SOW Metal Building.docx

DOCX document 251 KB Posted

Attached to
USCG Sector Mobile Metal Building Construction
Solicitation number
70Z02925QNEWO00021
Issued by

About this file

This document is a Statement of Work (SOW) for a commercial metal building construction project for the United States Coast Guard at Sector Mobile. The project involves constructing a pre-engineered metal building with specific dimensions of 40 feet wide by 50 feet long, 16-foot leg height, featuring 26-gauge steel roofing and wall panels in colors including Clay, Bright Red, and Pewter Gray. The building will include one walk-in door (36" x 80") and three rollup doors (12' x 14"), with vertical roof style and a 3/12 pitch.

The contract requires a total performance period of 30 calendar days, with work performed Monday through Friday from 7:00am to 4:00pm. The project is a small business set-aside under NAICS code 236220, with a firm-fixed price award to the lowest-price quoter. The contractor is responsible for supplying all materials, performing complete installation, ensuring compliance with manufacturer specifications and local building codes, and maintaining safety and environmental regulations. The project will be executed on a Coast Guard operational military installation, with specific requirements for personnel security, utility management, and site cleanup.

View the file

Other files

File Type Posted
Screenshot 2025-09-11 113832.png PNG image
Screenshot 2025-09-11 113702.png PNG image
SF1442.pdf PDF
Screenshot 2025-09-11 113808.png PNG image
Specification Document Commercial Building.docx DOCX document
AL20250092 Wage Rates.txt TXT text file
Screenshot 2025-09-11 113738.png PNG image
Construction Clauses.pdf PDF
Screenshot 2025-09-11 113000.png PNG image

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT SPECIFICATIONS

Commercial Metal Building Construction

UNITED STATES COAST GUARD

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

Scope of Work: Commercial Metal Building Construction

General Information:

1.1. Building Type: Pre-engineered commercial metal building.

1.2. Building Dimensions: Width: 40 feet Frame Length: 50 feet

1.3. Leg Height: 16 feet

1.4. Materials and Finishes:

1.5. Roof Material: 26-gauge (or equivalent) steel roofing panels.

1.6. Color: Clay

1.7. Wall Exterior Material: 26-gauge (or equivalent) steel wall panels.

1.8. Color: Bright Red

1.9. Orientation: Vertical

1.10. Wainscot: Material: 26-gauge (or equivalent) steel wall panels.

1.11. Color: Pewter Gray

1.12. Trim Material: Formed steel trim. Color: Slate Blue

1.13. Door Frames and Trim Material: Steel Color: White

1.14. Fasteners: All necessary fasteners, including bolts, screws, and sealants, will be provided. Fasteners will be compatible with metal materials and suitable for exterior use.

1.15. Structural Specifications:

1.16. Frame Spacing: 5 feet on center.

1.17. Roof Style: Vertical

1.18. Roof Pitch: 3/12

1.19. Roof Overhang: 6 inches

1.20. Trusses: High Clearance

1.21. Leg Style: Ladder Legs

1.22. Brace: 2' Brace

1.23. Installation Surface: Cement (assumed to be properly prepared and level)

1.24. Enclosure Details:

1.25. Left Side: Fully Enclosed - Vertical Siding (Bright Red with Pewter Gray Wainscot)

1.26. Right Side: Fully Enclosed - Vertical Siding (Bright Red with Pewter Gray Wainscot)

1.27. Front End: Fully Enclosed - Vertical Siding (Bright Red with Pewter Gray Wainscot)

1.28. Back End: Fully Enclosed - Vertical Siding (Bright Red with Pewter Gray Wainscot)

1.29. End Walls Deluxe (Wainscot): Pewter Gray

1.30. Side Walls Deluxe (Wainscot): Pewter Gray

1.31.

1.32. Door Specifications Walk-In Door: Quantity: 1 Dimensions: 36" x 80"

1.33. Type: 6-Panel, Pre-hung Steel Door

1.34. Location: Sidewall Features: Header Bar Color: White

1.35. Rollup Door: Quantity: 3 Dimensions: 12' x 14'

1.36. Type: Chain Hoist Included

1.37. Location: Sidewall Features: Header Bar Color: White

1.38. Scope of Work Details Material Supply:

1.39. The contractor is responsible for supplying all materials necessary for the construction of the metal building, including, but not limited to: Steel framing components, Roofing panels, Wall panels, Wainscot panels, Trim, Doors, Fasteners, and Sealants.

1.40. All other necessary hardware and accessories.

1.41. All materials shall be new and of good quality, meeting industry standards and manufacturer specifications.

1.42.

Delivery:

1.43. The contractor is responsible for delivering all materials to the project site.

1.44. Delivery shall be coordinated with the client to minimize disruption.

1.45. The contractor is responsible for offloading and storing materials securely on site.

Installation:

1.46. The contractor is responsible for the complete installation of the metal building, including Erection of steel framing. Installation of roofing panels. Installation of wall panels and wainscot.

Installation of trim. Installation of doors (walk-in and rollup).

1.47. Proper sealing and weatherproofing of all joints and seams.

1.48. Ensuring all work is performed in accordance with manufacturer specifications and local building codes.

1.49. Site cleanup and removal of construction debris

1.50. TEMPORARY FACILITIES OR UTILITIES

None required.

1.51. PROJECT PERFORMANCE PERIOD

A. The total contract performance period shall include not only the time needed to complete the base bid and approved option items, but it also includes the time needed to submit, review, and approve all material submittals, and complete all project record (closeout) documents. After work begins at the site, perform the work continuously during normal working hours and show daily progress until all work is complete.

B. The total contract performance period is 30 calendar days.

Arrangements for visiting the site may be made by contacting:

Mr. James Petrik Email: james.m.petrik2@uscg.mil Telephone: (240)210-5515

1.52. DRAWINGS ACCOMPANYING SPECIFICATION

There are no drawings accompanying this specification.

1.53. WORK HOURS

1.53.1. Normal Working Hours

A. Perform all work at the site from Monday through Friday from 7:00am to 4:00 pm, unless otherwise approved. This project requires a special schedule to prevent operational interruptions during the installation process. Please refer to the scope section for detailed coordination of working hours. The contractor shall plan a schedule to minimize disruptions to building operations.

B. Performing the work beyond the listed working hours is at the discretion of the Coast Guard unit and the contractor must gain prior approval.

1.54. SPECIFIC ENVIRONMENTAL REQUIREMENTS

There are no specific environmental requirements. Refer to section titled Environmental for general environmental requirements.

1.55. SAFETY PROGRAM

1.55.1. General

The Contractor is wholly responsible for work site safety. Implement a safety program that protects the lives and health of personnel in the construction area, prevents damage to property and avoids work interruptions. Provide appropriate safety measures including but not limited to barricades, signs and signal lights as well as complying with the requirements of all applicable federal, State and local safety laws, rules and regulations.

1.56. AVAILABILITY OF UTILITY SERVICES

A. Reasonable amounts of the following utilities will be made available to the Contractor without charge.

(1) Electricity, and

(2) Potable Water.

B. The Contractor shall pay all costs incurred in connecting, converting, and transferring the utilities to the work. The contractor shall be responsible for making connections including providing back flow preventers, transformers and for disconnection. The contractor shall provide temporary toilet facilities for their personnel.

1.57. UNDERGROUND AND CONCEALED UTILITIES

A. Any utility locations provided are diagrammatic, not exact.

B. Physically verify the location and elevation of the existing underground and concealed utilities local to the work area. Employ techniques to scan the construction site including electromagnetic and sonic equipment prior to commencing the work. Mark the surface of the ground where existing underground utilities are discovered.

1.58. UTILITY OUTAGES

Identify the utility, reason for interruption, proposed time of interruption, and duration of interruption. Do not interrupt utilities until authorized by the Contracting Officer’s Representative (COR).

1.59. CONTRACTOR USE OF PREMISES

The work shall be performed on a Coast Guard operational military installation. Become familiar with and obey station fire, traffic, and security regulations. Personnel shall not stray from the immediate area of work or direct avenues of ingress and egress unless authorized in advance by the COR. Isolate each construction area with temporary partitions and dust controls. Provide movable high-visibility safety fencing about all work areas and equipment laydown areas located outdoors. Provide temporary covers on excavations that remain open overnight.

1.60. CLEANUP

The Contractor shall keep the work area, including the laydown and storage area, free from accumulations of waste materials on a daily basis and comply with all federal, state, and local regulations pertaining to the storage, transport, and disposal of wastes. The Contractor shall not use Coast Guard waste disposal facilities including garbage cans, trash piles, or dumpsters.

1.61. ENVIRONMENTAL

1.61.1. Protection of the Environment

The Contractor shall comply with all applicable federal, state, and local laws and regulations for the protection of the environment, including but not limited to the Endangered Species Act (ESA), Bald and Golden Eagle Protection Act (BGEPA), the Migratory Bird Treaty Act (MBTA), National Historic Preservation Act (NHPA), the Resource Conservation and Recovery Act (RCRA), and Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA).

1.61.2. Generated Waste

A. Any waste generated because of the project shall either be recycled or be disposed of in accordance with RCRA requirements.

B. Any hazardous waste shall be manifested off site with the Coast Guard unit listed as the Generator and signatory. Any hazardous waste shall be analyzed, characterized, stored, and disposed of in accordance with RCRA and all applicable federal, state, and local laws and ordinances.

C. Hazardous waste shall be properly transported and delivered to an appropriate facility. The Contractor shall submit for COR approval the proposed disposal facility, qualifications of the transporters, and the draft hazardous waste manifest.

1.62. DISPOSITION OF MATERIALS

A. All materials including construction debris and equipment shall be removed from Government property. The Government will not be responsible for the condition or loss of, or damage to, such property after notice to proceed. Materials and equipment shall not be viewed by prospective purchasers or sold on the site.

B. The Contractor shall submit the disposal receipt from the landfill within 10 working days of disposal.

1.63. STORM PROTECTION

The Contractor shall take every practicable precaution to minimize danger from storms to personnel, the work, and to adjacent property. Precautions shall include, but not be limited to, closing all opening, removing all loose materials, tools, and equipment from exposed locations, and removing or securing scaffolding and other temporary work.

1.64. RECEIPT OF MATERIALS

The Contractor is responsible to receive all equipment, materials, and supplies.

1.65. DELIVERY AND STORAGE

The Contractor is responsible for the proper transport and storage of all equipment and materials.

1.66. SECURITY

A. Submit a list of the names of all personnel working on the project site prior to the preconstruction conference for approval. The roster shall be submitted via email, and at a minimum, include the first name, last name, job description, and company of employment.

B. Immediately submit a new list upon a change in on-site project personnel. Refer to the paragraph titled, Special Notice Prior Notification, for notification requirements. Only personnel on the approved list are allowed onto the project site.

C. All approved personnel shall carry a valid, Government-issued identification while on Government property in conformance with the Real ID Act of 2005. Non-compliant personnel shall be escorted off Government property.

1.67. FINAL INSPECTION AND ACCEPTANCE

A. Electronically submit a written request for final acceptance to the Coast Guard.

1.68. WARRANTIES

A. Endorse all warranties or guarantees to the Government.

1.69. TRAINING

A. The Contractor shall provide training to unit personnel in the operation of the equipment. The Operation and Maintenance Manuals shall be approved and provided to the unit prior to the training.

1.70. SUBMITTALS

A. Submittals will be reviewed by the Coast Guard and returned within 10 working days after receipt, unless otherwise stated.

1.71. SUBMITTAL LIST

A. ROSTER OF PERSONNEL

(1) As required by the paragraph titled Security.

B. PROJECT SCHEDULE

(1) Prepare a Construction Progress Schedule. It shall include all major milestones and events for the entire duration of the construction contract.

C. SAFETY PLAN

(1) At a minimum, describe the general safety program and identify specific safety provisions for hazards incidental to the contract work such as elevated working surfaces, or similar conditions of the work. Comply with the paragraph titled Safety Program.

D. PRODUCT DATA

(1) Submit the product data sheet for each manufactured item. It shall include the manufacturer's descriptive literature of cataloged products, equipment drawings, diagrams, performance and characteristic curves and catalog cuts. Submit complete descriptive data for each type of material. Clearly mark data to indicate the type of material to be provided.

1.71.2. OPERATION AND MAINTENANCE MANUALS

A. Submit electronically and provide the following:

(1) Contact information for the prime contractor, sub-contractor, and major equipment vendor/supplier;

(2) Warranty information;

(3) Installation instructions;

(4) Maintenance instructions;

(5) Parts list.

-- End of Section --