
7518E88-011
PACKING, SQUARE,.375 SQ. X 66.0 LG
4
91211A224
SCREW,HEX,NYLON PATCH LOCK,3/4-10 X 2.50
30
6D59526-001
GASKET, F712100
1
6D59526-002
GASKET, F712100
1
386B072024
SCREW, CAP, HEX SKT HD, .625-18UNF X 2.8
24
386B204010
NUT, DOUBLE HEX, SLF LKG, .625-18
24
522C011680
GASKET
2
387B155H01
BEARING DEPTH PLATE
2
522C615024
DRIVE SCREW TYPE U #2
16
522C011621
GASKET
4
522C011602
GASKET,PART# ON DWG LIST 2 MATL TYPES..
4
522C710240
STUD BTMG TYPE,1.125-8UN- 2A X 5.00 LG
8
522C306224
STUD-DOWELL BOTTOMING TYPE 1.500 DIA
4
522C900118
NUT, HEX, 8 THREAD, 1.125 NOM
48
526C541223
BOLT-STUD CONTINOUS THREAD 1.125-8UN-2A
8
522C504108
SCREW, HEX CAP, .500- 13UNC, 1.50 LG
4
522C900120
NUT, HEX, 8 THREAD, 1.250 NOM
12

12/03/2024 In Reply Refer to: MLS Quotation 24-MLS-010

3.2.4 The Contractor shall provide Condition “A” new 2SCOG STDB HP Turbine Steam Chest overhaul kits (P/N 2007018656) to include the below material per references 2.1 through 2.14.

3.2.4.1 Parts kits include the following material:

Part Number
Description
Qty
385B940H01
SHIM
2
386B012020
WASHER LOCK, 1.250 NOM.
3
386B225055
PIN-COTTER, .187 NOM. DIA. X 1.5 L
6
387B152H01
THRUST DISC UPPER,2.875 DIA
2
387B153H01
THRUST DISC LOWER
2
387B163H01
WASHER, LOCK
5
387B165H01
NUT, ADJUSTING
5
387B169H01
NUT, HEX (SPECIAL)
2
522C034110
PIN-DOWEL .1875 NOM X 2.000 LG
2
522C034130
PIN-DOWEL .2500 NOM X 2.500 LG
3
522C038127
PIN-DOWEL .2500 X 1.750
2
522C506068
SCREW-HEX CAP .625- 11UNC, 4.00 NOM
4
522C900224
NUT, HEX, 8 THREAD, 1.500 NOM
18
522C900310
NUT, HEX, COARSE, .625-11 UNC-2B
12
522C905220
NUT, HEX, FINE THREAD SERIES 1.250 NOM
5
523C108H01
ROD LIFTING,2.38 DIA X 25.50 LG.
2
523C151H02
BUSHING,2.75 DIA X 5.25 LG
2
523C167H01
VALVE, RGH. MACH.
3
523C551H02
BUSHING
2
523C555H01
VALVE, RGH MACH.
1
523C557H01
VALVE
1
523C727H01
EXPANSION RING
3
523C729H01
EXPANSION RING
2
523C973H01
BUSHING,2.25 DIA X 2.25 LG
2
523C975H01
BUSHING,1.50 DIA X 1.50 LG.
6
526C557219
BOLT-STUD,625-11UNC- 2A,DIA,4.75 MAX LG
4
526C609082
STUD, BOTTOMING TYPE 1.500-8 UN-2A, 10.2
9
615F608H02
RING, PRESSURE SEAL
9
615F608H03
RING, PRESSURE SEAL
6
615F968H01
VALVE SEAT (2.00)
3
615F970H01-970
VALVE SEAT OVERSIZED
1
615F972H01
VALVE SEAT (2.75)
1
3.3HP Rotor Refurbishment
3.1.1The Contractor shall open and inspect government provided HP rotors
3.1.2The Contractor shall provide a report of funds and repairs needed
3.1.3The Contractor shall overhaul and repair the HP rotor to a minimum of Condition “B” RFI status for inclusion in the Steam Critical Spares Program
3.4LP Rotor Refurbishment
3.2.1The Contractor shall open and inspect government provided LP rotors
3.2.2The Contractor shall provide a report of funds and repairs needed
3.2.3The Contractor shall overhaul and repair the HP rotor to a minimum of Condition “B” RFI status for inclusion in the Steam Critical Spares Program

3.5 HP and LP Rotor Re-install Technical Assistance

3.3.1The Contractor shall provide on-site assistance to Code 412 ISEAs during turbine overhauls and repairs
3.3.2The Contractor shall provide a report of findings and assistance provided
3.6HP and LP Turbine Drawings
3.4.1The Contractor shall provide Northrup Grumman Drawings (Reference 2.1 through 2.5) to allow for ISEA inspection of all material received.

3.2 Commonality of Systems, Subsystems, and Components

3.2.1 In line with C-211-H019 Commonality and Standardization (NAVSEA), contractors are directed to develop and implement a Commonality and Standardization Plan. When selecting equipment/components, the Contractor shall utilize NAVSEA Enterprise Commonality Virtual Shelf (VS) (https://www.pdrep.csd.disa.mil/default.htm) before other tools.

3.3 Manufacturing Phase-Out or Discontinuation of Production, Diminishing Sources, and Obsolete Materials or Components

3.3.1 The contractor shall notify the contracting officer immediately upon determining the unavailability of obsolete materials or components. The contractor may recommend a solution to include the impact on the contract price and delivery. The contractor shall not initiate any item redesign or incur any additional costs without the express, written authorization of the contracting officer.

3.4 Diminishing Manufacturing Sources and Material Shortages Management (DMSMS) Contract Requirements

N/A

3.5 Parts Obsolescence

3.5.1 The contractor shall establish and implement a parts obsolescence program. In the event that manufacturing phase-out or discontinuance of production of such items is contemplated, the contractor is required to notify the contracting officer and publish the discontinuance in the Government-Industry Data Exchange Program (GIDEP), where feasible; and to provide immediate advance notice of production phase-out to ____NSWCPD Code 412____.

4.0 DATA REQUIREMENTS

· CDRL A001, Contract Status Report

· CDRL A002, Government Property Inventory Report (FINAL)

· CDRL A003, Condition Found Report

· CDRL A004, Counterfeit Prevention Plan

· CDRL A005, Systems Security Plan

· CDRL A006, Unauthorized Supplier Purchase Report

· CDRL A007, HP and LP Turbine Drawings for ISEA Inspections

5.0 SECURITY REQUIREMENTS (Ensure this section matches Security Office’s input)

5.1 SECURITY TRAINING.

5.2 ON SITE WORK.

N/A

5.3 DD254 REQUIREMENT.

N/A

5.4 OPERATIONS SECURITY (OPSEC)

5.4.1 The Contractor shall protect critical information associated with this contract to prevent unauthorized disclosure. The NSWC Philadelphia Division's (NSWCPD) Critical Information List (CIL)/ CIIL (Critical Indicators and information list) will be provided on site, if warranted. Performance under this contract requires the contractor to adhere to OPSEC requirements. The Contractor may not impose OPSEC requirements on its subcontractors unless NSWCPD approves the OPSEC requirements. During the period of this contract, the Contractor may be exposed to, use, or produce, NSWCPD Critical Information (CI) and/or observables and indicators which may lead to discovery of CI. NSWCPD’s CI will not be distributed to unauthorized third parties, including foreign governments, or companies under Foreign Ownership, Control, or Influence (FOCI) unless such FOCI has been appropriately mitigated through measures approved by the Defense Counterintelligence and Security Agency. Questions concerning these requirements shall be directed to the PCO.

5.4.2 CUI correspondence transmitted internally on the contractor's unclassified networks or information systems, and externally, shall be protected per NIST SP-800-171, Protecting Controlled Unclassified Information (CUI) in Non-federal Systems and Organizations.

Assembled large components/systems being transported to and from testing areas, other production or government facilities (whether or not on public roadways) shall be in an enclosed van trailer or covered flatbed trailer. Component/System outside storage, staging, and test areas shall be shielded/obscured from public view wherever physically possible.

5.4.3 NSWCPD’s CI shall not be publicized in corporate wide newsletters, trade magazines, displays, intranet pages or public facing websites. Media requests related to this project shall be directed to the PCO, and the COR who will forward the required to the NSWCPD Public Release Authority for review.

5.4.4 Any attempt by unauthorized third parties to solicit, obtain, photograph, or record, or; incidents of loss/compromise of government Classified or CI, Business Sensitive, Company Proprietary information related to this or other program must be immediately reported to the contractor's Facility Security Officer and Cognizant Security Office and/or the Naval Criminal Investigative Service, and the NSWC PD Security Division (Code 105).

5.5 RECEIPT, STORAGE, AND GENERATION OF CONTROLLED UNCLASSIFIED INFORMATION (CUI) All Controlled Unclassified Information (CUI) associated with this contract must follow the minimum marking requirements of DoDI 5200.48, Section 3, paragraph 3.4.a, and include the acronym "CUI" in the banner and footer of the document. In accordance with DoDI 5200.48, CUI must be safeguarded to prevent Unauthorized Disclosure (UD). CUI export controlled technical information or other scientific, technical, and engineering information must be marked with an export control warning as directed in DoDI 5230.24, DoDD 5230.25, and Part 250 of Title 32, CFR. Nonfederal information systems storing and processing CUI shall be protected per NIST SP-800-171, or subsequent revisions. All transmissions to personal email accounts (AOL, Yahoo, Hotmail, Comcast, etc.) and posting on social media websites (Facebook, Instagram, Twitter, LinkedIn, etc.) are prohibited. Destroy CUI associated with this contract by any of the following approved methods: A cross-cut shredder; a certified commercial destruction vendor; a central destruction facility; incineration; chemical decomposition; pulverizing, disintegration; or methods approved for classified destruction.

5.6 PLANNING, PROGRAMMING, BUDGETING AND EXECUTION (PPBE) DATA.

When contractor employees, in the performance of their duties, are exposed to Planning, Programming, Budgeting and Execution (PPBE) data, a Non-Disclosure Agreement (NDA) with all affected contactor personnel must be executed in coordination with the COR and PCO to ensure safeguarding disclosure of this data.

5.7 U-NNPI SECURITY REQUIREMENTS

N/A

5.8 U-NNPI

N/A

5.9.2 Specific Requirements for Protecting U-NNPI

6.0 PLACE OF PERFORMANCE

6.1 100% of the work performed will be at the contractor’s facility.

7.0 TRAVEL

8.0 GOVERNMENT FURNISHED PROPERTY

N/A

9.0 GOVERNMENT FURNISHED INFORMATION

N/A

10.0 PURCHASES

N/A

11.0 COUNTERFEIT MATERIAL PREVENTION

11.1 Electronic End-Items

N/A

11.2 Non-Electronic Materials

11.2.1 Department of the Navy contractors (and their subcontractors at all tiers) who obtain critical or high risk materiel shall implement a risk mitigation process as follows:

11.2.1.1 If the materiel is currently in production or currently available, materiel shall be obtained only from authorized suppliers

11.2.1.2 If the materiel is not in production or currently available from authorized suppliers, materiel shall be obtained from suppliers that meet appropriate counterfeit avoidance criteria

11.2.1.3 Contractor shall notify the contracting officer when critical or high risk materiel cannot be obtained from an authorized supplier;

11.2.1.4 Contractor shall take mitigating actions to authenticate the materiel if purchased from an unauthorized supplier

11.2.1.5 Contractor shall report instances of counterfeit and suspect counterfeit materiel to the contracting officer and the GIDEP as soon as the contractor becomes aware of the issue.

12.0 PERSONNEL

N/A

13.0 NSWCPD ELECTRONIC COST REPORTING AND FINANCIAL TRACKING (ECRAFT) SYSTEM

14.0 SPECIAL REQUIREMENTS

14.1 Quality Management System

Clause FAR 52.246-11, Higher-Level Contract Quality Requirement and E-246-H020, Quality Management System when requiring higher level contract QMS like ASQ/ANSI/ISO 9001

· Reminder to invoke CDRL for Quality Assurance Workbook (QAWB)

· A QAWB is required to be submitted to NSWCPD 30 days prior to start of work

· A copy of the completed test and inspection (T&I) plan and associated OQE (contained in the QAWB) shall be submitted to the AIT Manager within 14 days of installation completion)

0. The Contractor shall adhere to the requirements of NAVSEA Technical Specification 9090-310 (series) (Modernization work only).

0. The Contractor shall adhere to the requirements of the latest NAVSEA Standard Items relevant to the requirements of the SOW.

0. The Contractor shall maintain a Quality Management System (QMS) in accordance with ASQ/ANSI/ISO 9001:2015 standards. QMS packages are required to adhere to the requirements of:

· NAVSEA Standard Item 009-04 (series) (Modernization & Non-Modernization work)

· NAVSEA Technical Specification 9090-310 (series) (Modernization work only)

0. The Contractor shall maintain Quality Management System (QMS) acceptance from NAVSEA 09MP in accordance with NAVSEA Technical Specification 9090-310 (series) (Modernization work only).

0. The Contractor shall notify in writing the following when any changes are made to the Quality Management System (QMS) that may affect work:

· NSWCPD’s Quality Department (Modernization & Non-Modernization work)

· NAVSEA 09MP (Modernization work only)

0. Risk Management

14.2.1 The contractor shall develop an internal risk management program and work jointly with the (Code 412) to develop an overall risk management program.

14.2.2 Assign responsibility for risk mitigation activities, and monitor progress through a formal tracking system.

14.2.3 Conduct risk identification and analysis during all phases of the program, including proposal development. Develop appropriate risk mitigation strategies and plans.

14.2.4 Use projected consequences of high probability risks to help establish the level of management reserve and schedule reserve.

14.2.5 Assess impact of identified performance, schedule and costs risks to estimate at completion, and include in the estimate as appropriate. Develop a range of estimates (best case, most likely, worst case).

14.2.6 The Contractor shall capture risks and associated mitigation plans in a risk database and provide status updates to the Government for all documented risks upon request.

SOW-PWS Template 17 March 2023 version Page 13