SOW genral.docx

DOCX document 26 KB Posted

Attached to
USCG ANT KODIAK COMPASS SWING
Solicitation number
70Z045-26-Q-KODI0001
Issued by

About this file

This is a Statement of Work (SOW) for magnetic compass adjustment services at the U.S. Coast Guard's AIDS to Navigation Team in Kodiak, Alaska. The contractor is required to adjust the magnetic compass for a USCG 38-foot asset and provide an updated and corrected deviation card upon completion. Work must commence no later than five days after notice to proceed and be completed within the timeframe specified for working days following contract award. The site visit will occur at US Coast Guard ANT Kodiak, with MK1 Seth Wilson designated as the Contracting Officer's QA Evaluator representative. Work execution is subject to weather, wind, and sea state conditions, and all work must be performed to best standard practices by experienced personnel under the supervision of qualified supervisors, with satisfaction determined by the Contracting Officer.

Contractor responsibilities include immediately notifying the QAE representative of the intended start date, obtaining all necessary appointments, licenses, and permits without additional government expense, and complying with all applicable federal, state, and local laws. All trash and debris must be removed from the site upon completion, and the contractor must contact the Contracting Officer's QAE representative to arrange for final inspection and acceptance of work. The related RFQ (Solicitation Number 70Z045-26-Q-KODI0001) indicates a government estimate of less than $4,000, a quote deadline of 2pm AST on February 23, 2026, and NAICS code 811210 (Electronic and Precision Equipment Repair and Maintenance) with a small business size standard of $34.0 million.

View the file

Other files

File Type Posted
COMBINED SYNOPSIS.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SCOPE OF WORK

1. GENERAL REQUIREMENTS:

SWING SHIP AND ADJUST COMPASS. Adjust the magnetic compass for a USCG 38FT Asset in Kodiak AK. Provide an updated and corrected deviation card upon completion.

2. COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK:

Upon acceptance the contractor shall commence work NLT five days after notice to proceed and work diligently to complete the entire work ready for use by working days after contract award.

3. SCOPE OF WORK:

Adjust the magnetic compass underway for a USCG 33FT Asset in Kodiak AK. Provide an updated and corrected deviation card upon completion.

4. SITE VISIT:

US Coast Guard ANT Kodiak

5. DESIGNATED CONTRACTING OFFICER’S QA EVALUATOR (QAE)

REPRESENTATIVE:

MK1 Seth Wilson

6. CONDITIONS AFFECTING THE WORK:

Weather, winds, and sea state

7. AFTER AWARD OF THE CONTRACT:

The contractor must immediately notify the contracting officer’s QAE representative of his intended start date. The work shall be done in accordance with the specification.

8. ORAL MODIFICATION:

No oral statement of any person other than the contracting officer shall in any manner or degree, modifies or otherwise affect the terms of this contract.

9. WORKMANSHIP:

All work shall be accomplished with the best standard practices, and by workmen thoroughly experienced in the required trades. The work shall be supervised by experienced personnel and shall be satisfactory to the Contracting Officer.

10. PERMITS:

The contractor shall without additional expense to the government, obtain all appointments, licenses, and permits required for the prosecution of the work. The contractor shall comply with all applicable federal, state and local laws.

11. CLEAN UP:

All trash and debris shall be removed from the site. The job site shall be left in a clean and neat manner.

12. UPON COMPLETION OF WORK:

Contact the Contracting Officer’s QAE Representative to arrange for inspection/acceptance Of work.

File details come from the government source that posted it. Updated .