This document is a Statement of Work (SOW) for a federal contract opportunity to replace HVAC ductwork and a fresh air damper at the Milwaukee, WI Air Traffic Control Tower (ATCT) and Terminal Radar Approach Control (TRACON) building.

The key details are: The contractor shall furnish all labor, supplies, materials, and equipment to complete the work. The work must be done Monday through Friday between 0600-1700 hours, with full shutdowns coordinated on weekends. The period of performance is 30 days after the Notice to Proceed. Contractors will be escorted at all times while on-site. The work includes demolition, fabrication and installation of new supply air plenum and ductwork, adding a new damper and modulating valve, and programming Schneider controls. All products and materials must be approved by the Contracting Officer's Representative prior to beginning work. The related federal contract opportunity is Solicitation Number 697DCK-24-R-00540 for "Milwaukee ATCT - Minor HVAC Work", with an estimated project size of less than $75,000, issued by the Department of Transportation Federal Aviation Administration Southwestern Region.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work

Requirement : Contractor shall furnish all labor, supplies, materials, and equipment to replace HVAC ductwork and fresh air damper at Milwaukee, WI ATCT and TRACON building.

Location: 5330 S. Howell Ave., Milwaukee, WI 53207

Contracting Officer’s Representative: A COR will be assigned to this project and copy of their delegation letter will be provided to the contractor. The delegation memorandum will spell out the responsibilities and limitations of the COR

Authority: Only the Contracting Officer has the authority to make changes to the contract. Any action taken on the part of the contractor without proper approval from the Contracting Officer is solely the responsibility of the contractor and may not be reimbursed by the Government.

Hours for Work: Work shall be conducted Monday thru Friday between the hours of 0600-1700.

Full shutdowns should be done on the weekend and must be coordinated with the Contracting Officer’s Representative (COR).

Period of Performance: All on-site work must be completed within 30 days after issuance of the Notice to Proceed by the Contracting Officer (CO).

Security: Contractors will be escorted at all times while at the FAA facility.

Contractor will:

1. Demoli on of old supply plenum and associated leaking supply duct.

2. Fabricate and install new extended supply air plenum.

3. Fabricate and install new supply branch ducts into exis ng supply ducts.

4. Add new buna seal to connec on surface joining supply plenum and AHU-10.

5. Remove and reinstall Humidifier Steam Wand into new supply plenum.

6. Purchase and Installa on of new Greenheck, or equal, VCD-34 Low Leakage Insulated Airfoil

Volume Control Damper.

7. Installa on and integra on of Belimo, or equal, Modula ng Valve on new outside air damper.

8. Necessary Schneider Program modifica ons to properly control return air and outside air dampers.

All products, materials and equipment to be used to accomplish work must be submitted and approved by the COR prior to commencement of work. All work performed must meet all Federal, State, and local regulatory codes regardless of whether it is contained in this Statement of Work.