This document is a Statement of Work (SOW) for the purchase of one (1) Composite Lab Paint Booth to be delivered, installed, and performance-verified at Tinker Air Force Base, OK.
The SOW outlines the technical specifications for the paint booth, including size requirements, air flow, filtration, lighting, and electrical controls. It also details the installation and performance verification responsibilities of the contractor. The contractor must provide a proposal that verifies compliance with all SOW requirements and includes booth construction drawings. The government will provide power within 25 feet of the booth's installation location. After installation, the contractor must demonstrate that the booth meets or exceeds all OEM specifications and SOW requirements.
The related federal contract opportunity is Solicitation FA812624Q0035 for the purchase of one Composite Lab Paint Booth in accordance with the SOW requirements. The solicitation is being issued by the Department of the Air Force Materiel Command Air Force Sustainment Center.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CSS - FA812624Q0035.pdf | ||
| Item Description M24-013 Composite Lab Paint Booth.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PREAMBLE
Commander’s Safety Intent
The safety of everyone on Tinker AFB is our top priority. All Individuals must accept personal responsibility for safety and seek opportunities for improving the safety of our work environment. Everyone working on Tinker AFB is challenged to find, fix (if able) and report all hazards and near-misses. It is our shared duty to take every reasonable step and precaution to prevent accidents and preserve the health/safety of each Contractor and Government employee.
1 SCOPE. This Statement of Work (SOW) defines the effort required for the purchase of one
(1) each Composite Lab Paint Booth to include Delivery, Installation, and Performance Verification in Building at Tinker Air Force Base, OK.
2 REQUIREMENTS
2.1 General. The Contractor shall provide to the Government Point of Contact (GPOC) the date that the Delivery, Installation, and Performance Verification will begin ten (10) business days after Contract Award and verify date of installation within five (5) days prior to installation beginning. The Contractor shall be responsible for ensuring all services, parts and components provided under this contract are in accordance with (IAW) the terms and conditions outlined in this SOW.
2.2 Item Description. M24-013 Composite Lab Paint Booth shall meet the specifications as defined below:
• Contractor shall provide Installation.
• Contractor shall provide Performance Verification.
• Contractor must meet all requirements outlined in accordance with (IAW) this SOW.
2.3 Contractor Requirements
a. Item one – One (1) M24-013 Composite Lab Paint Booth
(1) Booth foot print shall be no more than 70 square feet due to our lab's space limitations but shall be greater than 50 square feet so there is enough space to maneuver in the enclosed booth.
• The internal working volume shall be greater than 225 cubic feet
(2) Booth shall have a height of the ceiling shall not be higher than 10 feet due to the lab ceiling height.
(3) Booth shall come with appropriate lighting to visualize the spraying of panels.
• Fluorescent or LED non colored light only
(4) Booth shall have a cross draft air design with filtered doors (industry standard) to ensure debris free incoming air.
(5) Booth shall have a 3 stage chromate filter approved by Tinker Air Force Base Civil Engineering air quality is required along with a manometer for filter monitoring
(6) Booth shall have at least one entry way into the booth.
(7) Booth exhaust and air intake shall provide a minimum air velocity of 70 feet per minute.
• Booth shall have a continuously variable exhaust fan or an alarm that audibly sounds when the air flow is reduced by 20% to indicate a filter change is required.
• Booth shall not have any pass through flow except through the exhaust.
(8) Booth electrical controls shall be on the exterior of the booth on a non-moving panel.
(9) Booth panels shall be metal for grounding purposes and of a thickness such that a compressed air line can be secured to the interior along with a sprinkler head for fire suppression.
b. Contractor shall submit a proposal at time of solicitation that includes verification that all items in this SOW have been complied with as well as drawings showing overall booth construction.
2.4 Installation
2.4.1 The Contractor shall be responsible for equipment delivery to Tinker AFB, OK 73145. The Contractor shall be responsible for offloading equipment and moving equipment to installation area ( ) where a standard loading dock is available at the southeast corner of the building at door EB-1. The Government shall provide power to the area that the Composite Paint Booth is to be installed. The Contractor shall provide the incidentals services that is IAW the OEM’s specifications.
2.4.2 The Government will provide power within 25 feet of the Composite Paint Booth.
2.6 Composite Paint Booth Performance Verification
After installation, the Contractor shall demonstrate that the Paint Booth meets or exceeds all OEM specifications and the requirements listed in section 2.2 of this SOW. The contractor shall demonstrate that the booth exhaust and air intake shall provide a minimum air velocity of 70 feet per minute when the filter door(s) are closed and the 3-stage filter is installed. Contractor shall be present for entirety of acceptance testing. Tinker AFB personnel, to include Base Civil Engineering will attend this demonstration and provide final approval of completion.
2.7 Hours of Operation: The Contractor shall perform the work required under this contract during the following days and hours: Monday through Friday, 0630 - 1600. If work hours are required outside the hours stated, the Contractor shall contact the Government POC for approval from the CO. Upon approval from the CO, the SME or GPOC escort Contractor personnel at all times.
2.7.1 These dates and hours exclude Federal Holidays, base closures due to inclement weather, and furlough days, as applicable.
3.0 On-Base Requirements
3.1 Environmental Protection & Safety: The Contractor shall be knowledgeable of and comply with all applicable federal, state, and local laws, regulations, instructions and requirements regarding environmental protection and occupational safety and health. The Contractor shall comply with any laws, instructions, or regulation changes during the term of this contract.
Contractors shall be compliant Tinker Air Force Base (TAFB) Supplement to Air Force Instruction (AFI) 32-7086, “Hazardous Materials Management”, Tinker AFB procedures per Tinker Air Force Base Hazardous Waste Management Plan (TAFB HWMP), and Complex procedures per Oklahoma City Air Logistics Complex (OC-ALC) Sup to AFI 32-7086, “Hazardous Material Management” and OC-ALCI 32-101 “Air Quality Record Keeping Procedure”. Publications are available digitally on e- Publishing website at www.e-publishing.af.mil for downloading or ordering.
3.1.2 Hazardous Material (HAZMAT): If no HAZMAT will be brought on base or used in performance on this contract, the Contractor shall certify “No HAZMAT will be brought on base” or “No HAZMAT Usage” by official correspondence. This certification shall be provided to the COR within ten (10) days after award. Upon COR receipt of the certification, the requirements of this section no longer apply. Appropriate penalties for the Contractor, or administrative and disciplinary action for the later shall be assessed if found in violation of above certification.
The Contractor shall not store chemicals or hazardous material (HAZMAT) on Tinker AFB. Contractors shall be compliant with HAZMAT management procedures per Oklahoma City Air Logistics Complex (OC-ALC) Supplement to AFI 32-7086, “Hazardous Materials Management”. The Contractor shall maintain a log of all HAZMAT that is used on base. This usage log shall be provided to the COR monthly, the last business day of each month, or when the required work is completed. The COR will forward the records to the Unit Environmental Coordinator (UEC) no later than the fourth (4th) day of the following month or the first (1st) subsequent business day.
3.1.3 Safety Data Sheet (SDS) and Labeling: Upon COR receipt of the “No HAZMAT Usage” certification, the requirements of this section no longer apply.
The Contractor shall not transport, ship, or use any chemical, material or substance used in the performance of this PWS on Tinker AFB before written approval is provided by 72 ABW/CEIE, Natural Infrastructure Management (Environmental Compliance). The Contractor shall submit to the COR, ten (10) calendar days after contract award date all Safety Data Sheets (SDSs) and a completed OC-ALC Form 152, SDS Information Sheet. The Contractor shall receive approval from the COR prior to shipping any chemical, material, or substance to Tinker AFB. A copy of the manufacturer SDS shall accompany the shipment. Contractor shall comply with the effective dates for SDS requirements IAW the Occupational Safety and Health Administrations (OSHA) Hazardous Communication Standard, Title 29, Code of Federal Regulation (CFR) Part 1910.1200. The Contractor shall ensure containers of hazardous chemicals are labeled with the following information, prior to shipping to Tinker AFB IAW OSHA Hazardous Communication Standard, Title 29, CFR Part
1910.1200 (2012): product identifier; signal word; hazard statement(s); precautionary statement(s);
pictogram(s); and name, address and telephone number of the chemical manufacturer, importer, or other responsible party. The COR will forward all SDS submittals to 72 ABW/CEIE for approval. A current manufacturer SDS shall be submitted to the COR if the Contractor changes manufacturer or vendor for any chemicals that were prior approved. The Contractor shall maintain copies of manufacturer SDSs for all chemicals and SDSs shall be readily accessible at all times by Contractor personnel as well as government employees.
3.1.4 Hazardous Waste: If no HAZWASTE will be generated during performance of this contract, the Contractor shall certify “NO Hazardous Waste Generation” by official correspondence. This certification shall be provided to the COR within ten (10) days after award. Upon COR receipt of the “No Hazardous Waste Generation” certification, the requirements of this section no longer apply.
Appropriate penalties for the Contractor, or administrative and disciplinary action for the later shall be assessed if found in violation of above certification.
The Contractor shall dispose of contaminated solid waste, spent or processed chemical solutions, used rags and hazardous waste in government furnished waste containers located in the shop or area the work is being performed. The Contractor shall notify the COR if the required waste containers are not available on site.
3.1.5 Discharges: Any discharges into Tinker’s industrial waste treatment plant (IWTP) or sanitary sewer shall be approved and done IAW Tinker Industrial Wastewater Discharge Permit as instructed by 72 ABW/CEIE, Natural Infrastructure Management (Environmental Compliance). Notice of intent documentation shall be provided to the COR within ten (10) days after award. The COR will submit the required notice of intent documentation to the UEC for 72 ABW/CEIE approval. The Contractor shall not discharge into IWTP and sanitary sewer prior to approval issued by 72 ABW/CEIE. The Contractor shall maintain records of written approval issued by 72 ABW/CEIE for discharges into IWTP and sanitary sewer.
3.1.6 Off-Site Discharges: For discharges outside of Tinker AFB, the Contractor shall ensure wastewater discharges, that may contain pollutants resulting from any contracted service, go to a state or federal permitted treatment facility such as a municipal Publicly Owned Treatment Works (POTW). The Contractor shall provide official correspondence ten (10) calendar days after contract award date to the COR from the POTW that states the POTW is permitted for all pollutants that the Contractor may discharge during the contracted service.
3.1.7 Spills: Upon occurrence of any spill that could enter the storm system or cause any harmful environment effects, the Contractor shall immediately call 911 to report the incident. When possible, the Contractor shall use a base telephone to receive help from Tinker AFB 911. If using a cell phone, the Contractor shall request Tinker AFB 911. The Contractor shall immediately report all environmental violations to the COR and UEC. The Contractor shall provide five (5) copies of a typed or written report about the incident within four (4) clock hours as follows:
One (1) copy to CO, two (2) copies to the COR, a copy for UEC and one (1) copy for record. The format of the report shall be left up to the Contractor, but the report shall contain the following information:
1.) Name and contact number of person reporting the spill 2.) Date and time of incident 3.) Location and source of spill 4.) Substance or pollutant spilled 5.) Amount spilled and rate of discharge 6.) Any damages or injuries involved 7.) Extent of area impacted 8.) Potential hazards 9.) Actions taken 10.) Organizations contacted 11.) Remarks Section - that addresses the cause of the spill (e.g. human error, equipment, etc.)
and whether 911 was called and which agencies responded.
3.1.8 Environmental Training: Upon COR receipt of the “No Hazardous Waste Generation” certification, the requirements of this section no longer apply.
b. When appropriate, encourage Contractor to complete Human Trafficking Awareness Training.
c. Encourage the Contractor to take steps to investigate and eliminate slavery and human trafficking in their supply chains and to publish information for consumer awareness.
d. Periodically access the Department of State’s Trafficking in Person (TIP) website for updates and to view the latest reports. http://www.state.gov/g/tip
3.7 Commanders Safety Intent: The safety of everyone on Tinker AFB is our top priority. All Individuals must accept personal responsibility for safety and seek opportunities for improving the safety of our work environment. Everyone working on Tinker AFB is challenged to find, fix (if able) and report all hazards and near-misses. It is our shared duty to take every reasonable step and precaution to prevent accidents and preserve the health/safety of each Contractor and government employee.
3.8 Speak up for safety: Safety surety is an integral part of our overall goal of establishing a world class safety and health program. Our “Speak Out for Safety” initiative ensures a partnership with Contractors and government employees to further enhance safety to ensure we are looking out for all our partners and empowers all employees to actively participate in each other’s safety.
A safe workplace is everyone's business. As part of the contract team, military, civilian and Contractor personnel are empowered to Speak Out for Safety (S.O.S.) when they observe an unsafe act. Events that present imminent danger to personnel or catastrophic damage to property we empower our employees to intercede to ensure continued safe operations.
3.9 Communicating Hazards Of Workplace (CHOW): Contractor’s onsite representative communicates all hazards being introduced to the worksite by the Contractor. This is accomplished prior to commencement of work and refreshed daily during performance, IAW Contractor’s Site Safety Plan.
3.10 Emergency Procedures: The Contractor personnel shall follow the direction of the Government personnel with regard to emergency procedures, such as fire, tornado, active shooter, bomb threats, or other emergency. It is the responsibility of the Contractor to provide guidance and to establish procedures for its employees to respond to an emergency. It is the Contractor’s responsibility to account for their employees following an emergency evacuation. The Contractor personnel shall participate with the Government personnel in all fire and tornado drills at no additional cost to the Government.