SOW Fire Panel Replacements B810 B67 B94.pdf

PDF 969 KB Posted

Attached to
DFC BLDG 810, 94, 67, Fire Panel Replacements
Solicitation number
EQPXAFB-26-0024
Issued by
Not on record

About this file

Statement of Work Summary: DFC Fire Panel Replacement

This is a Design-Build Services Statement of Work for the replacement of Edwards EST-3 fire alarm control panels and associated systems at three buildings (B810, B67, and B94) within the Denver Federal Center in Lakewood, Colorado. The project is a firm fixed-price contract with a 180-calendar-day period of performance, comprising 60 days for design services, 60 days for construction to substantial completion, and 60 days for project closeout. The contractor must submit HSPD-12 clearance applications by 95% design submission and coordinate all work with the GSA Contracting Officer and Contracting Officer's Representative/Project Manager.

The scope of work requires the D/B Contractor to provide all engineering, programming, labor, materials, supervision, and testing to upgrade existing EST-3 systems to EST-4 fire alarm control systems while maintaining continuous life safety protection and minimizing disruption to occupied buildings. Key requirements include performing functional testing of existing systems (minimum 10% of initiating devices and 100% of notification zones), replacing all incompatible addressable initiating devices, providing new fire alarm system printers, upgrading communicators, providing surge protective devices, and securing NFPA 72 shop drawing approvals from the GSA regional fire protection engineer. The contractor must also provide a licensed third-party fire protection engineer to witness acceptance testing, conduct fire watches during system changeover, and coordinate with O&M preferred service providers for sprinkler and elevator system work. Building 810 requires integration between the new EST-4 system and an existing Silent Knight fire alarm system. Design submissions are required at 35%, 65%, 95%, and 100% (IFC) completion levels, with detailed specifications, drawings, calculations, cost estimates, quality control plans, safety plans, and phasing plans required at appropriate submission intervals. All work must comply with NFPA 72, NFPA 101, International Building Code, GSA PBS standards, and all applicable federal, state, and local codes.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

U.S. General Services Administration

Public Buildings Service

Statement of Work for

Design-Build Services

PROJECT IDENTIFICATION

Project Title: DFC Fire Panel Replacement Building: DFC B810, B67, and B94 Building ID #: CO0624AA, CO0627AA, CO0660AA

Building Location: Denver Federal Center Lakewood, CO 80225

Project Control Number: RCO35057, RCO35058, RCO35059 Kahua Number: 42591

SOW Author: William A. Roum

Design-Build Services Statement of Work, V8.0 Fire Panel Replacements, DFC Buildings 810, 67, and 94

[Editor: Right-click and Update Table of Contents before finalizing document]

TABLE OF CONTENTS

PROJECT INFORMATION 5

PROJECT SUMMARY 5

PROJECT BACKGROUND 5

CONTRACT TYPE 5

DELIVERY TYPE 5

PROJECT GOALS 5

PROJECT OBJECTIVES 6

PROJECT SCHEDULE 6

SCOPE OF WORK 7

PROJECT REQUIREMENTS 7

PROJECT SITE REQUIREMENTS 7

STANDARDS AND CRITERIA DOCUMENTS 9

CUTTING & PATCHING REQUIREMENTS 13

NATIONAL HISTORIC PRESERVATION ACT (NHPA) REQUIREMENTS 14

NATIONAL ENVIRONMENTAL POLICY ACT (NEPA) REQUIREMENTS 14

EXTERNAL REVIEW AGENCIES - LOCAL STATE OTHER FEDERAL 16

FINE ARTS REQUIREMENTS 16

ACCESSIBILITY REQUIREMENTS 16

SAFETY REQUIREMENTS 16

FIRE PROTECTION AND LIFE SAFETY REQUIREMENTS 16

HAZARDOUS MATERIAL REQUIREMENTS 21

BUILDING CONTROL SYSTEMS, INCLUDING BUILDING AUTOMATION SYSTEMS (BAS) AND

BUILDING MONITORING AND CONTROL (BMC) SYSTEMS 31

COMMISSIONING 31

SITEWORK AND STORMWATER REQUIREMENTS 32

BUILDING TECHNOLOGY SERVICES 35

March 10, 2026 2 of 53 Back to Top

MANUFACTURER REQUIREMENTS 35

BUILDING INFORMATION MODELING ( ) 35

ENERGY MODELING AND PERFORMANCE 35

COBie 35

DESIGN STAGE 37

PRE-DESIGN PHASE 37

DESIGN PHASE 37

CONSTRUCTION PROCUREMENT PHASE 43

CONSTRUCTION STAGE 44

GENERAL 44

PERMITTING 44

CONSTRUCTION SCHEDULE 45

CONSTRUCTION PROGRESS REPORTS 45

SHOP DRAWINGS / PRODUCT DATA SUBMISSIONS 45

SCHEDULE OF INSPECTIONS AND TESTS 46

CONSTRUCTION INSPECTIONS 47

SPECIAL INSPECTIONS 47

COMMISSIONING 47

QUALITY CONTROL PLAN 48

CONSTRUCTION INDOOR AIR QUALITY (IAQ) MANAGEMENT 50

SAFETY PLAN 52

COORDINATION OF WORK 52

REQUESTS FOR INFORMATION 52

MODIFICATIONS / CHANGE ORDERS 52

CONTRACT ADMINISTRATION 53

CONTRACTOR’S STAFF 53

MEETINGS 53

COMMUNICATION 54

March 10, 2026 3 of 53

PROJECT CLOSEOUT 54

SCHEDULE OF VALUES 56

FEE & PAYMENT 57

GOVERNMENT FURNISHED PROPERTY 57

ATTACHMENTS 57

March 10, 2026 4 of 53

1.PROJECT INFORMATION

This section provides an overview of the project.

1.1. PROJECT SUMMARY

This project will replace the existing Edwards EST EST-3 fire alarm control panels and associated graphic annunciators at the Denver Federal Center (DFC) in Building 810, Building 67, and Building 94 with new EST-4 fire alarm control systems. The existing EST-3 systems are end-of-life equipment with limited manufacturer support and replacement parts no longer readily available, creating long-term operational, maintenance, and reliability concerns for the Government.

The project is intended to improve system reliability, maintainability, and code compliance while supporting continued building operations and occupant life safety throughout the Denver Federal Center campus. Building 810 also requires integration between the new EST-4 system and the existing Silent Knight fire alarm system currently serving portions of the facility.

The project will include replacement of fire alarm control equipment, associated annunciators, and related system components necessary to support continued operation of the fire alarm systems at each facility. Existing removed EST equipment identified by the Government shall be preserved and turned over to GSA for potential reuse in supporting other existing EST systems located throughout the Denver Federal Center.

This effort supports ongoing facility infrastructure modernization initiatives across the Denver Federal Center and is intended to address aging fire alarm infrastructure prior to complete manufacturer obsolescence and increased system failure risk.

1.2. The D/B Contractor shall coordinate work and gain approvals required in this Statement of Work (SOW) with the Contracting Officer (CO) and Contracting Officer’s Representative/Project Manager (COR/PM) as required. PROJECT

BACKGROUND

The Denver Federal Center (DFC) is a multi-building federal campus consisting of administrative, operational, and mission-critical facilities occupied by multiple federal agencies. Buildings 67, 94, and 810 are existing federally owned facilities that currently utilize legacy Edwards EST EST-3 fire alarm systems as part of their base building life safety infrastructure. The existing EST-3 systems have reached end-of-life status, with limited manufacturer support and replacement parts becoming increasingly difficult to procure and maintain.

Building 67 is an existing occupied federal office and operations facility that includes integrated smoke control functions associated with the building fire alarm system. The facility has experienced historical smoke control testing deficiencies, creating operational

March 10, 2026 5 of 53 and maintenance concerns for the existing fire alarm infrastructure. The building currently operates on an EST-3 platform with associated field devices and annunciation equipment serving the facility.

Building 810 is an occupied federal facility within the Denver Federal Center campus currently utilizing an EST-3 fire alarm system in conjunction with an existing Silent Knight fire alarm system serving portions of the building. The existing configuration requires continued operational coordination between systems to maintain facility life safety functionality. Due to the age of the infrastructure and the mixed-system configuration, modernization of the fire alarm control equipment is required to support long-term reliability and maintainability.

Building 94 is an existing occupied federal facility utilizing an EST-3 fire alarm control system and associated graphic annunciators as part of the building’s life safety systems. Similar to other EST-3 systems located throughout the Denver Federal Center campus, the existing equipment is approaching obsolescence and presents ongoing maintenance and operational support challenges.

The proposed project is part of the Denver Federal Center’s broader infrastructure modernization and lifecycle replacement efforts intended to maintain reliable, code-compliant fire alarm and life safety systems across the campus. The project will upgrade the existing EST-3 fire alarm control equipment to the EST-4 platform while maintaining building operations throughout construction and supporting continued occupancy of the facilities.

1.3. CONTRACT TYPE

This contract is a firm fixed-price contract. The services required shall include, but shall not be limited to, the following:

● Contract Management

● Professional Architect/Engineer Services

● Construction Services including Materials, Labor, and Supervision

● Professional Inspection and Testing Services

1.4. DELIVERY TYPE

The project is a Design-Build delivery type.

1.5. PROJECT OBJECTIVES

To be considered successful, the project must achieve the following objectives:

● Deliver the project on schedule and within the approved project budget while maintaining compliance with all contract requirements and milestone deliverables.

March 10, 2026 6 of 53

● Successfully replace the existing Edwards EST EST-3 fire alarm control systems in Buildings 67, 94, and 810 with operational EST-4 fire alarm systems that support long-term maintainability, reliability, and manufacturer support.

● Maintain continuous life safety protection and minimize disruption to tenant operations throughout construction, testing, and system changeover activities.

● Ensure successful integration and operational compatibility between the new EST-4 fire alarm system and the existing Silent Knight fire alarm system serving portions of Building 810.

● Complete all work in compliance with applicable federal, state, and local codes, including NFPA 72, NFPA 101, International Building Code (IBC), GSA PBS standards, and GSA fire protection requirements.

● Achieve successful completion of all required testing, commissioning, smoke control integration testing, and final acceptance testing with no unresolved deficiencies.

● Complete the project with zero lost-time accidents, safety incidents, fire protection violations, or unauthorized system impairments attributable to contractor operations.

● Maintain a safe and secure work environment for building occupants, Government personnel, construction personnel, and authorized visitors throughout all phases of the project.

● Complete all work with no security violations and ensure compliance with all federal facility security requirements, badging procedures, access restrictions, and escort requirements.

● Ensure all sensitive, security-related, and operational documents are properly managed, distributed, stored, archived, and destroyed in accordance with established GSA procedures and project protocols.

● Maintain positive and professional working relationships with GSA, tenant agencies, building occupants, Authorities Having Jurisdiction (AHJs), subcontractors, and other project stakeholders throughout the duration of the project.

● Provide timely, accurate, and complete project communications, schedules, outage notifications, testing plans, progress updates, and closeout documentation.

● Coordinate all fire alarm outages, impairments, and testing activities in advance with the GSA Project Manager, GSA Building Manager, tenant agencies, and applicable stakeholders to minimize operational impacts.

● Preserve, protect, and turn over Government-designated removed EST equipment to GSA for potential reuse in supporting other existing EST systems throughout the Denver Federal Center.

● Deliver complete and accurate project closeout documentation, including as-built drawings, testing reports, programming documentation, operation and maintenance manuals, warranties, and training materials.

● Manage and execute the project in a cooperative partnering environment focused on proactive communication, issue resolution, and successful project completion without litigation or formal disputes.

March 10, 2026 7 of 53

1.6. PROJECT SCHEDULE

The overall Period of Performance shall be 180 calendar days from Notice To Proceed (NTP) to Project Closeout, based on the following:

● Design Services 60 calendar days after NTP

● Submit All HSPD-12 Clearance ApplicationsNot Later Than 95% Design Submission

● Construction to Substantial Completion 60 calendar days after 100%

Approval

● Project Closeout (as defined in Section 5.4.) 60 calendar days after Substantial

Completion

March 10, 2026 8 of 53

2.SCOPE OF WORK

DFC Building 810

The contractor shall provide all engineering, programming, labor, material, supervision and testing to upgrade the existing Main Building Fire Alarm Control Unit (FACU) at Denver Federal Center Building 810 , due to the current fire alarm control equipment no longer being supported by the manufacturer.

The existing Main FACU located Location Here, consists of an Edwards EST-3 with [Description of the System here, # of nodes, Evac sequence, network class, emergency voice/alarm, Service provider, etc.]. The fire alarm system has (#) networked sub-panels.

This building fire alarm system is normally operated in a general evacuation mode. The building evacuation via initiating devices (i.e. Manual stations, heat detectors, smoke detectors, sprinkler water flow switches) will notify the Alarm Co. The existing graphic annunciator is located Location Here. The current system distributor for equipment and programming is

DFC Building 67

The contractor shall provide all engineering, programming, labor, material, supervision and testing to upgrade the existing Main Building Fire Alarm Control Unit (FACU) in/at Agency Name and Address Here , due to the current fire alarm control equipment no longer being supported by the manufacturer.

The existing Main FACU located Location Here, consists of an Edwards EST-3 with [Description of the System here, # of nodes, Evac sequence, network class, emergency voice/alarm, Service provider, etc.]. The fire alarm system has (#) networked sub-panels.

This building fire alarm system is normally operated in a general evacuation mode. The building evacuation via initiating devices (i.e. Manual stations, heat detectors, smoke detectors, sprinkler water flow switches) will notify the Alarm Co. The existing graphic annunciator is located Location Here. The current system distributor for equipment and programming is

DFC Building 94

The contractor shall provide all engineering, programming, labor, material, supervision and testing to upgrade the existing Main Building Fire Alarm Control Unit (FACU) in/at Agency Name and Address Here , due to the current fire alarm control equipment no longer being supported by the manufacturer.

The existing Main FACU located Location Here, consists of an Edwards EST-3 with [Description of the System here, # of nodes, Evac sequence, network class, emergency voice/alarm, Service provider, etc.]. The fire alarm system has (#) networked sub-panels.

This building fire alarm system is normally operated in a general evacuation mode. The building evacuation via initiating devices (i.e. Manual stations, heat detectors, smoke detectors, sprinkler water flow switches) will notify the Alarm Co. The existing graphic annunciator is located Location Here. The current system distributor for equipment and programming is

March 10, 2026 9 of 53

The Scope of Work indicated is not intended to limit the design of the D/B Contractor’s Architect/Engineer (A/E). Variation from the Scope of Work will be considered by GSA, if the proposed change is within the construction budget limitations, meets the objectives for the project, and results in an improved design. The Contracting Officer and the COR/PM must approve all proposed changes to the Scope of Work.

2.1. PROJECT REQUIREMENTS

2.1.1. Base Bid

● Perform functional test of the building fire alarm system (minimum 10% of each type of initiating device and 100% of fire alarm notification zones) and document existing control components and arrangement, existing sequence of operations, existing network wiring arrangement, existing field NAC and SLC wiring arrangements, and any operational deficiencies identified at the time of the test.

● Upgrade existing base building fire alarm control equipment from the EST-3 to EST-4 platform. Control equipment to include (as required) all building CPUs, amplifiers, network cards, SLC cards, power supplies, notification power supplies, and annunciators.

● Provide listed surge protective device (SPD) on the power supply side of all fire alarm control panels in accordance with NFPA 70, National Electrical Code.

● Replace all addressable initiating devices no longer compatible with the EST-4 platform or that are no longer supported by the manufacturer. All compatible field devices shall remain in working order as part of the new total system upon completion of this project.

● Scope Writer Note for Alarm Co. Monitoring via POTs [Upgrade the fire alarm communicator (DACT) to an internal communicator if an external communicator is currently in use. The communicator shall utilize the current POTS phone lines for primary and alternate communication pathways. The communication format shall be 4+2 or similar and shall be general signals (Alarm, Trouble, Supervisory, etc.).] OR Scope Writer Note for [Upgrade the fire alarm communicator (DACT) to an internal communicator compatible with the EST equipment. The communicator shall utilize additional GSA IT approved using cellular and/or IP communication pathways. Two separate communication pathways are required. Communication format shall utilize contact-ID.]

● Provide a new fire alarm system printer.

● All fire alarm control equipment disconnect shall be labeled and breaker lock installed if not already provided. Each FACU shall be labeled with the breaker location information.

● All remote fire control panels (Non networked sub-systems) that are monitored by the base building FACU are not part of this upgrade and will remain as is, in service and monitored by the base building system.

● Contractor shall provide a set of NFPA 72 shop drawing documents for review and approval by the GSA regional fire protection engineer. See section 2.12.2 of this scope of work for additional shop drawing document requirements.

● Contractor shall provide a written work plan, schedule, and testing plan for the changeover of all active fire alarm equipment.

● Contractor shall be responsible for providing the services of a licensed third-party fire protection engineer to witness the fire alarm system acceptance testing performed in accordance with NFPA 72. See section 2.12.4 of this scope of work for additional third-party fire protection engineer requirements.

March 10, 2026 10 of 53

● Contractor shall be responsible for providing all building fire watches during the EST-3 to EST-4 equipment changeover while any system operations are impaired. The fire watch shall supplement all automatic input and output functions of the building fire alarm system, and shall be implemented in all areas of the building affected by the system impairment. Fire watch personnel shall be trained and staffed adequately to support all impaired system functions. Contractor shall provide a written fire watch plan and fire watch log for review and approval by the GSA regional fire protection engineer. It will be the contractor’s responsibility to limit the amount of time required for a fire watch. This includes, if necessary, working during nights, weekends, or holidays while risk to building occupants is decreased. The building fire alarm and emergency communication system must be maintained in proper working order throughout the duration of this project. At no time, except during the fire alarm control unit “change-over” shift is the building fire alarm system permitted to be not in full operation.

● The contractor may not work on an active fire alarm system or circuit without an approved fire alarm system outage. The contractor shall schedule with the GSA project manager and the building management in accordance with GSA fire alarm outage request procedures. All outages shall be approved by building management and the GSA NCR Regional Fire Protection Engineer. When the contractor works on the fire alarm circuits, the system must be taken out-of-service by management, and the system must be returned to "normal" before the electricians/contractors leave for the day. The Authority Having Jurisdiction (AHJ) is the GSA regional fire protection engineer. . Fire alarm programming changes are permitted only when confirmed acceptance testing is scheduled with the AHJ and/or the licensed third-party fire protection engineer. A fire alarm program change MUST be acceptance tested within 24 hours of the change.

● Contractor is responsible for hiring the services of O&M preferred service providers for all sprinkler system and elevator system work associated with the installation and testing of the building fire alarm system within this scope.

● All work shall be accomplished in accordance with the contract specifications (including GSA NCR’s fire alarm specification section) and drawings, as well as all local and/or national codes, regulations or standards applicable.

The Contractor is responsible to verify all fire alarm equipment quantities, type, and locations prior to bid.

All designs must be fully approved prior to the start of any construction.

2.2. PROJECT SITE REQUIREMENTS

2.2.1. Work Restrictions

The D/B Contractor shall survey the entire worksite and review existing documentation to be familiar with the existing conditions. This includes all areas of the building, structure, and site affected by the removal and demolition work, and alterations and new construction work, prior to initiation of design work.

During the construction period, the D/B Contractor shall have full use of the designated premises for construction operations, including full use of the indicated work site, limited only by the Government's right to perform work, or retain other contractors to perform work, on

March 10, 2026 11 of 53 portions of the project. The D/B Contractor shall limit the use of the premises to the work areas indicated, and to allow for Government occupancy and public use.

The building is to remain fully operational throughout the entirety of the project, with no disruption to tenant operations. All work areas must be cleaned at the end of every work day.

The work shall be sequenced to minimize disruption to building occupants, visitors, and maintenance activities. To the greatest extent feasible, demolition work should not take place until supplies are on hand to perform new work.

The D/B Contractor shall coordinate all work activities with the GSA Building Manager and the COR/PM to ensure that proper security and access arrangements are made without impact on the construction schedule.

2.2.2. Working Hours

2.2.2.1. Government Occupied Hours

Government personnel are scheduled to occupy the building during the following hours on weekdays, Monday through Friday, except for established Government Holidays, 6:00 AM to 6:00 PM.

2.2.2.2. Contractor's Working Hours

The following work shall be performed outside of Government Occupied Hours:

● Fire alarm testing

● Noisy and/or odor-producing work that may disrupt tenant operations in adjacent spaces.

Work accomplished outside of Government Occupied Hours shall be performed at no additional cost to the Government. The D/B Contractor shall submit a proposed schedule and gain the COR/PM approval at least 72 hours before proceeding with any work during Government Unoccupied Hours.

2.2.3. Loading Dock

Use of the existing loading dock facilities will be shared with Government activities on a first-come-first-served, wait-your-turn basis. The loading dock is available for the delivery of materials, tools, and supplies between the hours of 6 AM to 6 PM. Loading dock activities shall be coordinated with the GSA Building Manager a minimum of 72 hours in advance.

2.2.4. Parking

Limited parking is available on-site.

2.2.5. Staging and Storage

The D/B Contractor may be provided a staging area within the building, contingent upon GSA approval, and provided that its use will not interfere with operations of the Government.

No GSA employees will assist with unloading/loading of vehicles(s). The D/B Contractor

March 10, 2026 12 of 53 shall provide all personnel and equipment needed for unloading, moving, and assembling the materials.

2.2.6. Dumpster

Limited space is available on-site for a dumpster. Use of the existing building dumpster and trash bins is strictly prohibited.

2.2.7. Restrooms

Restrooms are available for use. Restrooms must be designated by the GSA Building Manager.

2.2.8. Existing Conditions

All Government property or systems displaced, altered, or damaged during the performance of this contract other than stated in this SOW shall be restored to its original condition at no cost to the Government. These repairs, if needed, shall be executed immediately when the Contractor is notified by the Contracting Officer that such repairs are required due to actions by the contractor or his/her subcontractors.

Maintenance of Existing equipment - Contractor shall collect information as needed from the Building manager or O&M staff for work to be done on any existing equipment / building systems for awareness and knowledge

Assessment - All due diligence must be performed to assess the existing conditions of the site, building, perimeter security and roadway access for the proposed project

Survey - A thorough survey must be done in order to understand the existing conditions and how the proposed project will impact the use , occupancy and surrounding areas.

2.3. STANDARDS AND CRITERIA DOCUMENTS

The D/B Contractor shall ensure that all design, work performed, and materials used, under this scope of work are in accordance with the guidelines, codes and specifications of the following associations and agencies. Any conflicts or ambiguities within, or among, the referenced Standards and Criteria Documents, or any deviations from requirements contained in the Standards and Criteria Documents, shall be reported to the COR/PM in writing, for determination as to applicability. The Contractor shall use the most recent versions of these documents issued at the time the RFP for the project is issued. In the event that there are conflicting requirements, the more stringent of the two shall be used.

2.3.1. GSA Requirements

● PBS Interim Core Building Standards including all applicable Standards, Criteria and Guides listed therein

March 10, 2026 13 of 53 https://www.gsa.gov/real-estate/design-and-construction/facilities-standards-for-the-public-buildings-service

● PBS P-120, Public Buildings Service Cost and Schedule Management Policy Requirements

● Implementation of Subject Matter Expert Review and Oversight Process for PBS Design, Construction, and Repair Projects

● PBS Building Code Official Authority for GSA Federal Buildings

● Architectural Barriers Act Accessibility Standard (ABAAS)

● PBS Order 3490.3 CHGE 1, “Security for Sensitive Building Information Related to

Federal Buildings, Grounds, or Property”, March 22, 2021

● PBS CAD Standards, March 10, 2021

● IAQ Guidelines for Occupied Buildings under Construction by SMACNA

● Occupational Safety and Health regulations for Construction and General industry; 29

CFR Parts 1926 and 1910

● Section 01546 – Safety and Health Specification (see attachments)

● International Code Council Codes (ICC)

● National Fire Protection Association (NFPA) National Fire Codes and Standards

● Egress issues shall meet NFPA 101 Life Safety Code

● ANSI NETA Standards

● OFM COBie Playbook (see attachments)

[https://insite.gsa.gov/organizations/public-buildings-service/design-and-construction/odc -resources/bim?term=bim]

● PBS EASi/EDMS File Naming Requirements (see attachments) [https://insite.gsa.gov/cdnstatic/PIB_18-02_Attach_6_File_Naming_2018_04_19.pdf]

● Section 889

● PBS Building Commissioning Guide (September 2020)

● Federal Metering Guidance (October 2022)

● National Historic Preservation Act of 1966, as amended, and its implementing regulations (36 CFR 800)

● [Building Preservation Plan (HBPP or BPP)] or [Historic Structure Report (HSR)] for the

[Building Name]

● Secretary of the Interior’s Standards for the Treatment of Historic Properties (36 CFR 68)

● ADM 1020.3A: GSA Procedures for Historic Properties (February 2024)

● National Park Service Preservation Tech Notes

● The Guiding Principles for Sustainable Federal Buildings [ONLY for New Construction and Major Renovations, for compliance with EISA 2007 § 433(a)]

● GSA Fine Art Collection Policies & Procedures 2024

● 40 CFR 61 National Emission Standards for Hazardous Air Pollutants

● 40 CFR 763 Asbestos

● 49 CFR 107 Hazardous Materials Program Procedures

● 49 CFR 172 Hazardous Materials Table, Special Provisions, Hazardous Materials

Communications, Emergency Response Information, and Training Requirements

● EPA Mold Remediation Guidelines, September 2008

March 10, 2026 14 of 53 https://www.gsa.gov/directives-library/p120-public-buildings-service-cost-and-schedule-management-policy-1?_gl=1*vr91na*_ga*MTQ5OTM1OTc1Ny4xNzUyNDkwMjQz*_ga_HBYXWFP794*czE3NzA2NTQ4NDgkbzYwJGcxJHQxNzcwNjU1OTc1JGo1NiRsMCRoMA..

https://www.gsa.gov/directives-library/p120-public-buildings-service-cost-and-schedule-management-policy-1?_gl=1*vr91na*_ga*MTQ5OTM1OTc1Ny4xNzUyNDkwMjQz*_ga_HBYXWFP794*czE3NzA2NTQ4NDgkbzYwJGcxJHQxNzcwNjU1OTc1JGo1NiRsMCRoMA..

https://drive.google.com/file/d/14gTs5hfjv6zNW5FxunnYYilvxFqdb39X/view https://drive.google.com/file/d/14gTs5hfjv6zNW5FxunnYYilvxFqdb39X/view https://drive.google.com/file/d/1sOiBGtvijRj4Gd0atIcdC2mNeFj-horR/view https://www.access-board.gov/aba/ https://www.gsa.gov/directives/files?file=2023-08%2FPBS_34903_CHGE_1_Secur_for_Sen_Build_Inform_Related_to_Fed_Build%2C_Grounds%2C_or_Property_%28Final_Word_3-22-21%29_CC044070_RV_3-30-21.pdf https://www.gsa.gov/directives/files?file=2023-08%2FPBS_34903_CHGE_1_Secur_for_Sen_Build_Inform_Related_to_Fed_Build%2C_Grounds%2C_or_Property_%28Final_Word_3-22-21%29_CC044070_RV_3-30-21.pdf https://www.gsa.gov/system/files/PBS_CAD_Standard-2021.pdf https://www.wbdg.org/FFC/GSA/gsa_commissioning_guide_2020.pdf https://www.energy.gov/sites/default/files/2022-10/federal-metering-guidance-2022.pdf https://www.achp.gov/sites/default/files/regulations/2017-02/regs-rev04.pdf https://www.achp.gov/sites/default/files/regulations/2017-02/regs-rev04.pdf https://www.nps.gov/tps/standards/four-treatments/36cfr68.pdf https://www.gsa.gov/directives/files?file=2024-02%2FCC048583%20ADM%201020.3A%20Procedures%20for%20Historic%20Properties.pdf https://www.nps.gov/tps/how-to-preserve/tech-notes.htm https://www.sustainability.gov/pdfs/guiding_principles_for_sustainable_federal_buildings.pdf https://www.gsa.gov/cdnstatic/Fine%20Arts%20Policies%20and%20Procedures%202017%20(1).pdf https://www.ecfr.gov/cgi-bin/text-idx?tpl=/ecfrbrowse/Title40/40cfr61_main_02.tpl https://www.ecfr.gov/cgi-bin/text-idx?tpl=/ecfrbrowse/Title40/40cfr763_main_02.tpl https://www.ecfr.gov/cgi-bin/text-idx?tpl=/ecfrbrowse/Title49/49cfr107_main_02.tpl https://www.ecfr.gov/cgi-bin/text-idx?tpl=/ecfrbrowse/Title49/49cfr172_main_02.tpl https://www.ecfr.gov/cgi-bin/text-idx?tpl=/ecfrbrowse/Title49/49cfr172_main_02.tpl https://www.epa.gov/sites/production/files/2014-08/documents/moldremediation.pdf https://www.ecfr.gov/cgi-bin/text-idx?tpl=/ecfrbrowse/Title49/49cfr172_main_02.tpl

[Editor: The following can be found at https://sites.google.com/gsa.gov/project-management-pm-hub/pm-support/pm-templates#h.z9twkwslm 0av]

● Section 02085 - Asbestos Abatement Procedures (see attachments)

● Section 02089 - Control of Polychlorinated Biphenyl Specification (see attachments)

● Section 02090 - Control of Lead Based Paint Specification (see attachments)

2.3.2. Building Management and Controls (BMC) and Federal Government Building Systems Network (BSN) Connection Requirements

[Editor: Include if the building has a BAS or BMC, or a network connected device(s) (e.g. air quality monitor, advanced metering, photovoltaic system, etc). Reach out to the Smart Buildings Specialist at NCRSmartBuildingsProgram@gsa.gov for requirements. The following documents in support of Section 2.16 and 2.17 of this SOW.]

● 7002.1 ADM GSA Smart Buildings (December 2021)

● Smart Buildings Implementation Guide Requirements (see attachments)

[https://insite.gsa.gov/cdnstatic/GSA%20Smart%20Buildings%20Implementation%20Gui de_v12.pdf]

● Smart Buildings Program Guide (see attachments) [https://insite.gsa.gov/cdnstatic/GSA%20Smart%20Buildings%20Program%20Guide_v1 1.pdf]

● GSA Data Normalization for Building Automation Systems (see attachments) [https://insite.gsa.gov/cdnstatic/GSA%20Data%20Normalization%20for%20Building%20 Automation%20Systems_v25.pdf]

● GSA National Capital Region Advanced Metering Systems (AMS) Guide, v1.1 (see attachments)

● Niagara NiCS Statement (see attachments)

● Security and Privacy Controls for Federal Information Systems and Organizations, NIST

800-53 Rev 5

● Guide to Industrial Control Systems (ICS) Security, NIST 800-82 rev 2

● GSA IT Building Technology Technical Reference Guide (BTTRG) v2.0 (see attachments) [https://www.gsa.gov/system/files/Building_Technologies_Technical_Reference_Guide_ %28BTTRG%29_Version_3.0_%28REDACTED_Final%29_May2024.pdf]

● Telecommunications Distribution Design Guide, Telecommunications and Infrastructure Standards, v8 (see attachments) [Editor: This applies to GSA Tenants only, [Library of Documentation, Guidance and Resources (gsa.gov)]]

● GSA Order 2100.1M GSA Information Technology (IT) Security Policy (see attachments) [https://insite.gsa.gov/directives-library/gsa-information-technology-it-security-policy-210 01m-cio?term=GSA%20Order%202100.1M%20GSA%20Information%20Technology%2 0(IT)%20Security%20Policy]

● IT Security Procedural Guide: Key Management CIO-IT Security-09-43, rev4 (see attachments)

March 10, 2026 15 of 53 https://sites.google.com/gsa.gov/project-management-pm-hub/pm-support/pm-templates#h.z9twkwslm0av https://sites.google.com/gsa.gov/project-management-pm-hub/pm-support/pm-templates#h.z9twkwslm0av mailto:NCRSmartBuildingsProgram@gsa.gov https://www.gsa.gov/directives/files?file=2024-03%2FCC044916_%20directive_ADM%207002.1%2C%20GSA%20Smart%20Buildings.pdf https://nvlpubs.nist.gov/nistpubs/SpecialPublications/NIST.SP.800-53r5.pdf https://nvlpubs.nist.gov/nistpubs/SpecialPublications/NIST.SP.800-53r5.pdf https://nvlpubs.nist.gov/nistpubs/SpecialPublications/NIST.SP.800-82r2.pdf https://insite.gsa.gov/organizations/staff-offices/office-of-gsa-it/office-of-public-buildings-services-ip/public-buildings-information-technology-services/building-and-energy-systems/library-of-documentation-guidance-and-resources https://insite.gsa.gov/organizations/staff-offices/office-of-gsa-it/office-of-public-buildings-services-ip/public-buildings-information-technology-services/building-and-energy-systems/library-of-documentation-guidance-and-resources

[https://insite.gsa.gov/cdnstatic/insite/Key_Management_%5BCIO_IT_Security_09-43_R ev_4%5D_04-09-2020docx.pdf]

● IT Security Procedural Guide: Building Monitoring and Control (BMC) Systems Security Assessment Process CIO-IT Security-16-76, rev2, October 13, 2020 (see attachments) [https://www.gsa.gov/cdnstatic/BAS_Security_Assessment_Process_%5BCIO_IT_Securi ty_16-76_Rev_1%5D_08-29-2018.pdf]

● IT Security Procedural Guide: Managing Enterprise Cybersecurity Risk CIO-IT Security-06-30, rev19, April 15, 2021 (see attachments) [https://insite.gsa.gov/cdnstatic/insite/Managing_Enterprise_Cybersecurity_Risk_%5BCI O_IT_Security_06-30_Rev_19%5D_04-15-2021_%281%29docx.pdf]

● 2180.2 CIO GSA Rules of Behavior for Handling Personally Identifiable Information (PII), October 8, 2019 (see attachments) [https://insite.gsa.gov/directives-library/gsa-rules-of-behavior-for-handling-personally-ide ntifiable-information-pii-21802-cio?term=2180.2%20CIO]

● 2181.1 ADM Homeland Security Presidential Directive-12, Personal Identity Verification and Credentialing, and Background Investigations for Contractors, March 18, 2020 (see attachments) [https://insite.gsa.gov/directives-library/homeland-security-presidential-directive12-perso nal-identity-verification-and-credentialing-and-background-investigations-for-contractors- 21811-adm]

● 2100.2C CIO P GSA Wireless Local Area Network (LAN) Security guide (see attachments) [https://insite.gsa.gov/directives-library/gsa-wireless-local-area-network-wlan-security-21 002c-cio?term=2100.2BCCIO%20P%20GSA%20Wireless%20Local%20Area%20Netwo rk%20(LAN)%20Security%20guide]

● GSA IT Policy Requirements Guide 12-2018 (see attachments) [https://insite.gsa.gov/cdnstatic/CIO%2012-2018_%20IT%20Policy%20Requirements%2 0Guide.pdf]

● GSA IT Security Procedural Guide: Security and Privacy Requirements for IT Acquisition Efforts CIO-IT Security-09-48, Rev6, April 15, 2021 (see attachments) [https://insite.gsa.govaaaaaaa/cdnstatic/insite/Security_and_Privacy_Requirements_for_ IT_Acquisition_Efforts_%5BCIO_IT_Security_09-48_Rev_6%5D_04-15-202.pdf]

● GSA IT Security Procedural Guide: SSL TLS Implementation Guide - CIO-IT Security 14-69, Rev3, April 6, 2021 (see attachments) [https://insite.gsa.gov/cdnstatic/insite/SSL_TLS_Implementation_%5BCIO_IT_Security_ 14-69_Rev_6%5D_04-06-2021docx.pdf]

● PBS Technology Policy (see attachments) [https://drive.google.com/file/d/0B-gXxLkFOhnKaGo4MjZrREg0TFBZMXhYUXZ0VXRTN XR1d253/view?resourcekey=0-Kval0KWoJrtF6oDku9HY3A]

March 10, 2026 16 of 53

2.4. CUTTING & PATCHING REQUIREMENTS

Destructive testing [is / is not] permitted to expose concealed conditions during the Design Phase.

The D/B Contractor shall replace, patch, and repair material and surfaces cut or damaged by methods and with materials in such a manner as not to void any existing warranties.

All substrates must be inspected and defects repaired prior to installing new material or finish. All replacement and new materials shall match the existing in material, dimensions, color and finish. All material selections and/or mock-ups need to be reviewed and accepted by the COR/PM and Tenant Agency prior to ordering.

2.4.1. Structural Systems

Do not cut structural beams or major structural elements without the written review and approval of a Licensed Structural Engineer. Additionally, the COR/PM shall obtain review and acceptance from GSA’s OE ’s (Office of Engineering) structural engineer and A/E’s structural engineer. Prior to cutting and/or drilling through any structural member, the Contractor shall conduct ground penetrating radar, or similar type of investigative measure to prevent cutting concealed material. Submit structural calculations sealed by a Licensed Structural Engineer to the COR/PM concurrently for acceptance.

Do not cut and patch structural elements in a manner that would change their load-carrying capacity or load-deflection ratio.

2.4.2. Operational Systems

The D/B Contractor shall not cut and patch operating elements, safety related systems, or related components in a manner that would result in reducing their capacity to perform as intended, or that would result in increased maintenance, or decreased operational life or safety.

2.4.3. Visual / Finishes

The D/B Contractor shall not cut and patch construction exposed on the exterior, or in occupied spaces, in a manner that would, in GSA's opinion, reduce the building's aesthetic qualities, or that would result in visual evidence of cutting and patching. The Contractor shall remove and replace construction that is cut and patched in a visually unsatisfactorily manner.

Patched areas shall be neatly trimmed prior to patching. Feather all patches to provide a complete and finished surface. Paint all exposed work provided under the contract including all patched areas, and exposed areas uncovered during demolition, to provide a complete and finished project. Paint patched areas and surrounding areas to the nearest break in wall surface, or other building line to provide a neat and finished appearance. All paint shall match adjacent painted surfaces. Protect all surrounding areas including fixtures, furniture, floors and accessories from paint splatter and droppings. Clean and restore all areas splashed with paint.

March 10, 2026 17 of 53

Any work related to removing equipment, brackets, supports, etc. that leaves holes or damaged surfaces on the floor, walls, and ceilings, shall be patched with the same adjacent material and finish.

2.5. NATIONAL HISTORIC PRESERVATION ACT (NHPA) REQUIREMENTS

This building is listed in the National Register of Historic Places. The D/B Contractor shall coordinate design and construction documents with GSA Preservation (GSA HP). GSA HP will provide guidance on preservation zones and appropriate treatments. The resulting proposed design/preferred alternative will be the basis for the Section 106 consultation with the DC State Historic Preservation Office (SHPO), if required.

● Recommendations shall be in compliance with the Secretary of the Interior's Standards and Guidelines for the Treatment of Historic Buildings.

● All recommendations shall be reviewed by GSA HP. GSA HP will review all submissions in their entirety for impact on restoration, rehabilitation and renovation zones as defined in the HSR.

2.6. NATIONAL ENVIRONMENTAL POLICY ACT (NEPA) REQUIREMENTS

[Editor: By Federal Law, National Environmental Policy Act of 1969 applies to all GSA actions and will require analysis and documentation pursuant to the PBS NEPA Desk Guide, October 1999. Project Managers should coordinate with the Regional Environmental Quality Advisor to complete and document the appropriate NEPA analysis, prior to contract award.]

NEPA analysis will need to be completed. GSA will review each design submission to inform National Environmental Policy Act (NEPA) Compliance. All National Historic Preservation Act (NHPA) compliance actions, if necessary, must be completed before NEPA analysis is finalized. Project implementation will not begin until GSA completes NEPA compliance actions.

[or]

Pursuant to paragraph 5.3 of the PBS NEPA Desk Guide (October 1999), this project is an automatic CATEX and requires no checklist.

2.7. U.S. COMMISSION OF FINE ARTS (CFA) REVIEW REQUIREMENTS

The CFA is a federal agency with authority to review and comment on federal projects in the District of Columbia that propose exterior alteration to buildings or sites. CFA’s purview is the design of buildings and sites, or their proposed alteration. While CFA does not require completion of NEPA and NHPA for submission, most GSA projects requiring CFA review also require NCPC review; therefore, completion of NEPA and NHPA is necessary regardless.

CFA’s schedule of meetings, submission deadlines, and project submission requirements are found on the agency’s website https://www.cfa.gov/project-review/government.

CFA staff may advise preliminary consultation for complex projects. The D/B Contractor shall make key personnel available to accompany the COR/PM and OE (Office of Engineering) representatives for consultations with CFA, as necessary.

March 10, 2026 18 of 53 https://www.cfa.gov/project-review/government

The CFA submission materials generally are the same materials used for the NCPC submission. The materials are to be 508 Compliant digital file(s) or transmitted through a secure File Transfer Protocol (FTP) site such that materials can be easily downloaded in PDF format if the file is too large. There's a 150 MB per file size limit for submissions accepting PDF and/or Zip files.

Usually, with support from the D/B Contractor, OE is able to coordinate submission of project materials to both NCPC and CFA so that the review times for each agency run concurrently.

The deadlines for both agencies are usually at the end of each month. To best support GSA’s project submission, the D/B Contractor shall prepare the submission materials to allow for early project consultation to streamline the approval process as well as have the most accurate estimate of project schedule.

2.8. External Review Agencies - Local, State, other Federal

This project may be subject to coordination, referral, and/or review submission by external review agencies such as Local, State, and other Federal agencies. The D/B Contractor should be familiar with the submission requirements of the applicable review agencies.

Additionally, the contractor shall be responsible for providing all materials and incorporating submission review timelines into the overall project schedule as necessary.

2.9. FINE ARTS REQUIREMENTS

It is not anticipated that Fine Arts will be disturbed during work activities. The D/B Contractor shall protect Fine Arts per the Fine Art Protection Work Plan and coordinate with SME in OE (Office of Engineering).

2.10. ACCESSIBILITY REQUIREMENTS

Architectural Barriers Act Accessibility Standard (ABAAS) is mandatory for all GSA projects.

If local accessibility standards exist, the D/B Contractor shall follow the most stringent requirements between the local standards and ABAAS.

The building ABAAS accessibility shall be maintained at all times.

2.11. SAFETY AND OCCUPATIONAL HEALTH REQUIREMENTS

The D/B Contractor and all subcontractors shall comply with the safety and health standards and guidelines referenced in Section 2.3.1 as well as the following requirements:

GSA National Safety and Health are the authority having jurisdiction (AHJ) for all safety and health concerns at all GSA owned facilities.

The D/B Contractor shall provide a site-specific Safety and Health Plan that includes job hazard analysis, bloodborne pathogens, emergency response, personal protective equipment (PPE) requirements, hazard mitigation, hazardous energy control (lock out/tag out), arc flash requirements, hazardous noise, confined space, crane plans, fall protection, chemicals being used onsite, trainings/ certification, and when safety toolbox meetings will occur.

March 10, 2026 19 of 53

The D/B Contractor shall provide Safety Data Sheets (SDSs) for all substances/ materials to be used in the performance of this contract to the onsite O&M shop. The Contractor will ensure all personnel wear the appropriate personal protective equipment required by the SDSs.

The D/B Contractor shall ensure that all hazards at the end of the workday/ project end are mitigated to ensure that the site is not left in an unsafe condition (e.g., fall, confined space, excavation, chemicals, walkways).

The D/B Contractor shall ensure a first aid kit is available at the site and that all employee injuries and incidents are reported to the COR immediately for reporting to GSA Safety and Health.

The D/B Contractor shall ensure that all hazardous energy sources are locked and tagged out, arc flash procedures are followed to include all PPE, lock out/ tag out (LOTO), labeling, demarcation of zones, and all 1-line drawings are updated. All new electrical must be updated on the inside electrical panel door, all wires are run correctly, and wires are labeled.

All equipment and material that is owned by the contractor/subcontractor must be labeled with the contractor's contact name and cell number for rapid identification during inspections or emergency situations.

The D/B Contractor shall only use extension cords with three (3) prongs (ground) and only use them for temporary power on a daily basis. All extension cords will be inspected before use for damage, frayed electrical, exposed wires, and must dispose of all damaged extension cords. Damaged extension cords cannot be repaired with electrical tape and must be replaced with new to prevent electrical shock hazards and fire. Extension cords cannot be plugged into outlets that have appliances or essential equipment plugged into them. The GFCI extension cord adaptors can be used to prevent tripping of electrical services.

The D/B Contractor shall not store chemicals, equipment, debris, or trash in or around electrical rooms/ panels, in hallways, stairwells, on stairs, or in authorized spaces at any time.

The D/B Contractor shall not permit any contractors/ employees from entering a confined space, accessing the roof top areas without the proper clearance, fall protection, RF Radiation hazard areas, or any other area deemed unsafe by the COR or GSA National Safety and Occupational Health.

The D/B Contractor will ensure compliance with all confined spaces with attention to the entry of permit required confined spaces. The contractor is responsible for working with the O&M contractor and building manager for compliance with the site confined space program.

The D/B Contractor shall at any time be able to submit inspection documentation and training documentation for its employees to the COR and GSA National Safety and Occupational Health personnel.

All accidents must be reported to the COR immediately and any injuries to personnel must be reported to the COR and National Safety and Health immediately with updates hourly until the situation is addressed. A written report shall be submitted within 24 hours of the

March 10, 2026 20 of 53 injury to the COR and National Safety and Health. Incidents without injury must submit a written report to the COR within 24 hours.

2.12. FIRE PROTECTION AND LIFE SAFETY REQUIREMENTS

[Editor: Project Manager must consult with the National fire protection engineer to determine the potential scope associated with fire protection and life safety systems and elements. The regional fire protection engineer shall also identify any fire protection or life safety specialties required for the project.]

GSA’s Fire Protection Engineers are the authority having jurisdiction (AHJ) for all GSA owned facilities.

2.12.1. Egress/Life Safety

● D/B Contractor’s fire protection engineer shall provide code analysis using the latest requirements of the International Building Code, NFPA codes and standards, and any other applicable requirements. Code analysis shall include, at a minimum, applicable construction codes and standards, use and occupancy identification, construction type, height and area requirements, fire resistant rated construction requirements, vertical opening separation requirements, interior finishes, fire protection systems, life safety systems, and egress requirements. The technical egress requirements of NFPA 101 shall be used in lieu of the International Building Code.

● D/B Contractor’s fire protection engineer shall provide occupant load and egress capacity calculations.

● Demonstrate compliance with NFPA 101 requirements for illuminated exit marking signage and emergency lighting.

● Demonstrate compliance with IBC requirements for fire resistant rated partitions, walls, and interior finishes.

● Demonstrate compliance with NFPA locking and exit door hardware requirements.

● Demonstrate compliance with the safeguarding construction and alteration operations requirements of NFPA 241. Construction activities for tenant alterations or building modernizations shall be separated from the remainder of an occupied building with walls having a minimum 1-hr fire resistant rating with 45-min opening protectives, or shall be provided with an active sprinkler system and continuous smoke partitions throughout the duration of construction. Construction phasing and/or separation walls shall be located in such a manner to maintain an NFPA 101 compliant egress arrangement for the remainder of the occupied building (dead-ends, common paths of travel, travel distances, etc.).

2.12.2. Fire Protection Systems

● Modify existing sprinkler systems in accordance with the latest requirements of the International Building Code, and NFPA 13, Standard for the Installation of Sprinkler Systems. Sprinkler installation shall be performed by a licensed sprinkler contractor with a minimum of five years experience in the installation of sprinkler systems.

● Design of sprinkler modifications shall be performed by D/B Contractor’s fire protection engineer. Locations of required sprinkler system modifications and design criteria shall

March 10, 2026 21 of…