SCOPE OF WORK
FOR
INSTALL NEW TILE FLOOR IN BUILDING 102 – GALLEY OFFICE
PROJECT #20191030
AT
U.S. COAST GUARD SECTOR KEY WEST
100 TRUMBO ROAD.
KEY WEST, FL 33040
July 2020
US Coast Guard Sector Key West Project No. 20191030 Install New Tile Floor in Building 102 – Galley Office
TABLE OF CONTENTS TOC-1 / 1
TABLE OF CONTENTS
DIVISION 1 - GENERAL REQUIREMENTS
011000 SUMMARY OF WORK
DIVISION 09 – FINISHES
096519 RESILIENT TILE FLOORING
ENCLOSURES
BUILDING 102 – GALLEY OFFICE SPACE DRAWING
END OF CONTENTS
SUMMARY 011000 - 1 / 3
SECTION 011000 - SUMMARY
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Project information.
2. Work covered by contract documents.
3. Phased construction.
4. Work by Government.
5. Access to site.
6. Coordination with occupants.
7. Work restrictions.
8. Safety precautions.
9. Site maintenance.
1.2 PROJECT INFORMATION
A. Project Identification: Install New Tile Floor in Building 102 – Galley Office | Project #: 20191030.
1. Project Location: US Coast Guard Sector Key West, 100 Trumbo Road, Key West, Florida 33040.
1.3 SCOPE OF WORK COVERED BY CONTRACT DOCUMENTS
A. The work of project is defined by the contract documents and consists of the following:
1. In general, this project consists of all work, including labor, equipment and materials, necessary remove the existing carpet in the Building 102 – Galley Office and install new vinyl composite tile floor and cove base.
WORK SEQUENCE
A. The work shall be conducted by the contractor to provide the least possible interference to the activities of government personnel.
SUMMARY 011000 - 2 / 3
B. Please provide notification to Coast Guard Sector Key West at least one full week prior to starting work. This will allow the Coast Guard to properly remove furniture in the space and vacate the work area.
1.4 WORK BY GOVERNMENT
A. General: Cooperate fully with Government so work may be carried out smoothly, without interfering with or delaying work under this contract or work by Government.
Coordinate the work of this contract with work performed by Government.
1.5 ACCESS TO SITE
A. General: During the construction period the contractor shall have limited use of project site for operations and material storage as specified by the Contracting Officer’s Representative (COR).
B. Pre-Bid Site Visits: Contractors are permitted to visit the site at their own expense prior to submitting bids/quotes in order to familiarize themselves with the project. Site visits can be arranged by contacting the Project COR. To make arrangements please contact the Sector Key West Engineering Officer:
1. LT Michael Cooper Engineering Officer USCG Sector Key West Email: Michael.G.Cooper@uscg.mil Office Phone: (305) 292-8756 Mobile Phone: (305) 797-2086
1.6 WORK RESTRICTIONS
A. Work Restrictions, General: Comply with restrictions on construction operations.
1. Comply with limitations on use of public streets and with other requirements of authorities having jurisdiction.
B. On-Site Work Hours: Limit work in the existing building to normal business working hours of 7:00 a.m. to 4:00 p.m., Monday through Friday, unless otherwise indicated.
1. Submit request to the COR at least 72 hours in advance for permission to work outside the normal working hours or on Saturdays, Sundays, or federal holidays.
C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated.
1. Submit request to the COR at least 72 hours in advance of proposed utility interruptions.
SUMMARY 011000 - 3 / 3
2. Obtain COR’s written permission before proceeding with utility interruptions.
D. Take action to prevent the spread of dust and debris.
1.7 SITE MAINTENANCE
A. The contractor shall perform daily clean-up of work site and, if utilized, dumpsters and storage areas. All dumpsters shall be covered and watertight should a contractor choose to utilize one.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 011000
RESILIENT TILE FLOORING 096519 - 1/4
SECTION 096519 - RESILIENT TILE FLOORING
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Cove base board.
2. Vinyl composition floor tile.
1.2 ACTION SUBMITTALS
A. Product Data: Provide product specification data sheet for each type of product indicated.
1.3 QUALITY ASSURANCE
1. Vinyl composition floor tiles shall meet minimum specifications outlined in ASTM F 1066 – Standard Specification for Vinyl Composition Floor Tile.
1.4 PROJECT CONDITIONS
A. Maintain ambient temperatures within range recommended by manufacturer in spaces to receive floor tile.
B. Until Substantial Completion, maintain ambient temperatures within range recommended by manufacturer.
C. Close spaces to foot traffic as necessary during floor tile installation.
D. Close spaces to foot traffic for 48 hours after floor tile installation to allow for adhesives to cure/dry.
PART 2 - PRODUCTS
2.1 VINYL COMPOSITION FLOOR TILE
A. Products: Subject to compliance with requirements, provide the following basis of design Vinyl Composition Floor Tile or an approved equal that matches the same salient characteristics:
1. Armstrong Flooring: Soft Warm Gray Vinyl Composition Tile
a. Item Number: 51861
b. Color: Soft Warm Gray
c. Size: 305 mm x 305 mm (12 inch x 12 inch)
d. Thickness: 3.2 mm (0.125 inch)
e. Warranty: 5-year standard manufacturer’s commercial warranty.
RESILIENT TILE FLOORING 096519 - 2/4
2.2 INSTALLATION MATERIALS
A. Adhesives: Water-resistant type recommended by manufacturer to suit floor tile and existing substrate conditions.
PART 3 - EXECUTION
3.1 PREPARATION
A. Remove existing carpet in Building 102 – Galley – Cook office space. Space is approximately 365 sqft. Remove approximately 86 linear feet of existing laminate cove base board. Contractor is responsible for field verifying measurements to ensure accurate quantity of new materials is ordered.
RESILIENT TILE FLOORING 096519 - 3/4
B. Prepare floor substrates according to manufacturer's written instructions to ensure adhesion of resilient products. Patch and sand/grind floor as necessary. Fill cracks, holes, and depressions in substrates with trowelable leveling and patching compound and remove bumps and ridges to produce a uniform and smooth substrate.
C. Verify that substrates are dry and free of curing compounds, sealers, and hardeners. Remove substrate coatings and other substances that are incompatible with adhesives. Do not install floor tiles until they are same temperature as space where they are to be installed. Move resilient products and installation materials into spaces where they will be installed at least 48 hours in advance of installation, do not store materials outside.
D. Sweep and vacuum clean substrates to be covered by resilient products immediately before installation.
3.2 FLOOR TILE INSTALLATION
A. Comply with manufacturer's written instructions for installing floor tile.
B. Lay out floor tiles from center marks established with principal walls, discounting minor offsets, so tiles at opposite edges of room are of equal width. Adjust as necessary to avoid using cut widths that equal less than one-half tile at perimeter.
C. Match floor tiles for color and pattern by selecting tiles from cartons in the same sequence as manufactured and packaged, if so numbered. Discard broken, cracked, chipped, or deformed tiles.
1. Lay tiles with grain running in one direction.
D. Scribe, cut, and fit floor tiles to butt neatly and tightly to vertical surfaces, permanent fixtures, and door frames.
RESILIENT TILE FLOORING 096519 - 4/4
E. Extend floor tiles into toe spaces, door reveals, closets, and similar openings. Extend floor tiles to center of door openings.
F. Adhere floor tiles to flooring substrates using a full spread of adhesive applied to substrate to produce a completed installation without open cracks, voids, raising and puckering at joints, telegraphing of adhesive spreader marks, and other surface imperfections.
G. Install new black vinyl cove base along perimeter of the room after installation of tile is complete.
3.3 CLEANING AND PROTECTION
A. Comply with manufacturer's written instructions for cleaning and protection of floor tile.
B. Cover floor tile until Substantial Completion.
END OF SECTION 096519
LPMcCue Typewritten Text
GALLEY OFFICE (APPROX ~ 365 SQFT)
LPMcCue Line
LPMcCue Typewritten Text
ENCLOSURE (1)