SOW Lashing Straps Refurbishment.pdf
PDF 2 MB Posted
- Attached to
- Lashing Straps Refurbishment Federal contract opportunity
- Solicitation number
- N4215824RC40246
About this file
This statement of work outlines the refurbishment of 25 lashing straps for the Department of the Navy Naval Sea Systems Command. The selected contractor will pick up the straps from Shop 72 at Naval Station Norfolk and refurbish them by disassembling, zinc plating and bonding selected parts, reassembling with new rivets, installing rubber sleeves, and conducting static strength testing to 10,000 pounds for 10 minutes. The contractor must then deliver the refurbished lashing straps back to Shop 72 at Naval Station Norfolk and address any failures found during inspection at no additional cost. The related pre-solicitation lists the solicitation number, names the opportunity as lashing strap refurbishment, and identifies it as a pre-solicitation for the Department of the Navy Naval Sea Systems Command.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sources Sought.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ORDERING DATA
LASHING STRAP REFURBISHMENT
VENDOR SERVICES TO:
1. Contractor: Will pick up 25 lashing straps for refurbishment from Shop 72 at NOB.
a. Log IDs: 28, 30, 31, 32, 40, 46, 48, 50, 54, 55, 56, 60, 74, 80, 90, 100, 106, 107, 110, 113, 114, 117, 119, 120, and 123
2. Contractor: Using the attached drawings do a complete refurbishment of lashing straps.
Contractor: Use pages 3-9 to disassemble lashing straps. Items 1 LATCH, 15 SADDLE, 16 LINK and 20 ADAPTER (Detail list on page 4) are to be blasted and then zinc plated (note # 1 page 3). After completion of zinc plating item 5 PAD is to be bonded (PLASTISOLED) to items 1 LATCH, 15 SADDLE, 16 LINK and 20 ADAPTER. Upon completion of plastisol, reassemble lashing straps using new rivets item 13 RIVET and
14 RIVET.
3. Contractor: Using page 10 manufacture and install rubber sleeves to cover the metal straps.
4. Contractor: Once complete weight test lashing straps using pages 11-17. Conduct a Static test using 10,000 LBS and hold for 10 min. Once complete inspect Lashing Straps and document on weight test record cards. When all testing is complete Contractor will deliver the lashing straps to NNSY Shop-72 at NOB.
5. Contractor: Deliver QTY 25 Lashing Straps to NNSY Shop-72 at NOB.
6. Code 290: Perform visual inspections of equipment when received from contractor.
7. Contractor: Any failure of equipment during inspections will be required to be refurbished again at no further cost to NNSY.
***CHANGES TO SCOPE***
IMPORTANT NOTE: In the event that service(s) cannot be accomplished as currently described within this SOW, the contractor MUST immediately notify the Contracting Officer, in writing, of the circumstances preventing successful completion. Failure to do so may alleviate the Government for payment of charges deemed to be outside of the scope of contract.
File details come from the government source that posted it. Updated .