SOW - MPD B334 Data Center UPS Procurment and Installation.docx
DOCX document 14 KB Posted
- Attached to
- 6140--Data Center UPS replacement Installation 640-25-1-5503-0001 | 36C261-24-AP-5705 | MPD B334
- Solicitation number
- 36C26125R0011
About this file
This document is a Statement of Work (SOW) for a federal contract opportunity to procure and install data center UPS systems at the Department of Veterans Affairs (VA) Menlo Park Division.
The SOW details the requirements for the contractor to provide all necessary personnel, equipment, and services to replace twelve (12) four-post rack-mountable VRLA UPS systems, including power distribution, wiring, rack PDUs, and monitoring software. The contractor will also remove and dispose of the old UPS and batteries, install new circuit breakers, and perform migration and load balancing services for the data center network devices. The contractor must procure and install a standalone server-based monitoring system to monitor all power distribution devices. This is a pre-solicitation notice, and the VA is conducting market research to identify vendors capable of performing this work. Interested vendors should provide their company information, socio-economic status, and capability statements by the October 21, 2024 deadline. No solicitation document is available at this time, and the Government reserves the right to cancel the requirement.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C26125R0011.docx | DOCX document | |
| Sources Sought Response Form.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C26125R0011 Data Center UPS replacement Installation MPD Building 334 Data Center Emergency Backup Power Equipment Procurement and Installation
SCOPE
The contractor shall provide all personnel, equipment, tools, materials, supervision, and services necessary to procure and install a quantity of twelve (12), four-post rack-mountable, VRLA, UPS systems, like or equal to APC Smart-UPS model SRT3000XLW-IEC. Replacement shall include power distribution center, wired inputs/outputs, 4kVA power modules (5), (13) hot-swap battery modules, management software, power distribution cables & cords.
The contractor shall procure and install a replacement 16kVA frame, power & battery modules, configuration software, distribution cables, L6-30R/P outlets, two (2) new AP6020A rack PDU’s in each rack, remove and dispose of old/failed UPS and batteries and cables. Provide and install replacement C13 to C14 power cords and start up system. Install a new 100A 2 pole breakers in the existing 3phase breaker panel, install all required conduit and wire to feed UPS distribution panel.
The contractor shall install and energize all UPS units and provide migration and load balancing services for all existing dual-powered data center network devices. Device power cables shall be migrated from existing in-cabinet PDU “A” unprotected C-13 and C-19 outlets over to UPS C-13 and C-19 outlets. The contractor shall identify and red-tag single power-supplied devices and provide advice to IT stakeholders as to how to safely migrate these devices over to the UPS systems’ outlets.
The contractor shall procure and install C-13 and C-19 caps to un-protected in-cabinet PDU “A” C-13 and C-19 outlets for the purpose of discouraging intentional or unintentional use of unprotected A-side outlets.
The contractor shall procure and install a discreet, stand-alone server-based equipment monitoring system consisting of a server, laptop computer and corresponding software and licenses necessary to monitor all data center power distribution devices (UPSs and PDUs) by an on-site technician in real time. All power distribution devices to be monitored shall be connected to the monitoring server via Category 6 Ethernet cable. Wireless connections are not authorized. Connection to the VA Internal Network is not permitted.
The contractor shall not engage in any activity not explicitly outlined in this memorandum without obtaining prior written approval from the Contracting Officer as outlined in an official Contract Modification action.