SOW - Locker Room Renovation.pdf

PDF 165 KB Posted

Attached to
Fitness Center Lockers Requirement
Solicitation number
F1S3AU6111A001
Issued by

About this file

This Statement of Work (SOW) outlines requirements for procuring and installing new lockers and benches at the Rosburg Fitness Center located at 210 W. Popson Ave., Building 2200, Edwards Air Force Base, California 93522. The project is funded by Rosburg Fitness Center Appropriated Funds and must be completed within 60 days from the contract award date, with work performed during normal business hours (Monday-Friday, 7:00 am-5:00 pm).

The contractor must provide all labor, materials, and equipment for procurement, delivery, installation, cleanup, and quality assurance. Locker specifications require 34 double-tiered, 3-wide units and 11 double-tiered, 1-wide units, each measuring 73 inches in height and 18 inches in depth, finished in deep blue/navy color with physical combination locks featuring master key override capability (battery-operated locks are not acceptable). Bench specifications include two 48-inch benches, two 60-inch benches, and seven 84-inch benches, all constructed of wood with light finish and bolt-mounted installation. All locker and bench specifications must receive Government point of contact approval prior to purchase. The contractor must professionally install all items, securely anchor them to walls and/or floors, install associated components including locking mechanisms and number plates, remove all debris and packaging materials, and conduct a final joint walk-through inspection with the Government. The contractor must maintain open communication with Mr. Garrett Holloway, Fitness and Sports Director (661-277-2784), and Mr. Ron Jackson, Fitness Operations Manager (661-277-8392), and comply with all applicable federal, state, and local safety regulations while providing appropriate safety barricades or signs.

View the file

Other files

File Type Posted
Locker RoomOverview.jpg JPG image
Q and A (2).pdf PDF
Q and A (1).pdf PDF
Combined Synopsis Solicitation- UPS and keypad v1.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK (SOW)

Rosburg Fitness Center

210 W POPSON AVE

BLDG 2200

EDWARDS AFB. CA 93522

DATE: 8 MAY 2026

INTRODUCTION/BACKGROUND

This Statement of Work outlines the requirements for a contractor to procure and install new lockers and benches for the Rosburg Fitness Center. The current lockers are outdated and require replacement to better serve the needs of facility patrons. The contractor shall be responsible for all phases of the project, from initial site assessment to final cleanup.

SCOPE OF WORK

The contractor shall provide all necessary labor, materials, and equipment to perform the following tasks:

A. Procurement and Delivery

a. Purchase new, commercial-grade lockers and benches that are appropriately sized to fit the measured spaces. Locker specifications (material, size, locking mechanism) must be approved by the Government point of contact prior to purchase.

i. Locker specifications

1. Dimensions

a. 73” in height, 18” in depth

i. Quantity

1. 34 double-tiered, 3-wide

2. 11 double-tiered, 1-wide

2. Other specifications

a. Color – deep blue/ navy

b. Locks – must feature physical combination with ability for master key override, battery-operated locks will not suffice

ii. Bench specifications

1. Dimensions

a. 48”

i. Quantity – 2

b. 60”

i. Quantity – 2

c. 84”

i. Quantity – 7

2. Other specifications

a. Wood, light finish

b. Bolt mounted

b. Arrange for the delivery of all new lockers, benches, and associated installation hardware to the worksite.

c. Unpack and inspect all delivered items for damage or defects upon arrival.

B. Installation

i. Professionally install the new lockers and benches in the designated areas as per the approved layout form point(s) of contact

ii. Securely anchor all lockers and benches to the walls and/or floor to ensure stability and safety.

iii. Install all associated components, including locking mechanisms, number plates, and benches (if applicable).

C. Cleanup and Restoration

i. Remove all debris, packaging materials, and other waste from the site.

ii. Properly dispose of all removed items and materials.

iii. Clean all work areas thoroughly, returning the locker room spaces to their original condition, ensuring they are clean and safe for use.

D. Quality Assurance

i. Perform a final inspection to ensure that all items are installed correctly, are level, and are free of defects.

ii. Verify that the installation meets all project specifications and safety standards.

iii. Conduct a joint final walk-through with the point(s) of contact listed below to confirm satisfactory completion of all work.

SAFETY – ACCIDENT PREVENTION

The contractor shall provide and maintain a work environment that safeguards the public and Government personnel, property, and materials. The contractor will comply with all applicable federal, state, and local safety regulations and provide appropriate safety barricades or signs as needed.

PERIOD OF PERFORMANCE

Work is to be performed during normal business hours (Monday - Friday, 7:00 am - 5:00 pm).

The entire project MUST BE COMPLETE within 60 days from the date of contract award.

FUNDING OF PROJECT

Funding will be provided by Rosburg Fitness Center Appropriated Funds.

PLACE OF PERFORMANCE

Work will take place at 210 W. Popson Ave., Bldg. 2200 in the male and female locker rooms.

ACCEPTANCE CRITERIA

The Government will inspect the finished work upon completion. The Government retains the right to refuse damaged or faulty equipment and materials or to require correction of any installation work that does not meet the standards set forth in this SOW.

OTHER REQUIREMENTS

The Contractor is to maintain open communication channels with the Fitness and Sports Director (FSD) and Fitness Operations Manager (FOM) before, during, and upon completion of this project.

• FSD: Mr. Garrett Holloway, (661) 277-2784, garrett.holloway.1@us.af.mil

• FOM: Mr. Ron Jackson, (661) 277-8392, ronald.jackson.35@us.af.mil https://www.google.com/url?q=mailto%3Agarrett.holloway.1%40us.af.mil https://www.google.com/url?q=mailto%3Aronald.jackson.35%40us.af.mil

Introduction/Background
Scope of Work
Period of Performance
Funding of Project
Place of Performance
Acceptance Criteria

File details come from the government source that posted it. Updated .