U.S. General Services Administration
Public Buildings Service
Greater Southwest Region
SANITARY & VENT PIPES REHABILITAION, MIDLAND, TX (V8-2/12/2019)-1
Date: February 20, 2021
Scope of Work
1. Project Title: Sanitary and Vent Pipe Rehabilitation
RTX33446
ePM# 65409
2. Project Location: TX0220MD
George HW Bush Federal Building 200 East Wall Street Midland, Texas 79701
3. Building Location Hours: Contractor will be allowed to work from 6:30am to 4:00pm. Normal business hours for this facility are Monday through Friday 6:00 am to 6:00 pm. If there is a requirement for work outside these normal business hours, the contractor shall request approval from the GSA PM / GSA building manager at least 72 hours in advance of the work to allow for proper scheduling and coordination of business operations.
4. Purpose: Repair existing sanitary waste and vent sewer and riser pipes of George HW Bush Federal
Building. The four-story building (plus basement) was built in 1971. The existing cast iron pipes which extend from the basement up through the roof are suspected to be leaking, cracked, rusted, corroded, and/or clogged. The building requires these needed repairs to extend the life of the building, prevent damage, and provide a safe and comfortable atmosphere for tenants.
5. Points of Contact:
5.1 Contracting Officer: Stephan Harris
Phone: 817-505-5132
Stephan.harris@gsa.gov
5.2 Project Manager: Duc Le
Phone 281-772-6072
Duc.le@gsa.gov
5.3 Property Manager: Johnny Ferraro
Phone 682-208-6696 johnny.ferraro@gsa.gov
AND: Lucas Ontiveros
Phone: 806-472-7401
Lucas.ontiveros@gsa.gov mailto:Stephan.harris@gsa.gov mailto:Duc.le@gsa.gov mailto:johnny.ferraro@gsa.gov mailto:Lucas.ontiveros@gsa.gov
SANITARY & VENT PIPES REHABILITAION, MIDLAND, TX (V8-2/12/2019)-2
5.4 Other: R7 Security Clearance Coordinators
r7clearance@gsa.gov
6. Notice to Proceed:
6.1 The Contracting Officer is the ONLY individual from the Government that can give the contractor a notice to proceed.
6.2 Before any of the work within the scope of the contract is started, the Contractor shall confer with the COR (Contracting Officer Representative) and agree on a sequence of procedure;
means of access to premises and building; delivery of material and use of approaches; use of corridors, stairways, elevators, and similar means of communications; and the location partitions, eating spaces for spaces for Contractor’s employees and the like.
7. Period of Performance: The total period of performance for this task order is 365 days after Notice to Proceed.
7.1 NACI – Security clearances – 45 days
7.2 Phase I – Pre-construction
7.2.1 Develop Repairs & Replacement Strategy – 14 days
7.2.1.1 External Visual Inspection
7.2.1.2 Pre-Clean Video Inspection
7.2.1.3 Pipe Cleaning & Descaling
7.2.1.4 Post Cleaning Video Inspection
7.2.2 Reports -14 days
7.2.2.1 Findings Sanitary & Ventilation
7.2.2.2 Recommended Repairs methods for each Pipes/Riser/Horizontal of each areas
7.2.2.3 Estimates
7.2.2.4 Schedules – Time & Sequences
7.2.3 GSA Reports Review – 7 days
7.2.4 Contractor Submittal (PDF Electronic Format, Video files) – 7 days
7.3 Phase II – Construction & Close out
7.3.1 Construction: - 240 days
7.3.1.1 Submittal
7.3.1.2 Pipe Preparation
7.3.1.3 CIPP Installation & Conventional (if required)
7.3.1.4 Restoration of openings
7.3.1.5 Testing/Post Installation Video Inspection
7.3.1.6 Restoration Interior surfaces
7.3.1.7 Final Clean up
SANITARY & VENT PIPES REHABILITAION, MIDLAND, TX (V8-2/12/2019)-3
7.3.2 Substantial Completion – 14 days
7.3.2.1 Third Party Testing Results (Report & Final Video)
7.3.2.2 Curing Data for each pipe
7.3.2.3 Waste Diversion – Final
7.3.2.4 O&M Manual
7.3.2.5 As-built – AutoCad & PDF
7.3.2.6 Warranties
7.3.2.7 GSA Substantial Completion Inspection
7.3.3 Punch List – 30 days
7.3.4 Final Inspection – 7 days
7.4 Contractor must start employee clearance process within ten (10) days after award.
7.5 Commence Installation Work no than (NLT) ten (10) days after Owner approval of Report of
Findings.
7.6 Substantial completion: The Contractor shall achieve Substantial Completion of the Work as agreed upon in the Contract Award and meet the requirements in the SOW and Specifications.
7.7 Contract Completion: The Contractor shall achieve Contract Completion within (30) calendar days from substantial completion. This includes all punch list items corrected, and all documentation required in this contract for close-out given to the Owner in a complete and proper delivery in accordance with this contract.
8. Description of Work: The project involves the rehabilitation of existing sanitary sewer and waste and vent piping mainly using the Cured-In-Place Technology (CIPP) method to minimize demolition and disruption of tenants as much as possible. Conventional method shall be used when piping is conveniently accessible and when necessary to connect lined pipe to branch drain piping.
8.1 It is critical that the building remain operational during normal business hours. To reduce the risk of pipe lining failures that may result from the accidental introduction of water into the pipe during the lining process only a 100% solids epoxy resin meeting either ASTM F1216 or ASTM 1743 requirements and having no VOC’s. This resin used in CIPP or Brush-on application shall be employed using a thermosetting resin technology with accelerants in the resin to expedite or retard curing times.
8.2 The locations and associated pipe diameters, materials, and approximate lengths to be lined will need to be verified by Contractor. Contractor shall provide all materials, labor, tools, equipment, supervision, and other services or work necessary for the proper execution of the requirements described in this document.
9. Project Requirements: The Project shall be divided into two (2) phases. Based upon the information obtained during Phase I GSA reserves the right to continue with Phase II; modify the Scope of Work for Phase II; or to terminate the task order at the conclusion of Phase I.
9.1 Phase I of the project includes but is not limited to the following work:
9.1.1 Review of existing plans, specifications and building information.
9.1.2 Preliminary site evaluation to determine access areas and coordinate schedules and building access for this phase of work.
9.1.3 Selective demolition work as required to conduct survey and cleaning operations.
9.1.4 Pre-Cleaning Video Survey of existing pipes to determine proper cleaning methods.
SANITARY & VENT PIPES REHABILITAION, MIDLAND, TX (V8-2/12/2019)-4
9.1.5 Cleaning and de-scaling of pipe interiors for pre-inspection of the system.
9.1.5.1 Cleaning and de-scaling methods shall be based upon condition of pipe observed during Pre-Cleaning Video Survey.
9.1.5.2 Obtain GSA approval of methods prior to the start of cleaning operations.
9.1.5.3 All debris from cleaning operations shall be properly disposed of offsite.
9.1.5.4 Maintain a clean and orderly site during on a daily basis.
9.1.6 Post-Cleaning Video Survey to determine appropriate relining/replacement strategies
9.1.7 Preparation of schedules, estimates and construction narratives to define the proposed rehabilitation procedures.
9.1.8 Recommendations shall include both conventional pipe replacement and pipe lining solutions based upon the observed conditions of the existing pipe.
9.1.9 If GSA elects to terminate the Task order upon the completion of Phase I:
9.1.9.1 The Contractor shall restore all finishes to original conditions
9.1.9.2 Contractor shall follow Project Close-Out Procedures
9.1.9.3 Submission of a copy of each video survey, estimate, schedule and construction narrative in electronic format.
9.1.9.4 Owner Acceptance of Work
9.1.9.5 Financial Close-Out.
9.2 Phase II of the project includes but is not limited to the following work.
9.2.1 Alterations to Existing Conditions: Existing conditions shall be cut, drilled, removed, temporarily removed, or removed and replaced, as necessary for performance of Work under the Contract.
9.2.1.1 Replacement of existing conditions that are removed shall match similar existing conditions.
9.2.1.2 Unless otherwise indicated, existing structural members shall not be cut or altered without authorization by the Contracting Officer.
9.2.1.3 Conditions remaining in place, which are damaged or defaced during the Work, shall be restored to the condition existing at the time of award of Contract.
9.2.1.4 Discolored or unfinished surfaces exposed by removal of existing conditions, that are indicated to be final exposed surfaces, shall be refinished, or replaced as necessary to produce uniform and harmonious contiguous surfaces.
9.2.2 Utilizing Cured-In-Place-Pipe (CIPP) or Picote Brush-on technology to rehab the existing sanitary sewer and sanitary waste and ventilation riser pipe.
9.2.2.1 Resin utilized in the relining process shall be cured by a thermosetting resin.
9.2.2.2 Equipment and materials employed shall be non-shrink epoxy-based resin using
100% solids and no VOC’s for all work performed in occupied space or in the interior of buildings. No Styrene based materials are acceptable.
9.2.3 Re-Instatement of openings at existing fitting locations and/or replacement of riser fittings as required.
9.2.4 The rehabilitated pipes will result in a complete and fully functional system meeting specifications. GSA reserves the right to employ a third-party inspector to review the installations.
9.2.5 Perform a Post-Lining Video Survey of each completed installation.
9.2.6 Restore existing finishes to pre-construction conditions.
9.2.7 Complete Project Close-Out requirements including but not limited to the following:
9.2.7.1 Complete all punch list items
9.2.7.2 Provide As-Built drawings indicating all repairs under this contract.
9.2.7.3 Provide copies of all warranties
9.2.7.4 Complete all punch list items
9.2.7.5 Final Cleaning
SANITARY & VENT PIPES REHABILITAION, MIDLAND, TX (V8-2/12/2019)-5
9.2.7.6 Owner Acceptance
9.2.7.7 Financial Close-Out
9.3 Conferences and Meetings:
9.3.1 Pre-Construction Conference: A preconstruction conference will be scheduled prior to the start of Work. A time and place will be agreed upon after award.
9.3.2 Progress Meetings: The Contracting Officer’s Representative (COR) shall conduct regularly scheduled progress meetings at the Project Site. Dates and meetings shall be determined at the Pre-Construction conference.
9.3.3 Substantial Inspection: Inspection will take place at the request of the Contractor on an agreed upon date and time. On the same day as Substantial Inspection, Contractor will discuss their close-out plan.
9.4 Submittal Schedule: Schedules and reports are required for documenting the progress of construction during performance of the Work. Coordinate the timing for preparation and processing of schedules and reports with the performance of other construction activities and maintain a consistent and logical correlation between updated schedules and reports.
9.4.1 Submittal Schedule: The submittal schedule shall list all submittals required by the
Contract, Scope of Work, Attachments, and specifications.
9.4.1.1 Provide the Owner not less than 7 calendar days for review of each submittal.
9.4.1.2 Submit submittal schedule within 30 days of award.
9.5 Qualifications of Personnel:
9.5.1 The personnel employed by the contractor shall be capable employees or sub-contractors trained and qualified in the installation of CIPP methods.
9.5.1.1 Qualified personnel shall have prior experience installing CIPP in at least (2) two federal buildings within the past 5 years.
9.5.2 A detailed resume containing the information specified below must be submitted with proposal. Resume being on 8 1/2” x 11” and no more than 4 pages long using a 12 font.
9.5.2.1 The full name of the Company or Firm who will be installing the CIPP.
9.5.2.2 A detailed description of the previous 5 years’ experience installing CIPP and on Federal buildings using CIPP. Provide names, address, and dates of the Agencies and Buildings CIPP was installed.
9.5.3 Licensed Architect and Engineer firms are required to performed following tasks:
9.5.3.1 Updates as-built drawings
9.5.3.2 Inspections
9.5.3.3 Review & Recommendation on Submittals
9.6 Security: All contractor and sub-contractor personnel will be required to meet the latest established and recognized requirements of Homeland Security Presidential Directive (HSPD-12), as well as all local building access requirements and procedures.
9.6.1 Individual employees will submit security clearance request in advance of contract performance, with all required forms, identification, and certifications needed to have security clearance adjudication by the appropriate office of Department of Homeland Security.
9.6.2 No un-cleared personnel will be allowed in the building to perform work at any time.
9.6.3 All Contractor personnel are required to possess authorized badges with an expiration date not less than 5 years from the date work shall commence.
SANITARY & VENT PIPES REHABILITAION, MIDLAND, TX (V8-2/12/2019)-6
9.7 Project Criteria: The project shall conform to the following criteria.
9.7.1 PBS-P100 Facilities Standards for the Public Buildings Services
9.7.2 GSA Region 7 IDIQ Specifications
9.7.3 Scope of Work
9.7.4 Performance Specifications for CIPP
9.7.5 Sustainability –Attachment 1
9.7.6 Waste Diversion-Attachment 2
9.8 Delivery: Work shall be completed in phases:
9.8.1 PHASE 1 - INVESTIGATION: Site inspection, Video, and Pipe sample testing.
9.8.1.1 The contractor shall perform field reconnaissance, site investigations, video investigations, and pipe testing to obtain engineering information and design data for the accomplishment of the requirements of this SOW.
9.8.1.2 Contractor shall determine Repair and Replacement strategy based upon their field survey and assessment of existing conditions.
9.8.1.3 Contractor shall determine method of cleaning based on existing conditions.
9.8.1.4 Contractor shall determine wall thickness of each CIPP.
9.8.1.5 A Report of Findings shall be given to Owner with test results, methods of rehabilitation and cleaning, and wall thickness for each pipe using the CIPP method. Along with a schedule of sequenced work.
9.8.1.6 Owner shall review and approve Report of Findings prior to start of Phase 2.
9.8.2 PHASE 2 – SANITARY SEWER AND WASTE AND VENT RISER PIPE:
cleaned or demolished, rehabilitated or replaced, inspected, and tested.
9.9 Acceptance:
9.9.1 Acceptance will be in accordance with the Performance Specification for CIPP, Part 3, Section 3.7 Final Acceptance.
9.9.2 Conventional methods and all other construction required for this project will be in accordance with Region 7 specifications.
9.9.3 All plumbing lines will be labeled in accordance with Region 7 specifications.
9.9.4 For progress payments – CIPP by Perma-Liner, Picote, or equal installation work must have been inspected and tested. All testing reports and inspections must meet manufacturer’s requirements.
9.9.5 Pipes are fully functional and without leaks or other defects.
9.9.6 All close-out documents have been received and are complete and correct.
9.10 Progress & Compliance:
9.10.1 Schedule updating: The contractor shall revise the construction schedule bi- monthly and an updated schedule attached to each progress payment.
9.10.2 Pipe installation must be inspected and tested and comply with manufacturer’s specifications.
10. Options: An option provides an amount proposed by the Contractor and stated on the Bid Form for certain work that may be added (or deducted - preference is for add options) by the Government to the project Work within a specific time after award of the task order. The amount for an option shall be the net total addition (or deduction) to the task order price to incorporate the option work into the project Work.
10.1 Option work shall include miscellaneous devices, accessory objects, and similar items incidental
SANITARY & VENT PIPES REHABILITAION, MIDLAND, TX (V8-2/12/2019)-7
to or required for a complete installation, whether or not mentioned as part of the option description.
10.1.1 Selection: An option must be accepted by the Government within 90 calendar days after award of the task order to be included in the project Work. Each option must be accepted by the Government within the time stated to be included in the project Work.
10.1.2 Notification: If an option is accepted, the Contractor shall immediately notify each party involved, in writing.
10.1.3 Coordination: The Contractor shall adjust affected adjacent work as necessary to integrate the accepted option work completely and fully into the project Work.
10.1.4 Evaluation: Except when it is determined in accordance with FAR 17.206(b) not to be in the Government’s best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).
10.2 Option #1 – Asbestos-Containing Materials (ACM) Abatement: contractor is required to test and confirm the existing piping insulation for ACM. Demo and abate the ACM piping insulation and black mastic in existing piping insulation, estimated 2,500 linear feet of piping.
11. Liquidated Damages: $400.00 per day will be assessed each day past the substantial completion date and will be deducted from contractor’s final payment application.
12. Sustainability: The following will be required.
12.1 Green Purchasing: See attachment 1 for all green purchasing requirements
12.2 Waste Diversion: To the extent able, within fifteen days after award, the Contractor shall submit to the Project Manager, a Non-Hazardous Solid Waste Management Plan to include (not limited to):
a) List of materials Contractor will reuse
b) List of materials the Contractor will donate and name and address of donation recipient.
c) List of materials the Contractor will recycle and the name and address of the recycler.
If Contractor receives recycling revenue, Contractor shall keep revenue and provide receipt for GSA for reference.
d) Name and location of solid waste landfill for non-diverted material.
13. Attachments:
13.1 Attachment 1: Sustainability
13.2 Attachment 2: Waste Diversion Plan
13.3 Attachment 3: Site Location Map
13.4 Attachment 4: Specification for Cured-in-Place-Pipe
13.5 Attachment 5: Drawings – Plumbing plans
14. Closeout Plan:
14.1 30 days prior to Contract Completion, discuss contractor’s close-out plan.
14.2 Government Acceptance: Upon completion of work, the Government shall inspect and verify that the work is complete. All work found to be unacceptable shall be removed, replaced, and installed at Contractor’s expense.
14.3 Final Punch list complete within 30 days of Substantial Completion Inspection.
14.4 All submittals, O/M manuals have been submitted in electronic format.
14.5 As-Built drawings are correct on CD in AutoCAD and PDF format.
14.6 Financial Closeout
SANITARY & VENT PIPES REHABILITAION, MIDLAND, TX (V8-2/12/2019)-8
Attachment 1:
Sustainability:
• Green Purchasing:
o The contractor shall refer to the “Green Procurement Compilation” for all products being installed in federal facilities. The Green Procurement
Compilation can be found at https://sftool.gov/greenprocurement . The standards found in this compilation shall guide all product purchasing decisions as they relate to federal facilities.
o The use of the following standards (“Key Sustainable Product” or “KSP” standards) is mandatory for all contracts and task orders. See https://sftool.gov/green-products/1037/key-sustainable-products for more details.
▪ Nylon Carpet: NSF 140 Gold certification and > 10% post-consumer recovered content.
▪ Interior Latex Paint: < 50 grams per liter (g/L) VOCs post tint (i.e.
SCAQMD Rule 1113 standard).
▪ Gypsum Board: Greenguard Gold Standard or 0 g/L VOCs.
▪ Acoustical Ceiling Tiles: Meets California Section 01350 standard for low-VOC materials and total recycled content > 20% and recyclable in a closed loop process and USDA Certified Bio Preferred and
Environmental Product Declaration (EPD) available.
▪ Concrete (ready-mix and site-mix): > 25% fly ash or > 15% ground granulated blast-furnace (GGBF) slag
A. For each KSP listed, the Contractor shall submit proof of compliance to the CO or his designee prior to the installation of the product or material. The CO’s designee shall verify compliance.
B. If the KSP materials listed above are 1) not reasonably available within a reasonable period; 2) fail to meet the performance standards set forth in the specification or fail to meet reasonable performance standards of GSA; or 3) are available only at an unreasonable price, only then can the Contractor use other types of products. In these cases, the Contractor shall select products and materials, to the extent possible, which are the safest and most environmentally friendly. Exemptions must be submitted in writing and can only be approved by the CO https://sftool.gov/greenprocurement https://sftool.gov/green-products/1037/key-sustainable-products
SANITARY & VENT PIPES REHABILITAION, MIDLAND, TX (V8-2/12/2019)-9
Attachment 2:
Waste Diversion Plan:
1. Submittal Type: Pre-Construction or Final (Circle Appropriate Type)
2. ePM Number: 58964 (Should receive from GSA PM)
3. Field Office: Circle Appropriate Field Office:
Oklahoma City, Tulsa, New Mexico, Little Rock, Shreveport, Tyler, New Orleans, Baton Rouge, Dallas, Fort Worth, Midland Houston, San Antonio, McAllen, El Paso, Lubbock
4. GSA Project Manager: Duc Le
5. Contract Number:
6. Categories to Track:
6.1 Carpet: (rolled or tiled) Weight(lbs):
6.2 Architectural:(doors,windows,frames,millwork) Weight(lbs):
6.3 Ferrous Metals: (structural steel, studs, rebar) Weight(lbs):
6.4 Non-Ferrous: (wire, piping, duct) Weight(lbs):
6.5 Aggregate: (concrete,brick,blocks) Weight(lbs):
6.6 Plumbing Fixtures: (sinks,toilets,urinals) Weight(lbs):
6.7 Furniture: (Systems, casual, equip.) Weight(lbs):
6.8 Ceiling/Wall: (gypsum, tiles) Weight(lbs):
6.9 Roofing: (Shingles, Paper, membrane) Weight(lbs):
Recover Method:
Recover Method:
Recover Method:
Recover Method:
Recover Method:
Recover Method:
Recover Method:
Recover Method:
Recover Method:
7. Landfill Hauler:
Name and Address
8. Landfill Waste:
Name and Address
Recovery Methods: Recycled, Donated, Returned to Manufacturer, Use for Another Project Weights: If weight tickets available please submit, if not please estimate weight in lbs.
Contractor Signature:
Contractor Name Printed: Date
SANITARY & VENT PIPES REHABILITAION, MIDLAND, TX (V8-2/12/2019)-10