SOW - HML NMR Gen Fuel tank .doc

DOC document 75 KB Posted

Attached to
Generator Fuel Tank - Hollings Marine Laboratory, Charleston SC
Solicitation number
1305M223RNCNS0029
Issued by

About this file

This statement of work outlines requirements for replacing the 150-gallon diesel fuel day tank that serves as backup power for a nuclear magnetic resonance facility at the Hollings Marine Laboratory. The National Oceanic and Atmospheric Administration seeks to upgrade to a 700-gallon double-walled tank and associated equipment to extend backup runtime from 3.125 hours to 14.58 hours. Contractors must show experience maintaining generator backup systems and hold required licenses and certifications. The work includes removing the existing tank; installing a temporary fuel supply; constructing a support pad; installing the new tank, fuel lines, and electrical and control connections; testing; and complying with safety, security, and environmental requirements. The point of contact is Mr. Randy Grady, and questions may also be directed to Mr. Richard Sparkman.

View the file

Other files

File Type Posted
SF-30 Amendment 0002.doc DOC document
SF-30 Amendment 0001.doc DOC document
Wage Determination SC20230023 1-06-2023.pdf PDF
FormSF1442.pdf PDF
REQUIREMENT.docx DOCX document
Past Performance Reference Sheet.pdf PDF
Construction Clauses.DOCX DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work

HML NMR Generator Fuel Tank Upgrade NOAA Hollings Marine Laboratory

331 Fort Johnson Rd

Charleston, SC 29412 General

The Department of Commerce (DOC)/National Oceanic Atmospheric Administration

(NOAA)/ the National Ocean Service (NOS)/ Hollings Marine Laboratory (HML), located at 331 Fort Johnson Road, Charleston, SC is a federal research laboratory housing five (5) scientific business partners. The HML is a 117,000 square foot laboratory facility which includes laboratories, office spaces, a nuclear magnetic resonance (NMR) facility and an aquaculture facility.

Objective The Charleston facility has a requirement to replace the existing NMR Generator 150 gal Tramont diesel fuel day tank located outside the F Section. This generator and fuel system serve as the primary backup electrical power support for the HML’s NMR system located in the N section, first floor. The requirement to provide emergency backup electrical support to this delicate science equipment dictates the need to maximize the stand alone run time for this particular generator. In order to accomplish this task, increasing the current direct feed fuel available to the generator from the current 150gal tank to a 700 gal capacity diesel fuel tank is needed. As a result, the system at a full load burn rate of 48gal/hr will increase operational run time from 3.125 hrs to 14.58 hrs before the transfer of fuel from the main fuel storage tank is required. Historically the fuel transfer system has shown to be unreliable and this upgrade will mitigate that issue until a long-term solution can be implemented. The proposed replacement of the generator fuel tank system will extend emergency support system resilience and ensure the operational safety of the equipment.

Qualifications

The company/contractor must show competency and experience in the operation, maintenance, controls and service/repair of generator backup systems that operate in medium industrial, commercial, institutional, medical and/or academic facilities.

CERTIFICATIONS The Contractor shall provide proof that personnel performing work under this contract have valid state or local license or certification for generators covered under this contract. Persons performing maintenance shall have participated in a Certification Program within the last 12 months.

KEY CONTRACTOR PERSONNEL

Contractor’s key person or personnel list shall be provided to the Contracting Officer and Contracting Officers Representative (COR) fifteen (15) days prior to the start of the contract and shall be updated when approved changes are made.

The servicing contractor will perform the elements of this statement of work with factory trained, skilled, professional technicians, which are familiar with inspection, maintenance and repair procedures. Evidence of the above requirements shall be included with the vendor's quote.

Scope of Work A) Removal:

The Contractor shall install a temporary tank (500 gal min) as a fuel supply during the installation process to ensure continued availability of generator for back up support. The contractor shall remove and dispose of the existing 150 gal diesel fuel storage tank. The existing unit will be secured and all lock out/tag out procedures will be met and the unit will be electrically isolated so that proper removal can proceed. The Contractor shall remove waste and dispose of materials and debris on a daily basis. Clean up and disposal of materials and debris shall be done in full compliance with all local, State, and Federal Regulations. Contractor shall provide a certificate from a licensed disposal facility confirming that all material has been disposed properly. Removal, demolition, and cleanup shall be done in coordination with the Facility operations supervisor so that a minimal impact on HML operations.

B) Construction:

The Contractor shall construct a contract pad as required to support the manufacture specifications for the new 700 gal tank. Construction details (dimensions, load capacity, composition, location) are to be approved by onsite facilities operation supervisor prior to construction. Pad location considerations for adjacent support systems (LN2 supply, etc..) will be addressed prior to construction and approved by facility operations supervisor.

C) Installation:

Once removal and concrete pad construction are complete, the Contractor will install a new Tramont 700 gallon (double walled) UTRS-700 700 Gallon Day Tank System UL-142, ULCS601 listed with Tramont System 2000Plus, Day tank and any required equipment necessary for proper operation of the system. The contractor shall connect the new tank to the existing supply and return fuel lines for both the generator and the fuel transfer system IAW manufacture specifications and industry standards. Required electrical power and control connections shall be reinstalled and approved by facilities operation supervisor.

D) Testing:

Once repairs are complete the system will be tested for proper operation, approved by facilities operation supervisor, the generator will be placed in normal service. The repairs required should be characterized by performance of consistently reliable maintenance and service procedures. Prior to the current issue with the system, service and inspection of the generator was completed on an annual basis.

E) Safety Contractor employees shall immediately upon arriving to the job site; check-in with the facility operations supervisor and or Building Receptionist at the front desk and immediately prior to their departure from the job site shall check-out with the facility operations supervisor and or Receptionist at the front desk. During afterhours callbacks; the Contractor employees shall check-in with the building engineer on duty.

1. Lockout – tag out

2. Electrical safety – high voltage

3. Hazardous communications

4. Personal protective equipment

5. Fall protection

· The Contractor shall provide and ensure that all personnel at the work site wear the safety devices/apparel described below when working on the generator Systems.

1. Approved back support and protective devices

2. Eye protection in compliance with ANSIZ87.1. -1968.

3. Approved hearing protection

4. Approved hand protection

5. Other safety devices/apparel when conditions warrant

· The Contractor shall furnish documentation as directed by the Contracting Officers Representative (COR) of the completion of the approved safety training of equipment operators and other personnel. The safety training shall comply with all OSHA standards and a sample program shall be submitted to the Contracting Officers Representative (COR).

· The Clients Safety Officer reserves the right to inspect all areas for safety violations at its discretion, direct the Contractor to make immediate improvement of necessary conditions and/or procedures, and/or stop the work if other hazards are deemed to exist.

· In the event that the Client Safety Officer should elect to stop work because of any type of existing safety hazards after the Contractor has been notified and provided ample time to correct, the Contractor shall bear all costs for eliminating the hazard(s) and shall not be granted compensation for the work stoppage. The Contractor shall pay all additional expenses.

· The Contractor shall be responsible for initiating, maintaining and supervising all safety precautions and programs in connection with the performance of the contract. The Contractor shall take all necessary precautions for safety of, and shall provide reasonable protection to prevent damage, injury or loss to persons, properties, equipment and vehicles.

· The Contractor shall, without additional expense to the Client, be responsible for obtaining and renewing all necessary licenses and permits. The Contractor shall also be responsible for all damages to persons or property that occur as a result of the Contractor’s negligence and shall take proper safety and health precautions to protect the work, the workers, the public and the property of others. In addition, the Contractor shall be responsible for all materials delivered and work performed until completion and acceptance of the entire work.

· The Contractor shall comply with all applicable revisions, additions, changes and/or upgrades to any Federal, state, and municipal laws, codes, and regulations which are in effect on the date of contract and which affect the performance of the work.

Pre-Bid Site Visit All vendors are highly ENCOURAGED to attend a pre-bid site visit at Hollings Marine Laboratory. Even though not mandatory, more weight will be given in the bid evaluation for those in attendance. The site visit time and date will be upon request. During the site visit, prospective vendors will have the opportunity to review engineering drawings and inspect locations around the facility where the generator systems operate. The Facility operations supervisor will be available to answer questions during the site visit.

Personnel The contractor shall provide proof that all on-site employees are U.S. citizens or legal aliens. The contractor shall not employ personnel with felony convictions, or with a record of narcotics use, for work at Hollings Marine Laboratory. The contractor is responsible for completing a security investigation on all employees working at the Hollings Marine Laboratory in connection with this contract.

Conduct of Contractor Personnel The contractor’s employees are subject to and shall observe and comply with applicable regulations, policies, and procedures. Contractor employees shall not enter restricted areas in accordance with security regulations and safety policies. The Contractor shall be responsible for the selection, certification, assignment, supervision, management, and control of employees with the advice of the Contracting Officer (CO) and/or the Contracting Officers’ Representative (COR) in the performance of all contract work. The removal from the job site of any employee shall not relieve the Contractor of the requirement to provide enough personnel to perform the terms and conditions of the contract. The Contractor’s employees shall not use offices, rooms, work areas, etc. for their own use. When a task is completed, such employees shall immediately leave the area. Contract personnel shall not use or operate telephones, radios, computer terminals, or any other Government or privately-owned equipment or property without the express permission of the COR. The Contractor’s employees shall not disturb papers on desks, nor open desk drawers or cabinets. Breaks shall not be spent in offices or room areas, but taken only in the assigned rest areas. The Contractor’s employees shall not loiter in any working, patron, or other unauthorized areas. While waiting for transportation, or while on work breaks, they shall not block or impede movement on ramps, doorways, corridors or walkways.

Security Requirements Contractor employees shall comply with all security requirements. Copies of pertinent policies, regulations, and procedures will be provided to the Contractor upon request. Fifteen days prior to the contract start date, the Contractor shall submit to the Contracting Officer and or the Contracting Officers Representative the full name and any alias, address, city and state and date of birth of each employee hired to work on this contract. This employee list shall be constantly kept up-to-date. The Contractor shall fill out any questionnaires or other forms as may be required by the Government for security purposes. All Contractors will be required to register at front desk and receive a temporary pass for one day and, if needed, a door pass card will also be provided.

Work Schedules/Shifts The Contractor shall accomplish all work for the Hollings Marine Laboratory during the hours of 0700 and 1600 Monday through Friday, excluding Federal Holidays. This allows the flexibility for the contractor to schedule 8 hours of work during a time when Hollings Marine Laboratory staff will be at the facility.

Guarantee of Work Contractor shall guarantee all work and agree to remedy, at its own expense, any defects caused by poor workmanship or materials.

Conformance with Environmental Management Systems The Contractor shall perform work under this contract consistent with the relevant policy and objectives identified in the agency, organizational, or facility environmental management system (EMS) applicable for your contract. The Contractor shall perform work in a manner that conforms to all appropriate Environmental Management Programs and Operational Controls identified by the agency, organizational, or facility EMS, and provide monitoring and measurement information as necessary for the organization to address environmental performance relative to the environmental, energy, and transportation management goals. In the event an environmental nonconformance or noncompliance associated with the contracted services is identified, the contractor shall take corrective and/or preventative actions. In the case of a noncompliance, the Contractor shall respond and take corrective action immediately. In the case of a nonconformance, the Contractor shall respond and take corrective action based on the time schedule established by the EMS Site Coordinator. In addition, the Contractor shall ensure that their employees are aware of the roles and responsibilities identified by the environmental management system and how these requirements affect their work performed under this contract.

1. Register at front desk and receive a temporary pass for one day (if needed a door pass card will be provided)

2. The front desk personnel will have you read a brief statement concerning the EMS, the Facility operations supervisor or designated maintenance staff member will convey to the contractor any other items that need to be done to protect the Hollings Marine Laboratory and the environment issues we have.

IT Security Requirements The Certification and Accreditation (C&A) or Assessment and Authentication (A&A) requirements of Clause 48 CFR 1352.239-72 do not apply, and a Security Accreditation Package is not required.

The contractor shall not have access to any government owned equipment or be furnished government privileged information. All hardware and software provided in this contract will become the property of the government.

The contractor shall only supply software, product license and will not require the use of any contractor owned equipment. The contractor will not have remote access to any government owned equipment. The software and hardware related to this acquisition will be incorporated into an existing government Certification and Accreditation (C&A) or Assessment and Authentication (A&A) package.

The contractor shall provide all supporting documentation or a reference to obtain the necessary material which describes the security capabilities, the design and development processes and the testing and evaluation procedures used by the product or services being provided for this acquisition.

The contractor shall provide all supporting documentation or a reference to obtain the necessary material which describes all product or service updates and enhancements as they are implemented. For example, the product or service supporting documentation could be the user and system administrator guides, which document the functional properties of the security controls employed and allow for the analysis and testing of the security controls.

Additional Requirements and Provisions Contractor Qualifications:

In determining the responsibility of a contractor, the following criteria will be considered.

Contractors may be asked to produce evidence so their responsibility can be determined.

1. The contractor must have at the time of proposal any and all applicable licenses as required under the laws of South Carolina, Federal laws, and any local laws or ordinances for the performance of work under this agreement.

2. Adequate capital and credit rating sufficient to complete all operations under this agreement.

3. Whether the contractor can provide the service promptly, or within the time specified, without delay or interference.

4. The character, integrity, reliability, reputation judgment, experience, and efficiency of the contractor.

5. The quality of performance of previous contracts and services.

6. An adequate supply of equipment in good condition and adequate manpower to perform the service.

7. The contractor must submit an organizational chart of the Service Company showing location of offices and employees that will be associated with the administration and performance of this contract.

Point of Contact The Facilities Branch Chief, Mr. Randy Grady (252) 725-3541 will serve as the Point of Contact for specific questions concerning this Statement of Work (SOW). For any questions concerning the generator equipment or for site visit, please contact Mr. Richard Sparkman, Facility Operations Supervisor, at (808) 295-3822.