SOW Full Renv B223-224 for Schoolhouse_20250818_Rev3.pdf
PDF 4 MB Posted
- Attached to
- Amendment 0002- BID OPENING DATE EXTENDED-Full Renovation School House Classrooms at Building 223 and 224
- Solicitation number
- W912C325BA0020001
About this file
This is a Statement of Work (SOW) for a full renovation of two schoolhouse classrooms (Buildings 223 and 224) located at Fort Buchanan, Puerto Rico, issued by the Mission and Installation Contracting Command at Fort Hood. The comprehensive renovation project encompasses architectural, civil, structural, plumbing, mechanical, and electrical work to upgrade the facilities to meet TRADOC standards. Key scope elements include demolition of existing interior components, installation of new walls, floors, ceilings, doors, electrical systems, fire suppression systems, HVAC equipment, plumbing fixtures, and associated accessories.
The project requires a complete transformation of the buildings, including removing and replacing items such as gypsum board walls, ceramic tiles, suspended ceiling systems, electrical components, sprinkler systems, and mechanical equipment. The renovation will involve installing new resilient flooring, acoustic ceiling tiles, doors, hardware, paint, countertops, and comprehensive system upgrades. The contract specifications detail precise requirements for materials, installation methods, testing, and quality control, with a total project completion timeline of 240 calendar days from the Notice to Proceed. The estimated project involves significant technical complexity across multiple building systems and requires adherence to specific federal, state, and local building and safety regulations.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work (SOW) Regimen Schoolhouse Bldgs. 223 & 224
Fort Buchanan, PR
TABLE OF CONTENTS
DIVISION 01 – GENERAL REQUIREMENTS
Section 00 01 15 List of Drawings Section 01 11 00 Summary of Work Section 01 20 00.00 20 Price and Payment Procedures Section 01 30 00 Administrative Requirements Section 01 32 16.00 20 Small Project Const. Progress Schedule Section 01 33 00 Submittal Procedures Section 01 33 29 Sustainability Reporting Section 01 35 26 Governmental Safety Requirements Section 01 42 00 Source for Reference Publications Section 01 45 00.10 20 Quality Control for Minor Construction Section 01 50 00 Temporary Construction Facilities and Controls Section 01 57 19 Temporary Environmental Controls Section 01 58 00 Project Identification Section 01 74 19 Construction Waste Management and Disposal Section 01 78 00 Closeout Submittals Section 01 78 23 Operation and Maintenance Data
DIVISION 02 – EXISTING CONDITIONS
Section 02 41 00 Demolition
DIVISION 03 – CONCRETE
Section 03 30 53 Miscellaneous Cast-in-Place Concrete
DIVISION 05 – METALS
Section 05 50 13 Miscellaneous Metal Fabrications
DIVISION 06 – WOOD, PLASTIC AND COMPOSITES
Section 06 41 16.00 10 Plastic Laminate Clad Architectural Cabinets Section 06 61 16 Solid Surfacing Fabrications
DIVISION 07 – THERMAL & MOISTURE PROTECTION
Section 07 92 00 Joint Sealants
DIVISION 08 – OPENINGS
Section 08 11 13 Steel Doors and Frames Section 08 71 00 Door Hardware
DIVISION 09 – FINISHES
Section 09 22 00 Support for Plaster and Gypsum Board
Section 09 23 00 Gypsum Plastering
Section 09 29 00 Gypsum Board Section 09 51 00 Acoustical Ceiling
Section 09 65 00 Resilient Flooring Section 09 90 00 Paints and Coating
DIVISION 12 – FURNISHINGS
Section 12 36 00 Countertops
DIVISION 21 – FIRE SUPPRESSION
Section 21 13 00.00 40 Fire Suppression Sprinkler System Section 21 13 13.00 20 Wet Pipe Sprinkler System, Fire Protection
DIVISION 22 – PLUMBING
Section 22 00 00 Plumbing, General Purpose Section 22 13 19 Sanitary Sewerage Pumps
DIVISION 23 – HEATING, VENTILATION AND AIR CONDITIONING
Section 23 03 00.00 20 Basic Mechanical Materials and Methods Section 23 05 15 Common Piping for HVAC Section 23 05 48.19 Seismic Bracing for HVAC Section 23 05 93 Testing, Adjusting and Balancing for HVAC Section 23 07 00 Thermal Insulation for Mechanical Systems Section 23 08 01.00 20 Testing Industrial Ventilation System Section 23 09 00 Instrumentation and Control for HVAC Section 23 09 23.02 BACNet Direct Digital Control for HVAC and Other Building Control
Systems Section 23 09 53.00 20 Space temperature Control Systems Section 23 23 00 Refrigerant Piping Section 23 30 00 HVAC Air Distribution Section 23 81 23 Computer Room Air Conditioning Units
DIVISION 26 – ELECTRICAL
Section 26 20 00 Interior Distribution System Section 26 51 00 Interior Lighting
DIVISION 28 – ELECTRONIC, SAFETY AND SECURITY
Section 28 31 00.00 10 Fire Detection and Alarm System, Direct Current Loop
DIVISION 31 – EARTHWORK
Section 31 00 00 Earthwork Section 31 23 00.00 20 Excavation and Fill
ATTACHMENTS
No.1 ..................................... Asbestos Inspection Report Bldg. 223 and 224 provided by DPW Environmental Division
No.2 .................................... Lead-Based Paint Inspection Report Bldg. 224 provided by DPW.
No.3 ..................................... Installation Hazardous Waste Management Plan – Mar 2009
No.4 ..................................... Fort Buchanan Pollution Prevention and Sustainability Plan – 2015
* * * END TABLE OF CONTENTS * * *
SECTION 00 01 15
LIST OF DRAWINGS
PART 1 GENERAL
1.1 SUMMARY
This document lists the drawings for the project pursuant to contract clause "DFARS 252.236-7001, Contract Drawings, Maps & Specifications."
1.2 CONTRACT DRAWINGS
Contract drawings are as follows:
SHEET NO. DRAWING
NO.
TITLE
1 G-000 TITLE SHEET
2 G-101 PROPOSED LAYOUT BLDG. 223
3 G-102 DIMENSIONS BLDG. 223
4 G-201 PROPOSED LAYOUT BUILDING 223
5 G-202 PROPOSED LAYOUT BLDG. 224
6 CD-101 CIVIL DEMOLITION WORKS BLDG. 223
7 CD-102 PLUMBING DEMOLITION WORKS BLDG. 223
8 CD-201 CIVIL DEMOLITION WORKS BLDG. 224
9 C-101 CIVIL NEW WORKS BLDG. 223
10 C-102 REFLECTED CEILING NEW WORKS BLDG. 223
11 C-201 CIVIL NEW WORKS BLDG.224
12 C-202 REFLECTED CEILING NEW WORKS BLDG. 224
13 A-101 NEW DOORS AND SCHEDULES BLDG. 223
14 A-102 NEW WORKS BLDG. 224
15 A-201 NEW DOORS AND SCHEDULES BLDG. 224
16 A-202 NEW WORKS BLDG. 224
17 F-101 NEW FIRE ALARM WORKS BLDG. 223
18 F-102 NEW SPRINKLER SYSTEM BLDG. 223
19 F-201 NEW FIRE ALARM WORKS BLDG. 224
20 F-202 NEW SPRINKLER SYSTEM BLDG. 224
21 PD-101 PLUMBING DEMOLITION WORKS BLDG. 223
22 PD-201 PLUMBING DEMOLITION WORKS BLDG. 224
23 P-101 PLUMBING NEW WORKS BLDG. 223
24 P-201 PLUMBING NEW WORKS BLDG. 224
25 M-101 MECHANICAL DEMOLITION PLAN BLDG. 223
26 M-102 MECHANICAL CEILING DIFFUSERS AND
RETURN AIR GRILL PLAN BLDG. 223
27 M-103 MECHANICAL NEW WORKS PLAN BLDG. 223
28 M-104 MECHANICAL DEMOLITION PLAN BLDG. 224
29 M-105 MECHANICAL CEILING DIFFUSERS AND
RETURN AIR GRILL PLAN BLDG. 224
30 M-106 MECHANICAL NEW WORKS PLAN BLDG. 224
31 M-107 MECHANICAL SCHEDULE TABLES BLDG. 224
32 M-108 MECHANICAL CRAC UNITS BLDG 223-224.
33 M-109 MECHANICAL LIFT STATION WORKS BLDG.
224.
34 E-101 ELECTRICAL AND DATA DEMOLITION BLDG.
35 E-102 ELECTRICAL AND DATA NEW WORKS BLDG.
36 E-103 LIGHTING DEMOLITION BLDG. 223
37 E-104 LIGHTING NEW WORKS BLDG. 223
38 E-201 ELECTRICAL AND DATA DEMOLILITION BLDG.
39 E-202 LIGHTING DEMOLITION BLDG. 224
40 E-203 ELECTRICAL AND DATA NEW WORKS BLDG.
41 E-204 LIGHTING NEW WORKS BLDG. 224
42 E-301 PANEL SCHEDULES BLDGS. 223 AND 224
43 E-302 ELECTRICAL DETAILS AND ADDITIONAL
INFORMATION BLDGS 223 AND 224
44 E-303 16 STUDENTS TABLES BLDGS 223 AND 224
45 E-304 10 STUDENTS TABLES BLDG 224 ONLY
46 TD-101 TELECOMMUNICATIONS DEMOLITION BLDG.
47 T-101 NEW TELECOMMUNICATIONS WORK BLDG 223
48 TD-201 TELECOMMUNICATIONS DEMOLITION BLDG.
49 T-102 NEW TELECOMMUNICATIONS WORK BLDG 224
1.3 REFERENCE DRAWINGS
The reference drawings are intended only to show the existing site condition. Drawings are the property of the Government and shall not be used for any purpose other than that intended by the contract.
* * * END OF SECTION * * *
SECTION 01 11 00
STATEMENT OF WORK
PART 1 DESCRIPTION OF WORK
1.1 Work to be done: Provide labor, equipment, materials, insurances, supervision, incidentals and all necessary to perform “Full Renovation of Buildings 223 and 224 for Schoolhouse Classrooms to meet TRADOC Standards”, Fort Buchanan, Guaynabo, PR”.
1.1.1 Prospective Contractor: The prospective contractors are encouraged to visit project sites and familiarize themselves with all conditions that might affect the work or cost thereof. On this visit, the contractor will verify quantities, dimensions, details and notify in writing any omitted data or discrepancy with the drawings or scope of work. If it is necessary, the contractor shall coordinate all the necessary site visits for data compilation. The government will not be responsible for any difference between the existing conditions and the illustrated in drawing if it’s not notified prior to the proposal delivery.
1.1.2 Location: The work is located in Davis Street, Buildings 223 & 224 at Fort Buchanan, P.R. as shown in drawings.
1.2 The required work in all Architectural, Civil, Structural, Plumbing, Mechanical, and Electrical trades shall be performed in accordance with all applicable Technical Organizations and Regulatory Agencies listed in Paragraph 1.4.
Work shall also comply with US Army Corps of Engineers, Department of the Army, Environmental Protection Agency and PR Environmental Quality Board Standards and Regulations. The required work is described in general as follows:
1.2.1 Administrative: Safety and Environmental Works shall be performed in accordance with this SECTION 01 11 00, STATEMENT OF WORK and DIVISION 01, GENERAL REQUIREMENTS indicated in the TABLE OF CONTENTS: SECTION 00 01 15, LIST OF DRAWINGS; SECTION 01 20 00 00 20 PRICE AND PAYMENT PROCEDURES; SECTION 01 30 00 ADMINISTRATIVE REQUIREMENTS; SECTION 01 32 16 00 20, SMALL
PROJECT CONSTRUCTION PROGRESS SCHEDULES; SECTION 01 33 00, SUBMITTAL PROCEDURES;
SECTION 01-33-29, SUSTAINABILITY REPORTING; SECTION 01 35 26, GOVERNMENTAL SAFETY REQUIREMENTS; SECTION 01 42 00, SOURCES FOR REFERENCE PUBLICATIONS; SECTION 01 45 00 10 20, QUALITY CONTROL FOR MINOR CONSTRUCTION; SECTION 01 50 00, TEMPORARY CONSTRUCTION
FACILITIES AND CONTROLS; SECTION 07 57 19, TEMPORARY ENVIRONMENTAL CONTROLS; SECTION 01 58 00, PROJECT IDENTIFICATION; SECTION 01 74 19, CONSTRUCTION WASTE MANAGEMENT AND
DISPOSAL; SECTION 01 78 00, CLOSEOUT SUBMITTALS; SECTION 01 78 23, OPERATION AND
MAINTENANCE DATA.
1.2.2 Demolition Works: Contractor shall perform selective demolition, disposal and recycling works indicated in related specifications sections and drawings CD-101, CD-102, TD-101, CD-201, PD-201 and TD-201 in accordance with attached Specifications in DIVISION 02, EXISTING CONDITIONS and indicated in the TABLE OF CONTENTS:
SECTION 02 41 00, DEMOLITION. All demolition conducted on site shall satisfy the applicable environmental regulations including hazardous materials, disposal regulations, dust and debris control, safety (ANSI A106), and protection of unaffected areas. Disposable materials shall become the property of the Contractor unless noted or determined to be reused or turned over to the Government and shall be the Contractor’s responsibility the proper disposition. The contractor should provide daily housekeeping to ensure debris and leftovers resulting from work and activities associated with this project are cleaned properly. The Contractors shall clean up any adjacent areas, and streets impacted due to this project in accordance with local ordinances.
A. Civil demolition works for Buildings 223 & 224
The Contractor shall perform the following:
1.2.2.1 Remove and dispose selected single or double doors including frames, thresholds and accessories as indicated on drawings. WARNING: “THIS WORK REQUIRES LEAD BASE PAINT ABATEMENT. Some wall sections tested positive to Lead Base Paint (LBP)”. See inspection reports by Zimmetry Environmental Management Corp. attached.
1.2.2.2 Remove and dispose selected gypsum board walls, as indicated on drawings. WARNING: “THIS WORK REQUIRES LEAD BASE PAINT ABATEMENT. Some wall sections tested positive to Lead Base Paint (LBP)”.
See inspection reports by Zimmetry Environmental Management Corp. attached.
1.2.2.3 Remove and dispose of sanitary equipment (ie. FRP panels, toilet, sinks, shower stall, shower heads, faucets, hoses, water heaters, handicap folding seats, handrails, floor drains, cleanouts, etc.) as indicated on drawings.
The contractor shall protect selected water and sanitary connections for re-used.
1.2.2.4 Remove and dispose ceramic floor tiles as indicated on drawings. [Action taken: Warning message related to possible asbestos abatement was eliminated since did not apply anymore.]
1.2.2.5 Remove and dispose interior cove base sections as indicated on drawings.
1.2.2.6 Remove and dispose suspended ceiling system as indicated on drawings.
1.2.2.7 Remove and dispose of selected glass window panels and frames as indicated on drawings. WARNING: “THIS WORK REQUIRES LEAD BASE PAINT ABATEMENT. Some wall sections tested positive to Lead Base Paint (LBP)”. See inspection reports by Zimmetry Environmental Management Corp. attached.
1.2.2.8 Remove and dispose concrete wall section as indicated on drawings. WARNING: “THIS WORK REQUIRES LEAD BASE PAINT ABATEMENT. Some wall sections tested positive to Lead Base Paint (LBP)”. See inspection reports by Zimmetry Environmental Management Corp. attached.
1.2.2.9 Saw cut selected concrete floor section for plumbing, power and communications purpose, as indicated on drawings. [Action taken: Warning message related to possible asbestos abatement was eliminated since did not apply anymore.].
1.2.2.10 Demolish selected entrance concrete stairs, as indicated on drawings. WARNING: “THIS WORK REQUIRES LEAD BASE PAINT ABATEMENT. Some wall sections tested positive to Lead Base Paint (LBP)”.
See inspection reports by Zimmetry Environmental Management Corp. attached.
1.2.2.11 Remove and dispose of fire alarm and security system (control panels, sensors, smoke detectors, strobe lights, horns, etc.) as indicated on drawings.
1.2.2.12 Pressure wash selected exterior walls and concrete slabs, as indicated on drawings. Due to LBP report, pressure wash shall not exceed 1500psi.
B. Civil demolition works for Building 223 only
1.2.2.12 Remove and dispose of metal gate railings as indicated on drawings.
C. Civil demolition works for Building 224 only
1.2.2.13 Remove and dispose kitchen countertop and cabinet as indicated on drawings.
1.2.2.14 Pressure wash handicap ramp and exterior wall as indicated on drawings. Due to LBP report, pressure wash shall not exceed 1500psi.
1.2.2.15 Pressure wash handicap ramp and exterior wall as indicated on drawings. Due to LBP report, pressure wash shall not exceed 1500psi.
1.2.3 Architectural/Structural New Works: Contractor shall perform all works indicated in drawings in accordance with:
a. Attached specifications in DIVISION 05, METALS and indicated in the TABLE OF CONTENTS:
SECTION 05 50 13, MISCELLANEOUS METAL FABRICATIONS.
b. Attached specifications in DIVISION 06, WOOD, PLASTICS AND COMPOSITES and indicated in the
TABLE OF CONTENTS: SECTION 06 41 16.00 10, PLASTIC LAMINATE CLAD
ARCHITECTURAL CABINETS; SECTION 06 61 16, SOLID SURFACING FABRICATIONS.
c. Attached specifications in DIVISION 07, THERMAL & MOISTURE PROTECTION and indicated in the TABLE OF CONTENTS: SECTION 07 92 00, JOINT SEALANTS.
d. Attached specifications in DIVISION 08, OPENINGS indicated in the TABLE OF CONTENTS:
SECTION 08 11 13, STEEL DOORS AND FRAMES; SECTION 08 31 00, ACCESS DOORS AND
PANELS; SECTION 08 34 02, BULLEET RESISTANCE COMPONENTS; SECTION 08 34 63,
DETENTION HOLLOW METAL FRAMES, DOORS AND DOOR FRAMES; SECTION08 71 00,
DOOR HARDWARE; SECTION 08 71 63, DETENTION HARDWARE.
e. Attached specifications in DIVISION 09, FINISHES indicated in the TABLE OF CONTENTS:
SECTION 09 23 00, GYPSUM PLASTERING; SECTION 09 65 00, RESILIENT FLOORING;
SECTION 09 90 00, PAINTS AND COATINGS.
f. Attached specifications in DIVISION 12, FURNISHING indicated in the TABLE OF CONTENTS:
SECTION 12 36 00, COUNTERTOPS.
g. Attached specifications in DIVISION 31, EARTHWORK indicated in the TABLE OF CONTENTS:
SECTION 31 00 00, EARTHWORK; SECTION 31 23 00.00 40, EXCAVATION AND FILL.
A. Civil new works for Buildings 223 & 224
1.2.3.1 Correct all floor imperfections due to gypsum board wall and bathrooms ceramic tiles removal, to create a uniform floor surface. Use self lev1922111eling concrete equal or similar to ARDEX V-1000, as indicated on drawings.
1.2.3.2 Furnish and install new cementitious backerboard on restrooms walls and janitorial room for ceramic wall tiles installation, as indicated on drawings.
1.2.3.3 Furnish and install new ceramic wall tiles and sanitary cove based on restrooms equal or similar to DALTILE 3" x 12" ARTCRAFTED COCONUT CERAMIC, as indicated on drawings. Color and pattern to be determined by
Government.
1.2.3.4 Furnish and install new 12” x 12” non-slip ceramic floor tiles and cove base on restrooms area, as indicated on drawings. Color and pattern to be determined by Government.
1.2.3.5 Furnish and install new 3’ x 3’ terrazzo floor mop sink on janitorial room, as indicated on drawings. Color and pattern to be determined by Government.
1.2.3.6 Furnish and install new 12” x 12” x 1/8” resilient vinyl tile flooring, as indicated on drawings. Machine scrub and polish (as recommended by manufacturer) after finish. Color and pattern to be determined by Government.
1.2.3.7 Furnish and install new 4” vinyl cove base as indicated on drawings. Color to be determined by Government.
1.2.3.8 Build new 8 feet high gypsum board walls (1 and/or 2 sided) using 4” x 1-3/4” 18ga. studs @ 16”O.C., 5/8” gypsum panels and R-13 acoustic insulation for interior walls, as indicated on drawings.
1.2.3.9 Furnish and install new wood doors and steel frames, as indicated on drawings.
1.2.3.10 Restore (sanding and painting) exterior metal doors, as indicated on drawings.
1.2.3.11 Provide new handicap entrance/exit ramp and railing, as indicated on drawings.
1.2.3.12 Provide new metal gate and railing for the mechanical room, as indicated on drawings.
1.2.3.13 Furnish and install new 2’ x 2’ acoustic hung ceiling system at a final elevation of 8ft. from the finished floor level, on white corrosion resistance suspension grid 2” x 15/16” and supported on walls with molding, as indicated on drawings. The system shall be supported by hanger wire gauge #12, tied to the structural roof and shall include earthquake clips and accessories.
1.2.3.14 Furnish and install blanket insulation above the restrooms ceiling tiles system, 3-1/2” R -13, as indicated on drawings.
1.2.3.15 Seal with concrete block, mortar and plaster a wall opening as indicated on drawings.
1.2.3.16 Furnish, install, primer and paint new metal gate and railings, as indicated on drawings. Also, paint remaining railings.
1.2.3.17 Install new wall mounted toilets tissue dispensers, double roll, provided by the Government, as indicated on drawings
1.2.3.18 Install new wall mounted liquid soap dispenser, provided by the Government, as indicated on drawings.
1.2.3.19 Install new wall mounted paper towel dispensers, provided by the Government, as indicated in drawings.
1.2.3.20 Furnish and install a new surface mounted toilet seat cover dispenser, equal or similar to Fairbanks seat cover dispenser, as indicated on drawings.
1.2.3.21 Furnish and install new grab bars (ADA compliant) as indicated on drawings.
1.2.3.22 Furnish and install new fix tilted wall mirror 24” x 36” (ADA compliant) as indicated on drawings.
1.2.3.23 Paint interior walls, 1 coat of primer and 2 finish coats, as indicated on drawings. Color palette will be coordinated with Government.
1.2.3.24 Paint handicap access ramp with anti-slip floor paint as indicated on drawings. The color palette will be coordinated with the Government.
1.2.3.25 Final scrubbing, waxing and polishing all floors.
1.2.3.26 Install new Break Room kitchen cabinet as indicated on drawings.
1.2.3.27 Install new acrylic polymer countertop equal or similar to Corian-Cobalt (Premium patterned Granola colored with backsplash) and a 16” x 20” single bowl undermounted stainless steel kitchen sink, as indicated on
B. Civil new works for Building 224 only
1.2.3.28 Repair and plaster exterior wall crack to match the existing wall condition, as indicated on drawings.
1.2.4 Plumbing Work: Contractor shall perform all works indicated in drawings in accordance with:
Attached specifications in DIVISION 21, FIRE SUPPRESSION AND DIVISION 22, PLUMBING indicated in the TABLE OF CONTENTS: SECTION 21 13 00.00 40, FIRE SUPPRESSION SPRINKLER SYSTEM; SECTION 21 13
13.00 20, WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION; SECTION 22 00 00, PLUMBING, GENERAL
PURPOSE; SECTION 22 13 19, SANITARY SEWERAGE PUMPS.
A. Plumbing new works for Buildings 223 & 224
Work shall include:
1.2.4.1 Furnish and install new floor mounted water closet (regular and ADA compliant) with flush valves, floor outlet
& accessories, as indicated on drawings.
1.2.4.2 Furnish and install new wall mounted urinals, including with flush valves, and accessories, as indicated on drawings.
1.2.4.3 Furnish and install new vitreous China lavatories (18” x 20” and 18” x 27” ADA complaint) and accessories including rough-in, faucet, pop-up drain, p-trap, ball valve and flexible metal hose connections as indicated on
1.2.4.4 Furnish and install new stainless steel drinking water fountain with bottle filler, refrigerated and filtered, as indicated on drawings.
1.2.4.5 Furnish and install a new Sprinkler System including riser, flush valve, alarm sensors, sprinkler heads, pipes, support, hangers, fittings and accessories, as indicated on drawings. Sprinkler heads should be polished chrome, 0.75-inch diameter as indicated in drawings. Contractors shall provide plastic snap around labels for flow direction in the primary and secondary pipes within the limits of the project and shall identify the sprinkler heads properly in accordance with codes and standards. Contractor shall apply two coats of primer and one coat of paint in red for new black steel piping of the fire suppression system including drop connections. The system shall be tested and approved by a certified authority.
1.2.5 Mechanical Work: Contractor shall perform all works indicated in drawings in accordance with:
Attached specifications in DIVISION 23 HEATING, VENTILATING AND AIR CONDITIONING and indicated in the TABLE OF CONTENTS: SECTION 23 03 00.00 20, BASIC MECHANICAL MATERIALS AND METHODS;
SECTION 23 05 15, COMMON PIPING FOR HVAC; SECTION 23 05 48.19, SEISMIC BRACING FOR HVAC;
SECTION 23 05 93, TESTING, ADJUSTING AND BALANCING for HVAC; SECTION 23 07 00, THERMAL INSULATION for MECHANICAL SYSTEMS; SECTION 23 08 01.00 20, TESTING INDUSTRIAL VENTILATION
SYSTEMS; SECTION 23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC; SECTION 23 09 23.02, BACNET DIRECT DIGITAL CONTROL FOR HVAC AND OTHER BUILDINGS CONTROL SYSTEMS; SECTION 23 09 53.00 20, SPACE TEMPERATURE CONTROL SYSTEM; SECTION 23 23 00, REFRIGERANT PIPING;
SECTION 23 30 00, HVAC AIR DISTRIBUTION; SECTION 23 81 23, COMPUTER ROOM AIR CONDITIONIG UNITS. All existing air conditioning systems shall be removed and disposed of out of Fort Buchanan properly. All new air conditioning equipment shall be labeled ENERGY STAR and comply with a minimum EER = 12 and SEER = 17.
All demolition works conducted on site shall satisfy the applicable environmental regulations, including hazardous materials, disposal regulations, dust and debris control, safety (ANSI A106), and protection of unaffected work.
Demolished materials shall become the property of the Contractor unless noted or determined to be reused or turned over by the Using Agency and shall be the Contractor’s responsibility to dispose of. The Contractor shall promptly clean up any spillage from adjacent areas in accordance with local ordinances.
Contractor shall comply with the Buy American Act for all equipment presented in submittals.
All works shall be in accordance with the most current edition in effect at the time of the notice to proceed with the project for all applicable codes and standards including but not limited to:
I. The International Building Code
II. National Electrical Code
III. National Fire Protection Agency requirements
IV. Installation Design Guide.
V. HVAC Code
Implied specifications: When specifications are not furnished, the standards of work shall be IAW Unified Facility Criteria (UFC), and Industry Standards and Unified Facilities Guide Specifications (UFGS).
Preparation: Contractor shall be responsible for field/site visit to obtain and verify measurements, site conditions and to determine correct dimensions and structural support requirements IAW accepted local, state and federal building practices. All drawings provided to the contractor are for reference/information only. The contractor shall provide any/all deviations to accept local, state and federal building practices/codes to the attention of the Construction Inspector and Contracting Officer Representative for review/consideration by the Government. All demolition conducted on site shall satisfy the applicable environmental regulations including but not limited to hazardous materials, disposal regulations, dust and debris control, safety (ANSI A106), and protection of unaffected work.
Demolished materials shall become the property of the Contractor unless noted or determined to be reused or turned over by the Using Agency and shall be the Contractor’s responsibility to dispose of. The Contractor shall promptly clean up any spillage from adjacent areas in accordance with local ordinances.
A. Mechanical demolition works for Buildings 223 & 224
1.2.5.1 Remove and return to the government all existing A/C machines including the condensing unit and its corresponding air handling unit as well as all the supply and return sheet metal ductwork. WARNING:
“Floor vinyl tiles adhesive tested positive to asbestos”. In regard of Asbestos related works such as drilling, the recommended Working Practices (WP) is shown in the attached O&M Asbestos Plan, Section WP-4 (Cut or Drill Asbestos). Please refer to Page 61 of the attached Plan. This work does not require an Abatement Permit but strongly recommend be performed by a EQB Asbestos certified Worker.
1.2.5.2
1.2.5.3 Remove and dispose of dampers, filters, smoke detectors, drainage pipes, electrical and plumbing connections with their accessories.
1.2.5.4 Recycle all refrigerants according to Section 608 of the EPA Clean Air Act. Provide evidence of the recycled refrigerant.
1.2.5.5 Remove and dispose existing duct connection accessories to the AHU including flexible connections, and fresh air ducts from the mechanical room.
1.2.5.6 Remove and dispose of existing supply diffusers and return grills.
1.2.5.7 Remove and dispose of existing thermostats with their related accessories.
B. Mechanical demolition works for Buildings 223 only.
1.2.5.8 Remove and dispose existing 2’x 2’ aluminum fix louver as indicated on drawing sheet M-101 note 10.
1.2.5.9 Remove and dispose existing exhaust fan, including sheet metal duct and return grill as indicate on drawing sheet M-101 note 4.
1.2.5.10 Remove and return to the government one (1) Computer Room Air Conditioning (CRAC) system, including Condenser units. Remove and dispose existing (CRAC) drainage pipes, thermostats, electrical and plumbing connections, and their accessories.
C. Mechanical demolition works for Buildings 224 only.
1.2.5.11 Remove and return to the government two (2) existing Computer Room Air Conditioning (CRAC) system, including Condenser units. Remove and dispose existing (CRAC) drainage pipes, thermostats, electrical and plumbing connections, and their accessories.
1.2.5.12 Remove and dispose existing back-to-back transition duct and return grills as indicate on Note #3 of drawing
Sheet M-104.
1.2.5.13 Remove and dispose of existing exhaust fan, including sheet metal duct and return grill as indicate on drawing sheet M-104 note 6.
1.2.5.14 Remove and dispose of existing lift station 48” x 61” and 35” x 35” access hatches, 2hp submersible pump, one (1) 4-inch gate valve, one (1) 4-inch check valve, float switches and iron piping as indicated on drawing sheet M-109.
D. Mechanical new works for Buildings 223 & 224.
1.2.5.15 The Contractor shall pressure wash the interior of the mechanical rooms.
1.2.5.16 The Contractor shall paint the mechanical room with two (2) coats using equal o similar to Sherwin-Williams 2869, BM 869 OXFORD WHITE color walls (interior) and 6474 RAGING SEA color the hollow metal double door and frame.
1.2.5.17 The Contractor shall provide new DDC Control (32 Points) including programming and must be compatible with BACnet systems for the new A/C system.
1.2.5.18 The Contractor shall provide and install a 25 Ton 10000 CFM unit for Bldg. 223 and 30 Ton 12000 CFM unit for Bldg. 224 A/C system that can control and monitor the temperature and relative humidity in each space.
Each air conditioning machine shall have a dedicated power disconnect switch. The system must have a built mounted Variable Frequency Drive (VFD) and be capable of shutting down upon signal from duct mounted smoke detectors. The condensing unit shall be installed in the existing concrete pad, and installation must follow the manufacturer’s rigging instructions. The unit shall be compatible with BACnet systems. The new A/C systems should be equal or similar to those indicated in the Schedule table. Refer to drawing sheet M-107 for New Air Conditioner Schedule. In regard of Asbestos related works such as drilling, the recommended Working Practices (WP) is shown in the attached Asbestos Operations and Maintenance Plan, Section WP-4 (Cut or Drill Asbestos). Please refer to Page 61 of the attached Plan. This work does not require an Abatement Permit but strongly recommend be performed by a EQB Asbestos certified Worker.
1.2.5.19 Not used.
1.2.5.20 Furnish and install a new PVC SCH 40 condensate drainage pipe to connect the new A/C systems to the existing underground drainage piping.
1.2.5.21 Furnish and install new refrigerant pipes on all the A/C systems were applicable. The Contractor shall install carbon steel hanger rods with continuous thread in compliance with typical industry codes and standards. Install new closed cell insulation two (2) inch thick for interior and exterior refrigerant pipes. All exterior refrigerant pipes shall have aluminum jackets.
1.2.5.22 The Contractor shall provide and install new galvanized sheet metal ductwork, manufactured, and installed in accordance with latest edition of the duct construction standards of SMACNA for the applicable pressure class.
Insulation shall be two (2) inches thick, and density wrap # 1.5 for supply and return ducts. The Contractor shall apply fire stopping around the new ductwork on each wall penetrations. The Contractor shall provide shop drawings of ductwork installation before starting with the construction to the government. Refer to drawing sheet M-103 & M-106.
1.2.5.23 The Contractor shall provide and install variable air volume (VAV) boxes per each A/C machine including digital thermostat sensors (capable of controlling temperature and VAV boxes) and cat cabling with its accessories. Digital thermostats sensors shall be installed as indicated on drawing sheets M-103 & M-106. The VAV boxes shall comply with energy standards and codes. Refer to drawing sheet M-107 for VAV boxes Schedule.
1.2.5.24 Furnish and install new steel cone four (4) way supply diffuser and return grills with plastic egg crate face. All return grills shall be installed in a 24”x 24” acoustical ceiling. Refer to drawing sheet M-107 for Return Grill Schedule.
1.2.5.25 The Contractor shall test and balance the new system. The leak test shall be within acceptable parameters by codes and standards. Also, the Contractor shall provide an official TAB report by a certified technician demonstrating that the system is incompliance with local and federal standards, codes, and regulations. The report shall indicate the amount of volume (CFM’s) tested and balanced by each space.
1.2.5.26 Conduct a training course for DPW operating staff members designated by the Government in the maintenance and operation of the system, including specified hardware and software.
E. Mechanical new works for Building 223 only.
1.2.5.24 The Contractor shall provide, a new 18” x 9-1/2” exterior aluminum fixed louver, mill finished, and factory assemble for the fresh air ducting. The louver shall have green colored powder polyester coating and be equipped with an aluminum insect stainless steel screen in a removable frame. Paint the rear (inside) of the louver a green color equal or similar to Sherwin William direct-to metal alkyd enamel, Raging Sea, SW6474.
Refer to Sheet M-103 note #3.
1.2.5.25 The Contractor shall provide and install a new ceiling mounted exhaust fan capable of turning on and off with the movement sensor lights switches. New exhaust fan shall be connected to e new 4” PVC SCH 40 pipe through the ceiling to discharge at the new aluminum louver at exterior overhang, refer to drawing sheet M- 103 note #9.
1.2.5.26 Provide and install one (1) new Computer Room Air Conditioning (CRAC)units, equal or similar to Liebert Model PFH020ACPL7, as indicated on drawing M-108. The new A/C computer room units must have an integrated monitoring system in which humidity and temperature can be observed among other components included by the manufacturer. The control system interface must meet DDC hardware requirements of BACNET DIRECT DIGITAL CONTROL for HVAC and other building control systems. Refer to drawing sheet M-107 for new CRAC system sensor schedule.
F. Mechanical new works for Building 224 only.
1.2.5.27 Provide and install two (2) new Computer Room Air Conditioning (CRAC)units, equal or similar to Liebert Model PFH020ACPL7, as indicated on drawing M-108. The new A/C computer room units must have an integrated monitoring system in which humidity and temperature can be observed among other components included by the manufacturer. The control system interface must meet DDC hardware requirements of BACNET DIRECT DIGITAL CONTROL for HVAC and other building control systems. Refer to drawing sheet M-107 for new CRAC system sensors schedule.
1.2.5.28 The Contractor shall provide, a new 24”x 24” exterior aluminum continuous line fixed louver, drainable inverted (Y) type, mill finished, and factory assemble for the fresh air ducting. Frame shall be a 4” deep channel frame design. The louver shall have green colored powder polyester coating and be equipped with an aluminum insect stainless steel screen in a removable frame. Paint the rear (inside) of the louver a green color equal or similar to Sherwin William direct-to metal alkyd enamel, Raging Sea, SW6474. Refer to Sheet M- 106 note #3.
1.2.5.29 The Contractor shall provide and install a new ceiling mounted exhaust fan capable of turning on and off with the movement sensor lights switches. New exhaust fan shall be connected to e new 4” PVC SCH 40 pipe through the ceiling to discharge at the new aluminum louver at exterior overhang, refer to drawing sheet M- 106 notes # 9 & 10.
1.2.5.30 Contractor shall provide and install a new ¼ inches thick 48” x 61” and 35” x 35” aluminum access hatches, a
2hp submersible pump with 4-inch discharge side, one (1) 4-inch gate valve, one (1) 4-inch check valve, float switches, 2-inch galvanized goose neck and 4-inch iron piping and elbows as indicated on drawing sheet M- 109.
1.2.5.31 The Contractor shall clean and brush the new iron piping of the lift station and apply one (1) coat of anti-corrosion coating and two (2) coats of waterproof thermally insulating paint.
1.2.5.32 The Contractor shall repair interior lift station wall imperfections with cement plaster patch and finishing compound similar or equal to ARDEX TWP and CP patching and finishing product as indicated on drawing sheet M-109.
1.2.5.33 The Contractor shall seal the lift station walls and floor by applying two (2) coats of sanitary special coating using material equal or similar to Grey Coat Epoxy 100% solid epoxy as indicated on drawing sheet M-109.
1.2.6 Electrical Work: Contractor shall perform all works indicated in electrical drawings and this scope of work, in accordance with UFC 3-530-01 interior and exterior lighting system, UFC 3-520-01 interior electrical system, AR-420 - 1 ARMY facilities management, ASHRAE 90.1 Energy Standard for Buildings Except Low-Rise Residential Buildings and National Electrical Code (NEC) 70 and technical specification. The Contractor shall perform all works indicated in drawings in accordance with attached specifications in DIVISION 26, ELECTRICAL AND DIVISION 28.
ELECTRONIC, SAFETY AND SECURITY indicated in the TABLE OF CONTENTS: SECTION 26 20 00, INTERIOR DISTRIBUTION SYSTEM; SECTION 26 51 00, INTERIOR LIGHTING; SECTION 28 31 00.00 10, FIRE
DETECTION AND ALARM SYSTEM, DIRECT CURRENT LOOP.
1.2.6.1 Electrical and data:
A. Electrical and data demolition works for buildings 223 & 224
1.2.6.1.1 Remove and dispose all electrical duplex receptacles (including special use receptacles such as GFCI and IGR receptacles), as indicated on drawings.
1.2.6.1.2 Perform data conduit cuts as indicated on drawings. Coordinate with COR prior doing this action to confirm what shall be cut to avoid cutting NEC critical infrastructure.
1.2.6.1.3 Remove and dispose ethernet and communications infrastructure, as indicated on drawings.
1.2.6.1.4 Remove and dispose of electrical cables for loads, as indicated on drawings.
1.2.6.1.5 Remove and dispose cable trays, as indicated on drawings.
1.2.6.1.6 Remove and dispose data ports, as indicated on drawings.
1.2.6.1.7 Remove and dispose disconnect switches, as indicated on drawings.
1.2.6.1.8 Selected items to remain are indicated on drawings.
B. Electrical and data demolition works for building 223 only
1.2.6.1.9 Remove and dispose indicated electrical panels including their breakers, as indicated on drawings.
1.2.6.1.10 Perform conduit cut as indicated on drawings and coil cables above acoustic ceiling for future use, as indicated on drawings.
1.2.6.1.11 Remove and dispose electrical connection from panel C223 to P223.
1.2.6.1.12 Temporarily disconnect Advanced Meter current transformer, as indicated on drawings.
1.2.6.1.13 Remove and dispose main breaker enclosure with main breaker, as indicated on drawings. Power cables to remain.
1.2.6.1.14 Remove and dispose 45 KVA dry type transformer and associated as indicated on drawings.
C. Electrical and data demolition works for building 224 only
1.2.6.1.13 Perform cuts at conduits leading to mechanical room, as indicated on drawings.
1.2.6.1.14 Remove and dispose UPS, batteries, battery compartment and power connections, as indicated on
1.2.6.1.15 Some breakers shall remain on panels and to be reorganized and re-used, as indicated on drawings.
1.2.6.1.16 Remove and dispose indicated breakers on drawings.
1.2.6.1.17 Remove and dispose Lift Station electrical wires and breakers, conduits to remain.
D. Electrical and data new works for Buildings 223 & 224
1.2.6.1.18 Furnish and install new receptacles, for receptacle type or specifics refer to drawings.
1.2.6.1.19 Furnish and install conduit drops, for more specifics, refer to drawings.
1.2.6.1.20 Furnish and install basket type cable trays with bonding jumpers, as indicated on drawings.
1.2.6.1.21 Furnish and install NEMA 4X disconnect switches as indicated on drawings.
1.2.6.1.22 Furnish and install new shallow concrete boxes and receptacles as indicated on drawings.
1.2.6.1.23 Furnish and install new junction boxes as indicated on drawings, sizes, material and purpose varies.
1.2.6.1.24 Provide labels and identification as indicated in drawings.
1.2.6.1.25 Furnish and install new power cables for each new circuit as indicated on drawings.
1.2.6.1.26 Furnish and install conduits for each circuit as indicated on drawings.
E. Electrical and data new works for Building 223 only
1.2.6.1.20 Furnish and install new 120/208V, 400 amps, 42 spaces electrical panel, as indicated on drawings, and provide breakers for each load indicated on drawings. This panel shall be named “MDP”
1.2.6.1.21 Furnish and install new 120/208V, 400 amps, 42 spaces electrical panel, as indicated on drawings, provide breakers for each load indicated on drawings. This panel shall be named “A”
1.2.6.1.22 Use coiled cables to provide power to new electrical panel as indicated on drawings.
1.2.6.1.23 Extend conduits from computer room, CRAC A/C and Coiled cable circuits as indicated on drawings.
1.2.6.1.24 Furnish and install a new main breaker with lever operation enclosure as indicated on drawings.
1.2.6.1.25 Reconnect temporarily disconnected current transformers as indicated on drawings.
1.2.6.1.26 Furnish and install new surge protector device as indicated on drawings.
1.2.6.1.27 Re-power disconnected computer room as indicated on drawings.
1.2.6.1.28 Furnish and install new breakers for each load, as indicated on drawings.
1.2.6.1.29 Re-power existing Computer room air conditioning unit (CRAC) as indicated on drawings. Install breakers and power circuit from panel “MDP”
1.2.6.1.30 Re-power fire alarm panel, use AWG # 12 and 3/4” emt conduits as indicated on drawings.
1.2.6.1.31 Perform an insulation resistance test to cable run from main breaker to MDP panel, provide test results to COR. Tests are part of closeout documents. These tests shall be done and certified by a licensed electrician
F. Electrical and data new works for Building 224 only
1.2.6.1.32 Re-use breakers for new loads and adapt indicated ones as spare, details on drawings.
1.2.6.1.33 Re-power panel C224 from existing UPS breakers, as indicated on drawings.
1.2.6.1.34 Update panel schedules on each worked panel, as indicated on drawings.
1.2.6.1.35 Furnish and install two new 12” x 12” x 6” junction boxes to be used as access to Electrical/Mechanical room, as indicated on drawings.
1.2.6.1.36 Furnish and install new lift station pump electrical circuit and NEMA 4X S.S Control panel / disconnect, capable of complying with operation Logic and separate OCPD as indicated on drawings
1.2.6.2 Lighting System
A. Lighting demolition works for Buildings 223 & 224
1.2.6.2.1 Remove and dispose all interior lighting fixtures, as indicated on drawings.
1.2.6.2.2 Remove and dispose of all lighting control switches and motion sensors indicated on the interior of building.
1.2.6.2.3 Remove and dispose of all exit signs on the building.
1.2.6.2.4 Selected lighting fixtures to remain, as indicated on drawings.
B. Lighting new works for Buildings 223 & 224
1.2.6.2.5 Furnish and install, new 2’x4’ led t8 lighting fixtures equal or similar to Lithonia Lighting 2GTL-4
48L LP 480, 3 LED tubes, 38.11 watts as indicated on drawings.
1.2.6.2.6 Furnish and install, new 2’x4’ led t8 lighting fixtures equal or similar to Lithonia Lighting 2GTL-4
48L LP 480, 3 LED tubes, 38.11 watts, with battery back-up as indicated on drawings.
1.2.6.2.7 Furnish and install new emergency lighting fixtures as indicated on drawings.
1.2.6.2.8 Furnish and install new occupancy lighting control sensors, ceiling type, as indicated on drawings.
1.2.6.2.9 Furnish and install new exit signs with battery backup as indicated on drawings.
1.2.6.2.10 Use wires indicated on drawings for lighting fixtures.
1.2.6.2.11 Use conduits indicated on drawings for lighting fixtures.
1.2.6.2.12 Provide labels as indicated on drawings for each lighting fixture’s circuit and lighting pattern.
1.2.6.2.13 Use junction boxes as indicated on drawings, sizes and purposes varies.
1.2.6.2.14 Provide Labels and identification of circuits as indicated on drawings.
1.2.6.2.15 Furnish and install new emergency lighting fixtures as indicated on drawings.
1.2.6.2.16 Furnish and install new occupancy lighting control sensors, ceiling type, as indicated on drawings.
1.2.6.2.17 Furnish and install new exit signs with battery backup as indicated on drawings.
1.2.6.2.18 Use wires indicated on drawings for lighting fixtures.
1.2.6.2.19 Use conduits indicated on drawings for lighting fixtures.
1.2.6.2.20 Provide labels as indicated on drawings for each lighting fixture’s circuit and lighting pattern.
C. Lighting new works for Building 223 only
1.2.6.2.12 Server room and mechanical room lighting fixtures and lighting control fixtures will be re-used. The circuit shall be extended, as indicated on drawings, to keep them operating.
D. Lighting new works for Building 224 only
1.2.6.2.13 Server room lighting fixtures and lighting control fixtures will be re-used. The circuit shall be extended, as indicated on drawings, to keep them operating.
1.2.6.2.14 Furnish and install, new 2” x 2” LED T4 lighting fixture, equal or similar to Lithonia Lighting 2GTL
33L EZ1 LP840, 33.61 watts, as indicated on drawings.
1.2.7 Communications
A. Communications demolition works for Buildings 223 & 224
1.2.7.1 Remove and dispose of existing data cables, wall-mounted raceways, data outlets and junction boxes, as indicated on drawings.
1.2.7.2 Remove and dispose of existing cable trays up to the Communications room. Protect fiber optics steel conduits to remain.
B. Communications new works for Buildings 223 & 224
1.2.7.3 Furnish and install all new ¾” EMT conduit and cable tray for all new communication system. Cable tray shall be steel mesh/basket type with zinc (hot dip galvanized coating) and 3.94” rung spacing.
Cable trays shall run from the network room to the area to be refurnished above the ceiling, as indicated on drawings. Conduit shall run recessed on new gypsum walls and will run from above ceiling to new wall handy boxes. The Contractor may use J-hooks in areas where above ceiling walls exist. Install handy boxes 2” x 4” recessed on walls, including fish wires up to the ceiling level and the correspondent cable tray. These handy boxes will be used by the network enterprise center (NEC), in the future, for drop box installation. Provide required conduits and cable tray support.
1.2.7.2 Remove and dispose of existing cable trays up to the Communications room. Protect fiber optics steel conduits to remain.
1.2.7.3 All communication installation is only for infrastructure purposes. All equipment and cabling installation will be made in the future by the tenant in coordination with Ft. Buchanan Network Enterprise Center (NEC).
1.2.8 Fire Alarm System
A. Fire Alarm demolition works for Buildings 223 & 224
1.2.8.1 Remove and dispose of ceiling type smoke detectors, pull boxes, horn and strobe lights, as indicated on drawings.
B. Fire Alarm new works for Buildings 223 & 224
1.2.8.2 Furnish and install addressable photoelectric smoke detectors, manual stations, strobe/light combination, strobe lights and corresponding conduits and wire #18/2 as per equipment manufacturer requirement, as indicated on drawings. Fire alarm conduits and conductors shall be installed above ceiling and furred in existing walls.
1.2.8.3 New accessories or devices shall be connected to new Fire Alarm Control Panel FACP and be able to report any fire alarm from buildings 223 & 224 to Fire Department Station, Building 399. All new equipment and any other accessory required shall be addressable type and fully compatible with the existing receiver in the Fire Department Station.
1.2.8.4 The technical data of the receiver in the Fire Department Bldg. 399 can be obtained from: Monaco
Enterprises 14820 East Sprague Ave. PO Box 14129, Spokane Valley, WA 99214-0129 Phone 509-926-6277, Fax 509-924-4980. Point of contact Mrs. Toni Stroup.
1.2.8.5 The Contractor shall perform system programming and tests of simulated alarms as required by the
Fire Department. Fire alarm system shall be certified by a qualified technician authorized by the manufacturer of equipment and comply with all related NFPA codes and the American Disability Act
(ADA).
1.2.8.6 Do not splice any cable unless when interconnecting to another existing circuit.
1.2.9 Utility Outages: Work shall be scheduled to hold power outages to a minimum. Power outages and connections required during the prosecution of work that affect existing systems shall be arranged for at the convenience of the Government and facility users. Requests for utility outages and connections shall be made in writing to the Contracting Officer at least 30 Calendar days in advance of the time required. Each request shall state the facilities to be impacted, approximate duration of outage, and the nature of work involved. Power outages shall be arranged by Contractor for Monday thru Friday or for weekends at the convenience of Government and post facility users. Utilities outages during a holiday are to be considered an exceptional event, under emergency conditions or circumstances, that otherwise will result in a significant adverse impact on the contract. Panelboards, existing disconnect switches and circuit breakers shall be clearly labeled with plastic labels, duly protected as per technical specifications. Provide also plastic labels, to each cover plate of receptacle, toggle switch, lighting fixture and conductors, indicating circuit number and panelboard where circuit is connected.
1.3 NOT USED
1.4 CODES AND STANDARDS
1.4.1 GENERAL:
1.4.1.1 The project shall be constructed in accordance with the applicable codes, standards, design parameters or regulations noted in this section or other sections in the Statement of Work. In the event of conflict between codes, standards, or regulations, the most stringent requirement shall apply.
1.4.1.2 Reference to standard specifications of any technical society, organization, or association, or codes, manuals or regulations of Federal, State, or local, authorities shall mean the latest standard, code, manual, regulation, specification, or tentative specification adopted and published at least 30 days prior to submittal of proposals, unless specifically stated otherwise.
1.4.1.3 The reference of any code or standard listed below to the “building official” or the authority having “jurisdiction” or “governmental authority” shall be interpreted to refer to the Contracting Officer as being the authority for code interpretation.
1.4.2. BASIC REQUIREMENTS:
1.4.2.1 GENERAL: Construction shall be in accordance with the following codes, standards, and regulations. The most stringent shall govern when differences occur.
1.4.2.2 Building, Structural, Plumbing and Mechanical Codes: the latest edition of the Standard Building, Plumbing and
Mechanical Codes and the Puerto Rico State Building, Plumbing and Mechanical Codes.
1.4.2.3 Electrical Codes: National Electrical Code, latest edition, National Electrical Safety Code latest edition, NFPA and National Safety Code.
1.4.2.4 National Fire Protection Association Fire Codes, latest edition, and MIL.HANDBOOK 1008A, Fire Protection for Facilities.
1.4.2.5 Applicable OSHA Standards and Regulations.
1.4.2.6 Uniform Federal Accessibility Standards and ADA Standards, whichever is stricter.
1.4.3 STRUCTURAL: In addition to the general requirements stated above, structural design and construction will meet the latest editions of the following codes, standards, and specifications:
1.4.3.1 The Aluminum Association, “Specifications for Aluminum Structures”.
1.4.3.2 American Concrete Institute (ACI), “ACI-31B, Building Code Requirements for Reinforced Concrete”.
1.4.3.3 American Concrete Institute (ACI), “ACI-SSO, Building Code Requirements for Masonry Structures.
1.4.3.4 American Institute of Steel Construction (AISC), “Specification for the Design, Fabrication, and Erection of Structural Steel for Buildings”.
1.4.3.5 American Iron and Steel Institute (AISI), “Specifications of the Design of Cold-Formed Steel structural Members”.
1.4.3.6 American National Standards Institute (ANSI), “American Standard Building Code Requirements for Reinforced Masonry”.
1.4.3.7 American Welding Society (AWS), “Structural Welding Code”.
1.4.3.8…