Oklahoma City Veterans Affairs Health Care System
(OKC VA HCS)
Statement of Work (SOW) Install Stainless Steel Wall Covering for VA Medical Basement
I. GENERAL:
A. This project is to install stainless steel wall covering in the basement level at the OKC VA HCS at Oklahoma City, Oklahoma.
B. The contractor is fully responsible for verifying and validating all information contained within this statement of work. Contractor must fully evaluate the condition of the existing structures and verify the current condition of the project site.
C. All measurements/quantities provided in this document are approximate and are to be used for reference only. The contractor will be responsible for taking on-site measurements and verifying all quantities and distances.
D. All materials/fasteners/etc. must be new and provided by the contractor unless otherwise specified.
E. The contractor shall abide by all Safety, Security and Infection Control Policies and Procedures of the Oklahoma City VA HCS.
F. VA facilities are tobacco free. No smoking is permitted on VA property. The contractor is responsible for their subcontractor’s compliance with this policy.
G. All work must conform to, and comply with, the latest edition/version of ALL applicable VA, federal, state, and local laws, rules, regulations, codes, and standards.
II. JUSTIFICATION:
The basement level hallways and walls of the medical center are susceptible to constant damage from logistical transport equipment and materials due narrow pathways. To help minimize damage and repeated repairs of walls and the hallways, installation of metal wall coverings will prevent damage. Therefore, reducing labor hours and repair costs.
III. STATEMENT OF WORK:
The contractor shall provide supervision, manpower, and materials to install metal wall coverings. Contractor shall provide the included but not limited to the following:
A. Prepare wall surfaces to maximize adhesion where the metal paneling will be installed B. Where installed, remove and dispose cove base
C. Install 16-gauge, B2 finish smooth stainless metal sheets on drywall portion only of the hallways as annotated on attached floor plan D. Wall covering shall be 48 inches high from the floor with rounded edges E. Attach metal sheets with stainless steel screws and a heavy-duty adhesive to provide maximize adhesion to wall surface F. Screws shall be installed and be flush with the metal panel and will be left uncovered G. Ensure currently installed devices such as bumper guards which protect keypads and card reader machines, light switches, entry control keypads, fire alarm pull stations, utility outlets, and cover plates will remain in place. Metals panels will be installed around these devices H. VA Engineering staff will remove existing hand/foot rails and corner guards.
I. Clean-up and dispose trash and material generated by contractor and check out with COR for final inspection
IV. PHOTO REFERENCES:
Drywall with outlets
Card reader
Outlets
Hand/Foot rails to be removed by VA
Hand rails to be removed by VA
Elevator panels Corner guards to be removed by VA
V. FLOOR PLAN REFERENCES:
Area 1
Area 2
Area 3
Total Estimated Linear Feet: 410 feet Last Updated: 2/2/2023