SOW LD8 Concrete - 09-22-2025.pdf
PDF 506 KB Posted
- Attached to
- Lock and Dam 8 Spillway Concrete Supply
- Solicitation number
- W912ES25QA084
About this file
This document is a Scope of Work for concrete delivery to the U.S. Army Corps of Engineers, St. Paul District for horizontal surface repairs at Lock and Dam 8 in Genoa, Wisconsin. The contract requires delivering 350-450 cubic yards of concrete in 30-yard batches during winter months (November 1 - March 1) over a two-year period, with a base year and one option year. The concrete must meet specific technical specifications, including a compressive strength of 4,500 psi after 28 days, a water-to-cement ratio of 0.45, polypropylene micro fiber, 4-7% air content, and a maximum 4-inch slump.
Delivery will be to the Minnesota-side spillway, accessed through a property gate in Reno, MN. The concrete must be placed when ambient temperatures are between 55-65°F, with special requirements for cold weather placement. The contractor must submit a Certificate of Conformance electronically before shipment and follow the U.S. Army Corps of Engineers Safety and Health Requirements Manual. The contract includes an economic price adjustment clause based on the Producer Price Index for cement manufacturing, allowing potential price modifications on November 1, 2026, during the first option period.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation - W912ES25QA084.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCOPE OF WORK
Concrete
For Spillway Cells LD8
U.S. Army Corps of Engineers, St. Paul District
1. General Description.
The Contractor shall deliver mixed concrete to the Minnesota-side of the spillway located at Lock and Dam 8 in Genoa, WI. The purpose is for horizontal surface repairs to the spillway cells. These deliveries will take place during the winter months (November 1 – March 1) over a two-year period (a base year and one (1) option year) and will require backing across the 20’ wide Reno spillway. Minimum quantity will be 350 cubic yards but could increase to up to 450 cubic yards. Deliveries will be in 30-yard batches (+/- 10%) delivered to the work site.
Potential vendors are encouraged to visit the work site in advance of submitting a quote.
2. Concrete Specifications.
A. Must be able to achieve compressive strengths greater than 4500 psi after 28 days.
B. Water to cement ratio not to exceed 45%.
C. Polypropylene “micro” fiber to be used that meets ASTM C-1116, Type III.
D. Air content of the mix to be 4% - 7% at time of placement.
E. Slump of concrete at the time of placement shall not exceed 4”.
F. If a superplastizer is used, the slump shall not exceed 4” before admixture is added and shall not exceed 8” at the point of delivery after the admixture is added.
G. The coarse aggregate shall conform to ASTM C 33, size No 57 or 67, Class 4S.
H. When the ambient temperature during placing is 40 °F or less, or is expected to be at any time within 6 hours after placing, the temperature of the concrete as delivered shall be between 55 and 75 °F.
I. See Appendix B for mix design specifications.
3. Delivery Location.
Road access to the placement sites is through the property gate located in Reno, MN.
4. Submittals The Contractor shall submit a signed Certificate of Conformance electronically in pdf format via email to the Government technical point of contact prior to shipment of the material.
The Government Technical point of contact(POC) is: Eric Lockington
5. Safety A. All work shall be in conformance with the latest version of the Corps of Engineers Safety and Health Requirements Manual https://www.usace.army.mil/Missions/Safety-and- Occupational-Health/Safety-and-Health-Requirements-Manual/
PLACEMENT SITE
LOCK & DAM 8
https://www.usace.army.mil/Missions/Safety-and-Occupational-Health/Safety-and-Health-Requirements-Manual/ https://www.usace.army.mil/Missions/Safety-and-Occupational-Health/Safety-and-Health-Requirements-Manual/
6. Ordering A. A Task Order will be issued via Standard Form 1449 and signed by the Contracting Officer for each ordering period. Ordering periods will be from November 1, 2025, to March 1, 2026, and November 1, 2026, to March 1, 2027.
B. The individual deliveries will be ordered and scheduled by the authorized Ordering Officer(s). Ordering Officers (who will be designated at contract award) are authorized to make individual delivery orders against the task order up to the NTE task order value. Time and date of delivery will be specified when order is placed. Notice of orders will normally be made via email. The backup ordering procedure will be via phone. In these cases, the Ordering Officer shall send confirmation of the order in writing at the first convenient opportunity. The vendor/contractor must provide a designated email address and backup phone number prior to contract award (alternative communication means may be considered if presented).
C. Cancellation or change for delivery may be up to 24 hours prior to originally scheduled delivery due to a sudden change in site conditions or other schedule uncertainties.
7. Delivery Schedule A. Government will provide 48 hours notice of material quantities along with dates/time that material is to be delivered.
B. Delivery dates will be issued and coordinated by the Government Technical POC.
C. Delivery will take place between November 1, 2025, to March 1, 2026 (base year), and
November 1, 2026, and March 1, 2027 (option year), between the hours of 08:00 – 16:00 Monday through Friday.
D. Government will be responsible for snow removal along USACE access road and spillway. DRIVERS ARE SOLEY RESPONSIBLE FOR SAFE PASSAGE ACROSS SPILLWAY.
GOVERNMENT ASSUMES NO LIABILITY OF ACCIDENTS, INCIDENTS, ETC.
E. Trucks will be unloaded immediately and will not wait more than 20 minutes before being unloaded.
F. Government responsible for flagging operations across CP Rail crossing.
8. Government Point-of-Contact (POC) US Army Corps of Engineers Lock and Dam 8 4405 Highway 35 Genoa, WI 54632 POC: Eric Lockington Eric.J.Lockington@usace.army.mil
(651) 290-5034
9. Invoices All invoices shall be sent to:
USACE Mississippi River Project Office mailto:Eric.J.Lockington@usace.army.mil
Attn: Mike Holzer PO Box 397 431 North Shore Drive Fountain City, WI. 54629-0397
10. Economic Price Adjustment of Cement Price(S) Based On A Price Index
(a) To the extent that contract cost increases are provided for by this economic price adjustment provision, the Contractor warrants that the prices as identified in FAR Provision 52.215-20 Alt IV “Requirements for Certified Costs or Pricing Data and Data other Than Certified Cost or Pricing Data” in this contract does not include any amount to protect against such contingent cost increases.
(b) The Base and Adjusting Indexes, for the purpose of price adjustment under this clause, shall be “PPI industry data for Cement manufacturing, not seasonally adjusted)” found at https://data.bls.gov/dataViewer/view/timeseries/PCU327310327310;jsessionid=F24EC129 31222CE6C377403C5C611426 . All adjustments authorized under this clause shall be made by using the Base Index and Adjusting Indexes, which are published monthly.
(1) The Base Index, for the purposes of price adjustment under this clause, shall be the most recent Index published prior to the date for receipt of offers. The Base Index shall remain constant for the entire term of the contract.
(2) The Adjusting Index shall be the most recent Index published prior to the date of contract adjustment, as specified in paragraph (d) of this clause.
(c) The percentage difference between the Base Index and the Adjusting Index, rounded to the nearest .0001 percent, will be used in calculating all adjustments. The percentage of production vs delivery of the Contract Line Item Number (CLIN) price, as identified in FAR Provision 52.215-20 Alt IV, will be multiplied by the percentage increase or decrease and the resulting amount will be added to or deducted from the original contract price for that contract period to arrive at the new contract price from the effective date of the adjustment to the beginning of the next contract adjustment period, rounded to the same number of decimal points as the prices originally awarded.
(d) The date of contract adjustment shall be November 1, 2026, the first day of option period one.
The Contracting Officer shall calculate the adjustment due and shall issue a contract modification (with supporting documentation) adjusting the contract price, as specified in paragraph (c).
(e) An example of an adjustment calculation is provided herein for informational purposes only.
(1) The original contract price for cement products as identified in FAR Provision 52.215-20 Alt IV prices for that contract term (e.g., option period one) shall be used for all calculations during that particular contract term and new calculations shall be made for each contract adjustment period specified in paragraph (d) during that contract term.
https://data.bls.gov/dataViewer/view/timeseries/PCU327310327310;jsessionid=F24EC12931222CE6C377403C5C611426 https://data.bls.gov/dataViewer/view/timeseries/PCU327310327310;jsessionid=F24EC12931222CE6C377403C5C611426
(2) For purposes of this example, the contract prices for the line items as specified in paragraph (c) will be adjusted by the percentage calculated as follows:
Increase in Price
CLIN Price per cubic yard $100.00 Index at Time of Calculation, November 1, 2026 390.789 Divided by the index at time base price was set, September 15, 2025
357.573
Equals the Index Point Change 1.0929 Percentage of Production per 52.215-20 Alt IV 55% CLIN Production Percentage Price $55.00 Multiplied by 1.0929 Increase $60.11 (increase of $5.11 per cubic yard rounded) Equals Adjusted CLIN Price $105.11
(3) For an item with an original quote price of $100.00 and a 1.0929 Index Point Change increase as of the contract adjustment period, as shown above, the calculations for a new contract price for the contract adjustment period would be as follows: $55.00 × 1.0929 = $60.11, $60.11 - $55.00 = $5.11, $100.00 + $5.11 = $105.11. The unit price adjustment shall be rounded up or down, to match the number of decimal places in the original quote.
Decrease
CLIN Price per cubic yard $100.00 Index at Time of Calculation, November 1, 2026 345.752 Divided by the index at time base price was set, September 15, 2025
357.573
Equals the Index Point Change .9669 Percentage of Production per 52.215-20 Alt IV 55% CLIN Production Percentage Price $55.00 Multiplied by .9669 Decrease $53.18 (decrease of $1.82 per cubic yard rounded) Equals Adjusted Price $98.18
(4) If the Adjusting Index went down for the adjustment period, reflecting a .9971 percent Index Point Change increase over the Base Index, the new contract price for the contract adjustment period would be as follows: $55.00 × 0.9669 = $53.18, $55.00 - $53.18 = $4.82, $100.00 - $1.82 = $98.18.
(g) In the event that the Bureau of Labor Statistics ceases publication of the monthly index, the Contracting Officer will, in his discretion, designate another price index to be used in making the adjustment.
(h) Any dispute arising under this clause shall be resolved subject to the “Disputes” clause of the contract.
(End of clause)
| 1. General Description. |
| 4. Submittals |
| 5. Safety |
| 6. Ordering |
| 7. Delivery Schedule |