SOW FOR BLDG 1082 SEAM TEK3 EPOXY QUARTZ FLOORING INSTALLATION.doc

DOC document 70 KB Posted

Attached to
Supply and Install Epoxy Quartz Flooring Federal contract opportunity
Solicitation number
12305B22R0025
Issued by
Department of Agriculture Agricultural Research Service Field Research Implementation and Information Delivery Northeast Area

View the file

Other files for this federal contract opportunity

Other files attached to Supply and Install Epoxy Quartz Flooring, newest first.
File Type Posted
SF30.pdf PDF
Questions and Answers.docx DOCX document
12305B22R0025.pdf PDF
LSP RESIN CHEMICAL RESISTANCE PERFORMANCE CHART.pdf PDF
st_floors_seamtek_pds_Type3.pdf PDF
st_floors_seamtek_spec_Type3.pdf PDF
BLDG. #1082 DRAWINGS.pdf PDF
Wage Determination MD20220044 08052022.pdf PDF
st_floors_epoxy_colors_Type3.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UNITED STATES DEPARTMENT OF AGRICULTURE

BELTSVILLE AGRICULTURAL RESEARCH CENTER

FACILITIES SERVICE

ENGINEERING AND CONSTRUCTION BRANCH

BUILDING 426A, BARC-EAST

10300 BALTIMORE AVENUE

BELTSVILLE, MARYLAND 20705-2350

STATEMENT OF WORK AND SPECIFICATION

TO

SUPPLY AND INSTALL SEAMTEK TYPE 3 HEALTHCARE EPOXY QUARTZ FLOORING SYSTEM AT BLDG. #1082

BELTSVILLE AGRICULTURAL RESEARCH CENTER

BELTSVILLE, MARYLAND

AUGUST 2022

STATEMENT OF WORK

PROJECT NUMBER: B1082EQFS

PROJECT LOCATION: Beltsville Agricultural Research Center (BARC), Bldg. #1082, Beltsville, Maryland DESCRIPTION OF WORK: To supply and install SeamTek Type 3 Healthcare Epoxy Quartz Flooring System at Bldg. #1082.

HazMat: In accordance with this contract, the contractor shall provide all labor, material, equipment, and transportation to include all accessories and incidentals necessary to complete this job to government requirements. The facility under this contract may contain Asbestos and Lead materials. The contractor(s) is/are warned not to disturb any asbestos or Lead materials during the performance of this work. Should the contractor encounter any material that in their judgment may contain Asbestos or Lead, they must stop work immediately and notify the contracting officer (CO) and (COR) within 24 hours. See the Hazmat Testing Results for Asbestos and Lead.

Prior to commencing work, the contractor is required to obtain Construction Authorization, vehicle permits, and identification badges. These can be obtained from the Engineering and Construction Office, Building 426A, BARC-East, Beltsville, Maryland. Vehicle permits and identification badges shall be returned to the Government prior to the final payment being issued.

NOTE: THE CONTRACTOR SHALL NOTIFY THE GOVERNMENT TECHNICAL REPRESENTATIVE ON 301-504-8434 at least 24 HOURS BEFORE ANY WORK IS SCHEDULED TO START. All contractor's work shall be monitored and inspected by BARC personnel and done in accordance with the Statement of Work and attached drawings, specifications, graphics, BARC Special Conditions, and performed in accordance with all federal, state, and local regulations as well as all applicable local building codes, Construction Standards and Codes, Americans with Disabilities Act, local and State traffic codes, Maryland Department of the Environment, the Maryland Highway Specifications, and the Maryland Department of the Environment Regulations concerning Clean Water Act. In the event of conflict, the most stringent regulation shall prevail.

Scope of Work:

The contractor shall provide all labor, materials, supplies, specialized equipment/tools, transportation and supervision to supply and install SeamTek Type 3 Healthcare Epoxy Quartz Flooring System at Bldg. #1082.

A construction work schedule shall be provided by the contractor prior to work start up.

The contractor shall perform the following work, but not limited to:

A. To install SeamTek Type 3 Healthcare Epoxy Quartz Flooring System at Bldg. #1082.

1. Mobilization:

Mobilize all necessary personnel, specialized tools and equipment, approved materials, Dumpsters, safety items and all other necessities to initiate a work start up after receiving the notice to proceed.

Contractor shall stage ladders and scaffolding as to allow free access to main front entrance to building at all times. All necessary precautions shall be taken to provide safe passage at the point of entrance/exit (contractor may be required to construct temporary safety passage to catch debris that could fall on individuals entering and exiting the building).

The contractor shall have delivered, handling and storage of all materials by the manufacture’s specifications.

Pre-Installation conference shall be required with Prime Contractor, Owners Representative, Flooring Contractor and/or Manufacturer's Representative to review the following: Evaluate slab conditions and extent of repairs necessary for Contractor to begin normal preparation and installation of seamless flooring.

Evaluate detail conditions at all penetrations, terminations, perimeter and drain locations. Detail problems shall be documented and resolved prior to floor installation.

Test concrete sub-floors using the Calcium Chloride test method to verify that slab moisture vapor transmission rate does not exceed manufacturer’s recommendations.

The Flooring Contractor shall provide an add option cost as part of the bid for the treatment of substrate moisture vapor transmission in the event the substrate exceeds manufacturers recommendations. Slab testing shall be performed immediately prior to floor installation so as to achieve the nearest real time conditions. Any slab developing readings of 3 pounds of water per 24 hours per 1000 square feet or greater by ASTM F-1869-98 shall receive Integral Concrete Waterproofing which shall be compatible with flooring and approved by the Flooring Manufacturer. Waterproofing shall be installed by a contractor that is certified by the manufacturer of the waterproofing material. The waterproofing system must have a materials and labor warranty of at least 5 years against the loss of bond due to substrate moisture vapor transmission if initial readings are above 3 pounds. The moisture proofing product shall be certified as compatible with the flooring material manufacturer.

Review job site conditions, including temperature, power, and lighting. Such problems shall be documented and resolved prior to floor installation.

Protect surrounding substrate and surfaces as well as in place equipment from damage during surface preparation and system installation.

All drains must be working and set at the proper elevation.

Job area shall be free of other trades during floor installation, and for a period of 48 hours upon completion.

The Prime Contractor shall provide adequate ventilation by use of fans or other devices.

The Prime Contractor shall maintain lighting at final end use levels during the installation.

The Prime Contractor shall ensure that leaks from pipes and other sources are corrected prior to floor installation.

The Prime Contractor shall provide minimum substrate and ambient temperature of 70(F and relative humidity below 80% during floor installation and until final acceptance.

2. Demolition/Surface Preparation:

The Prime Contractor shall for New or Exposed Concrete Slabs: Prepare concrete to “open” surface pores by means of vacuum-blasting, removing contaminants and bond breaking substances, including but not limited to dust, latencies, curing compounds, coatings, sealers, oil and grease. In circumstances approved by the manufacturer, mechanical abrasion by means such as terrazzo grinding will be acceptable. Oil and grease not removed by vacuum-blasting shall be chemically removed. Mechanically remove delaminated or deteriorated concrete by scabbing or chipping hammers. Areas to be patched shall be saw cut to minimum 1/2” depth at perimeters and keyed to existing concrete. (For thorough instructions regarding preparation of concrete and non-concrete substrate, consult STI “Instruction for Surface Preparations”.)

The Prime Contractor for Renovation Projects Where an Original Resinous Floor Remains: Assure that the existing floor is bound tightly to the substrate by performing preliminary “pull tests”. Assure that the existing floor and substrate are dry and exhibit no signs of previous moisture problems. Remove loose and deteriorating flooring to expose sound substrate and patch back to original elevation prior to prep of the remaining surface. Thoroughly prepare the remaining floor using terrazzo grinding or another prep procedure approved by the manufacturer.

The contractor shall remove and dispose of Government property, all items indicated as TO BE REMOVED. Such items become the property of the contractor and shall be loaded, transported per applicable DOT regulations, and disposed of at approved landfills.

3. Quality Assurance:

Manufacturer: The Sub Contractor shall obtain all manufacturer’s flooring materials required for this Requirement from a single source.

The Sub Contractor: Shall have a minimum of 5 years’ experience in the installation of seamless flooring and be approved in writing by the specified manufacturer.

Floor Thickness Verification: At the EPM/COR direction and under his supervision the Prime Contractor shall take 3 random cores at Bldg. #1082, through system to substrate, prior to applying final seal coat, to verify proper floor thickness. Repair cored areas to match surrounding surface prior to applying final seal coat. Remove and replace areas with less than specified thickness, in a manner that does not effect aesthetics or integrity of overall floor.

4. Installation:

The contractor shall provide boom lifts, scaffolding, ladders, scaffolding systems, etc. that is required to facilitate a safe and productive working environment.

The Prime Contractor shall supply and have install by an experienced Seamless Epoxy Quartz Floor Installer a LSP SeamTek Type 3 or approved equal by the COR and applied at a minimum floor finish thickness of 3/16". System shall be sealed with Chemical Resistant Epoxy resin. System shall have a mild skid resistant texture. All epoxy resins shall be 100% solids for low odor and job-site safety during installation. Aggregate to be decorative ceramic coated quartz blends to be selected by the EPM/COR. System shall have the following properties:

Compressive Strength ASTM C-579 11,000 psi

Tensile Strength ASTM C-307 2,400 psi

Flexural Strength ASTM C-580 4,000 psi

Flexural Modulus ASTM C-580 2.5 X 105

Chemical Resistance Chart (The following is a generic listing of chemical resistance and cannot be counted on to be accurate for all commercial solutions. We recommend testing of the specific chemicals to verify resistance.)

E - Excellent (up to 7 days), G - Good (Up to 24 hours), SS - Splash and Spill with immediate removal or NR - Not recommended.

See the enclosed LSP Resin Chemical Resistance Performance Chart.

The prime Contractor shall apply new flooring components required for the system in accordance with the statements in System Overview above and handle materials per manufacturer’s installation instructions, including mixing and application. Terminate at edge of expansion joints, or as designated by Design Professional. Install a 4” integral cove base on walls unless otherwise indicated on drawings.

The prime Contractor shall cure resinous materials in compliance with manufacturer’s directions.

The Prime Contractor shall cleanup work area, removing all equipment, materials and trash.

The Prime Contractor shall provide temporary protection from construction traffic and other trades prior to final acceptance by the owner.

The Prime Contractor shall make sure that the Integral Concrete Waterproofing (ICW) done as follows: In accordance with Job Site Conditions Section 1.08, A, 3) test all concrete slabs scheduled to receive seamless flooring using the Calcium Chloride test method (ASTM F 1869-98) to determine if moisture vapor transmission rates are within limits acceptable to the manufacturer.

5. Delivery, Handling and Storage:

Deliver materials in manufacturer's undamaged containers, clearly marked with the following:

1. Product Name

2. Manufacturer's Name

3. Resin or Hardener Designation

4. Mix Ratio of Resin and Hardener

Handle materials in a safe and proper manner to avoid damage or spill.

Inspect direct jobsite deliveries to verify correct material and quantities are received in good condition.

Replace, at no cost to the owner, materials that are found to be defective in manufacturing or damaged in transit, handling or storage.

Store materials per manufacturer's instructions and as follows.

1. Seals and labels shall be intact and legible.

2. Temperature of storage area shall be maintained between 60(F and 80(F.

3. Do not use materials which have been stored for a longer period of time than the manufacturer's maximum recommended shelf life.

6. Performance Requirements and Warranty:

The Prime Contractor shall provide Manufacturer's standard single source warranty in accordance with the manufacturer's written warranty on seamless flooring for period of two years after installation, warranting against loss of bond and wear through to concrete substrate (through normal wear and use) exclusive of substrate moisture related problems. Warranty shall be single source from the manufacturer, including material and labor.

7. Submittals:

The Prime Contractor shall submit to the EPM/COR three 12" X 12" system samples with the bid for purposes of chemical resistance testing. The end user has the option to conduct on site chemical resistance testing “in their hands” to assure that the submitted system is acceptable for use in their environment. The end user reserves the right to refuse any bidder whose samples do not meet with their approvals as a result of these tests.

The Prime Contractor shall submit to the EPM/COR the Manufacturer's standard color charts for color selection for color selection by the EPM/COR.

The Prime Contractor shall submit to the EPM/COR a Site-Specific Safety Plan.

8. General:

A. Demolition: The contractor shall remove and dispose of Government property, all items indicated as TO BE REMOVED. Such items become the property of the contractor and shall be loaded, transported per applicable DOT regulations, and disposed at approved landfills.

B. Field Verification: The contractor is responsible for field verification of all measurements, quantities, and field conditions prior to commencing work.

C. Staging: All equipment, supplies and materials for this contract shall be stored in the work area at the contractor’s risk. The buildings and grounds at BARC will be secured at the end of each day by BARC Security. The security at BARC is not responsible for any of the contractor's stored material, equipment, either inside or outside the building at any time.

A. Construction Project Schedule: See contract, FAR 52.236-15 Schedules for Construction Contracts. The Contractor will not begin actual work until the construction project schedule has been approved by the Contracting Officer. The Contractor shall submit one electronic copy of the updated construction project schedule with each progress payment request.

B. Contract Inspector’s Daily Report: Contractor shall submit to the Contracting Officer a daily report listing the names of all those present on the job site each day, along with their Job Classification, hours of work and a brief description of the work performed by each on that day. The Contract Inspector’s Daily Report is to be submitted at the beginning of work each day for the previous day’s work and shall be maintained throughout the term of the contract.

C. Formal Meetings: Any meeting (deemed formal by the contractor, the COR, or the Contracting Officer) will have the minutes of said meeting prepared by the contractor (and a copy provided to the Contracting Officer). The minutes will include: Date, Name of Attendees (with contact info), Old Business, and New Business subjects (or narratives). Regardless of who requests a meeting (the COR or the Contractor or the Contracting Officer) the contractor may be required to provided hard copy pictures of the issues to be discussed. Each issue will be linked to a contract specification section number and/or subject area by page number. Issues discussed will also include an action/completion date.

D. Safety Submittals: Contractor shall submit a "site specific" Safety Plan to the Contracting Officer that describes how the contractor is to comply with all applicable OSHA standards and NFPA codes pertaining to construction work to include, but not limited to: General Safety and Health Provisions, Occupational Health and Environmental Controls, Personal Protective and Life Saving Equipment, Hand and Power Tools, Welding and Cutting, Electrical, Scaffolds, Fall Protection, Excavations, Demolition, Stairways and Ladders, Toxic and Hazardous Substances, Confined Space Entry, Lockout/Tagout, Respiratory Protection, Hearing Protection. Safety Plan shall identify Contractor and sub-contractor employees who are authorized/qualified to perform electrical work. No work shall proceed until written approval of the Safety Plan by the Contracting Officer. Safety Plan shall describe how the Contractor and/or sub-contractors are to secure equipment, supplies, tools, and chemical products. Contractor and/or sub-contractor equipment, supplies, tools, and chemical products are to be under the control of the Contractor at all times, equipment, supplies tools, and chemical products found not to be under the control of the Contractor or sub-contractor are subject to confiscation and will be reported to the Contracting Officer. Note see the enclosed sample of a Site-Specific Safety Plan.

E. The Contractor shall inspect the entire construction site daily, including days without construction work if there are NFPA 101 Life Safety Code deficiencies existing while construction work is shut down, the results of that inspection shall be documented on the attachment “DAILY INSPECTION FORM”, and the form is to be signed and submitted to the Contracting Officer.

F. Contractor shall provide continuous monitoring for noise, dust, chemical vapor generation, volatile organic compounds, and vibration. At no time shall noise exposure to any ARS staff exceed 75 dB. Contractor shall provide to the Contracting Officer a written weekly update of the all test results and also for proposed work for the subsequent two weeks (a two week “look-ahead”)involving any construction activity that will produce loud noises, heavy vibrations, strong smells, or significant dust inside ARS staff occupied space.

G. Contractor and sub-contractors shall notify in writing the Contracting Officer at least one week prior to executing high risk work (this may be included in the two week “look-ahead” update). High risk work includes, but is not limited to, tasks requiring Lockout/Tag Out, live electrical work, hot work, work at heights, trenching/ shoring, crane operations, and confined space entry. Contractor’s Competent Person shall provide the Contracting Officer written weekly documented safety inspection results.

H. Contractor shall provide to the Contracting Officer for approval, copies of Safety Data Sheets (SDS) for EVERY CHEMICAL WITHOUT EXCEPTION prior to bringing such chemical on the work site.

I. Hot and Grinding Work Permits: The Contractor will not be permitted to work without this permit when performing Hot and Grinding Work.

J. Scheduling: The total contract period shall be 120 calendar days from the point of contract award. A period of 5 calendar days shall be allotted for the submittal, 5 calendar days for review and re-submit process. A period of 10 days shall be allotted for ordering materials. The work on-site shall be limited to one, one hundred and twenty (120) calendar days. The final inspection shall be scheduled a maximum of 103 calendar days from point of contract award, leaving 2 days for punch list remedies. The contractor shall submit a copy of his proposed schedule to the CO for approval. Please note that the shipping timeline is 10 delivery time after approved submittals. The actual construction work period shall be 105 calendar days.

K. Submittals: The contractor shall submit the manufacturer’s technical data sheets and shop drawings for the items listed in the Submittal Registry 5 calendar days from the point of contract award. Each submittal shall be attached to a Submittal Transmittal Form (enclosed), signed by the Contractor, and delivered to the Contracting Officer. Provide 6 copies of each material submittal. All Aquatherm materials shall list name of each product to be used identified by manufacturer and product number.

L. Coordination: The contractor shall coordinate with the COR, with adequate notice, all work which will require an inconvenience or work stoppage to Government personnel due to noise, dust, extreme temperatures, or interruption in utilities.

M. Complete Work: It is the intent of this project to contract for a complete, functioning mechanical and or electrical system, finished in all respects, accomplished by mechanics skilled in the trades involved and performed in the highest standards of workmanship.

N. Contractor Guaranty and Warranty: All contracted work shall be guaranteed by the contractor for a period of one (1) year for labor from the date of final acceptance against defective materials, design, and workmanship. The material shall be as specified in the manufacture’s specifications but at least one year. Upon receipt of notice from the Government of failure of part or parts of the guaranteed equipment during the warranty period, the affected part or parts shall be replaced within 48 hours with new parts by and at the expense of the contractor. ALL WARRANTIES SHALL BE TURNED OVER TO THE COTR PRIOR TO FINAL INVOICING.

END