SOW KABA Locks Final.pdf

PDF 151 KB Posted

Attached to
Cipher KABA Locks with Installation Federal contract opportunity
Solicitation number
W912CN-20-Q-EH01
Issued by
Department of the Army Materiel Command Army Contracting Command

View the file

Other files for this federal contract opportunity

Other files attached to Cipher KABA Locks with Installation, newest first.
File Type Posted
SOW Details Pin Type Revised 22June20.pdf PDF
SOW Details Final.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

413TH Contracting Support Brigade (CSB), RCO-HI

PHYSICAL SECURITY UPGRADES

1.0 General.

1.1 Background.

BLDG 500 physical security is not up to standard. Most of the outside doors have broken locks or no keys. The S3 shop has only 1 office with keys. The CDR, CSM, XO, W3 and BAO do not have a key to their office, and this BDE has made hundreds of requests for new keys to DPW over the past decade. Getting cipher locks is going to solve most of these issues. However, they are very expensive and we have to pay for them out of our own unit funds.

1.2 Objective. Replace all the locks to increase physical security in BDE HQ and eliminate the need for keys therefore making key control easier to manage.

2.0 Tasks. Work will be accomplished in four phases.

Phase 1 - Survey Phase 2 - Equipment purchase Phase 3 – Installation Phase 4 – Testing

2.1 Phase 1. Contractor will perform a survey of the building to confirm the number of cipher locks needed to accommodate physical security standards.

2.1.1 Perform a visual check of all doors and determine which doors have the highest priority.

2.2 Phase 2. The contractor will furnish all equipment, supplies, and tools needed to complete installation of Cipher KABA locks.

2.3 Phase 3. The contractor will perform the following tasks for each door:

2.3.1 Install and test 5 pin and 10 pin Kaba cipher lock on the determined doors, there are 17 total.

2.3.2 Services include labor for hardware replacement and supporting services support for 12 month periods.

2.4 Phase 4. At the conclusion of the installation (Phase 3) all the locks will be tested and codes will be documented and kept with key control managers (S2) and with DPW real estate.

3.0 Contractor Responsibilities.

3.1 Provide hands-on, onsite training for using and resetting the locks. The training will be new equipment training to teach basic operation of each lock such as how to use, reset, and basic troubleshooting. The end user training will be new equipment training in the basic operation and familiarization of the lock.

3.5 Provide a single POC (Program Manager/Contract Manager) for implementation and be overall responsible for this project. The name of the Program Manager and an alternate who shall act for the Contractor when the Program Manager is absent shall be designated in writing to the Contract Officer at least 10 days prior to the contract performance. The POC or alternate shall be physically present on-site when the work is being executed.

4.0 Government Responsibilities.

4.1 The Government will provide Contractor with continuous access, 8 hours a day, to the applicable installation areas, and will escort Contractor personnel, if necessary, during installation, integration, and testing of the system.

The Government will provide escorts as necessary.

4.6 The Government will provide adequate electrical circuits in the vicinity of the equipment installation.

5.0 Data/Deliverables.

5.1 Period and Place of Performance. The principal place of performance will be Schofield Barracks, HI, BLDG 500

(2IBCT HQ)

5.2. Invoice/Payment Terms. Contractor will provide invoices for material received and services rendered as of the date of invoice. The Government will authorize payment of each invoice submitted for material received by Contractor and services rendered as of the invoice date.

5.5 Warranty Support.

5.5.1 Manufacturer-provided commercial warranties will be extended to the Government. This warranty does not include the removal/re-installation of failed equipment. Contractor warrants its workmanship for one (1) year from date of acceptance. This warranty does not apply to supplies and consumables, products with original identification marks removed or altered, or services with defects or failures due to disaster, Acts of God, Acts of Terrorism or war, accident, neglect, or misuse; failure or defect of electrical power, external electrical circuitry, air conditioning, or humidity control; use of products with items not provided or approved by Contractor; or modifications, adjustments, repairs, or service provided by anyone other than Contractor or its authorized service provider.

5.5.2 Contractor will provide 24/7 telephone Warranty Help Desk support for one (1) year after completion of installation. Upon notification of a lock malfunction, Contractor will respond to the designated site facilitator/POC within one (1) hour via telephone or VTC to begin troubleshooting. The equipment supplied by Contractor will be the demarcation point for Warranty Support.

5.5.3 During the warranty period, in the event the Contractor does not resolve the problem, Contractor will assist the Government in obtaining Return Material Authorization (RMA).

5.6 Government--Furnished Property, Facilities, or Resources. None