SOW_Kirwin_NWR_ERFOS_2021.docx

DOCX document 17 KB Posted

Attached to
MT-CRESTON NFH-GRND BASED GEO HEAT-PUMP
Solicitation number
140F0521Q0032
Issued by

View the file

Other files

File Type Posted
B01 Comb Syn-Sol 140F0521Q0032.doc DOC document
Sol_140F0521Q0032.pdf PDF
N. Shore Refuge Road Map_Route 010.jpg JPG image
B12 MISC Notice to Offerors.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

RT#10 North Shore Road (ERFO) Kirwin National Wildlife Refuge

I. GENERAL CONDITIONS

A. The Contractor shall provide all material, equipment, and labor required to deliver the requested material and stockpile the material at the identified location.

B. Access to site is difficult. It is recommended that the Contractor schedule a site visit to understand the conditions and limitations it may cause prior to submitting a quote.

D. The Contractor shall have all certificates and licenses required by law for the execution of the work, and shall comply with all Federal, State, or local laws, ordinances, rules, regulations, and codes relating to performance of the work.

F. Typical working hours are 7:30 am to 4:00 pm Monday through Friday. Any work that deviates from this schedule or during a holiday must be discussed with the refuge point of contact prior to conducting any work outside typical hours. These times can be negotiable.

II. SAFETY

A. Contractor assumes full responsibility and liability for compliance with all applicable Federal, State, and local regulations pertaining to the protection of workers, visitors to the site, and persons occupying areas adjacent to the site, including the provisions of 29CFR1910 and 29CFR1926 of the Code of Federal Regulations. The Contractor shall hold harmless the Government for failure to comply with any applicable safety or health regulations on the part of himself, his employees, or his subcontractors.

III. WORK SITE CONDITIONS

A. The work site is located at Kirwin National Wildlife Refuge on North Shore Road.

B. Delivery address: Kirwin NWR, 702 East Xavier Road, Kirwin, Kansas 67644

C. Period of Performance: 6/1/2021 - 9/1/2021

IV. MEANS AND METHODS

A. The contractor will provide material and delivery of an estimated 2,000 Tons of “sandstone riprap” constituting a nominal size of 24-inch diameter. Delivery will be coordinated with the on-site point of contact Stephen Knowles: (stephen_knowles@fws.gov) once award has been issued. The delivered material will be stockpiled in a specific location at the refuge near North Shore Road identified on the attached map.

In order for quotes to be considered, vendors must have an active registration in the System for Award management (www.SAM.gov). *Quotes must include material type, material size, and confirm available quantity of 2,000 Tons of sandstone riprap material****Quotes are to be directed to Lydia M Patrick: lydia_patrick@fws.gov. ***