SOW for Brow Post Replacement.docx
DOCX document 821 KB Posted
- Solicitation number
- 70Z02923QNEWO123
About this file
This statement of work outlines requirements for the replacement of a floating pier brow post located at the US Coast Guard Saint Louis Moorings facility. The selected contractor will remove the existing bent brow post and install a new post according to provided drawings and specifications. The contractor must have qualified welders and will conduct work between 6 AM and 4 PM on weekdays to minimize disruptions. Specific tasks include removing interferences, taking down the existing brow, installing the new post per dimensions and welding standards, reattaching the brow, and reconnecting utilities. The contractor is responsible for safety and any damages. The related federal contract opportunity is solicitation number 70Z02923QNEWO123 issued by the Department of Homeland Security US Coast Guard to procure these brow post replacement services.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Industrial Facility Pier Floating Dock Drawings PDF.pdf | ||
| DBA St Louis.txt | TXT text file | |
| Construction_Clauses_Provisions_FAC 2022-06.pdf | ||
| UFGS ST.LOUIS.pdf | ||
| SF1442-Pier St.Louis Moorings.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USCG MOORINGS ST. LOUIS BROW POST REPAIR
U.S. Coast Guard Saint Louis Moorings
STATEMENT OF WORK
REPLACEMENT OF FLOATING PIER BROW POST
Located at:
100 Arsenal St Saint Louis, MO 63118
GENERAL REQUIREMENTS
1. SCOPE
1.1. Intent: The intent of this project is to replace the bent brow post for the floating pier brow, as defined in this scope of work, located at US Coast Guard Moorings, Saint Louis, MO.
2. REFERENCES
COAST GUARD DRAWINGS
02-A5002 DISCIPLINE S13
PUBLICATIONS
Unified Facilities Guide Specifications (UFGS) 05 05 23.16
3. REQUIREMENTS
3.1. General: Contractor shall furnish all labor, tools, materials, transportation, equipment, supervision, and personnel to perform the removal and replacement of the identified bent brow post at St. Louis Moorings. No repairs outside the Statement of Work criteria are authorized without permission from the contracting officer or their representative.
3.2. Qualifications: Contractor shall provide welders that have the qualifications and certificates as per section 1.3.4 of UFGS 05 05 23.16
3.3. Continuity of Facilities Operation: Schedule work to minimize interference with the facility’s normal operations. Perform all on-site work between the hours of 6:00 AM and 4:00 PM, Monday through Friday (federal holidays excluded), unless otherwise approved by the Contracting Officer or Contracting Officer’s representative.
WORK ITEM 1: REPAIR BENT BROW POST
1. SCOPE
1.1. Intent: This work item describes the requirements for the Contractor to remove and replace one (01) brow post.
1.2 Government Furnished Property: None
2. REFERENCES
COAST GUARD DRAWINGS
02-A5002 DISCIPLINE S13
PUBLICATIONS
Unified Facilities Guide Specifications (UFGS) 05 05 23.1
3. REQUIREMENTS
3.1 Conduct operational test of all shore ties and submit CFR.
3.2 Removal all interferences as necessary, to include but not limited to:
3.2.1 Potable Water piping.
3.2.2 Sewage (Forced Main) piping.
3.2.3 Electrical Shore Tie wiring.
3.2.4 Telecomms wiring.
3.3.5 All shore tie interferences the transfer from the wharf to the brow may be moved with the brow and left intact. See Fig A. for reference.
Fig. A
3.3 Remove brow from collars.
3.3.1 Contractor must submit a CFR detailing their plan to remove and reattach the brow for the duration of the work. Access to the pier must be available in the event of an emergency and shall be addressed in the plan.
3.3.2 The brow is connected to the collars by a pin. See Fig B. for reference.
3.3.3 Remove and save collar from bent post for re-use on new post
Fig B.
3.4 Remove bent post at base where it is connected to support I-beam.
3.5 Install new brow post.
3.5.1 Reference drawing 02-A5002 DISCIPLINE S13 for dimensions and welding specs.
3.5.2 Test new post for straightness.
3.5.3 Complete NDT of welds IAW (UFGS) 05 05 23.16 Section 3.3.1 Nondestructive Testing.
3.5.4 Apply paint/protective coating on new post.
3.6 Affix brow to collars.
3.6.1 Test collars for proper movement on post before attaching brow.
3.6.2 Connect brow to collars using pins as seen in Fig B (above).
3.6.3 Replace brow to original position.
3.7 Test brow for proper movement on post
3.7.1 Use crane to move brow up and down post as intended by design.
3.8 Replace all interferences as necessary.
3.8.1 Conduct post work operational test of the shore ties/utilities.
4. NOTES
4.1 Site Visit: Site visits are recommended. All site visits should be scheduled with the Contracting Officer, Facilities Engineer and/or their representative.
POC: DCC John Eister Email: John.J.Eister@uscg.mil Phone: (314)-771-6044 x2107
POC: IPD Supervisor Jame Tepen Email: James.A.Tepen@uscg.mil Phone: 314-771-6044 x 2130
4.2 Performance Standards: Proper adherence to all OSHA and Industry safety procedures is required prior, during and after work being performed. The contractor shall furnish all personnel with and require donning of required personal protective equipment (PPE). The contractor shall safeguard the public and government personnel, property, materials, supplies, and equipment exposed to contractor operations and activities, and avoid interruptions of government operations in the performance of services.
4.3 Liability of Damages: The contractor shall be liable for all damages to Government equipment and property when such damage is due to fault or negligence of the contractor. The contractor shall be responsible for all damages or injury to persons that occur as a result of the contractor’s fault or negligence. The contractor shall take proper safety and health precautions to protect the work, the workers, the public, and the property of others.