SOW Fire Damage Restoration.docx

DOCX document 23 KB Posted

Attached to
Fire Damage Restoration
Solicitation number
W50S8N20Q0003
Issued by

View the file

Other files

File Type Posted
SOW_Amendment 1 Fire Damage Restoration.docx DOCX document
B644_20200305.pdf PDF
SF 30 Amend 0001.pdf PDF
Wage Determination.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

Maintain (Fire Restoration) Fire House, Building 644 Project No. HAAW202009

174th Attack Wing

Hancock Field ANG Base 6001 East Molloy Road Syracuse, New York 13211

27 February 2020

TABLE OF CONTENTS

1. SCOPE OF WORK

2. AREA OF WORK

3. DESCRIPTION OF WORK

4. PERIOD OF PERFORMANCE

5. MATERIALS & EQUIPMENT

6. GENERAL CONDITIONS

7. GOVERNMENT WORKING HOURS

8. DIFFERING SITE CONDITIONS

9. UTILITIES

10. DISPOSAL OF MATERIALS AND CLEANUP

11. MATERIAL & EQUIPMENT ACCOUNTABILITY

12. FIRE & SECURITY

13. ENVIRONMENTAL

14. ACRONYMS & ABBREVIATIONS

1. SCOPE OF WORK:

The contractor shall provide all labor, personnel, equipment, tools, materials, supervision, transportation, quality control, and other items and services necessary to complete the work as described in this Statement of Work (SOW), the contract drawings, and specifications.

2. AREA OF WORK:

Work location is the 174th Attack Wing (174 ATKW), 6001 East Molloy Road, Syracuse, New York 13211 on Hancock Field Air National Guard Base. Contractor shall work only in the areas designated by the Contracting Officer Representative (COR). The primary area of work is Building 644, the Fire House.

3. DESCRIPTION OF WORK:

3.1. The work specified by this section consists of furnishing all labor, equipment, tools, appliances, transportation, materials, and quality control reports required to provide fire and smoke damage restoration services for Building 644.

3.2. Provide industry standard restoration services for:

3.2.1. Approximately 8,500 SF of horizontal surfaces

3.2.2. Approximately 20,000 SF of vertical surfaces

3.2.3. Approximately 40 pieces of furniture

3.3. In Room 112 (Apparatus Bays), only low emulsification or quick separation type soaps that are compatible with oil water separators are authorized. Submit material selection for approval before use.

3.4. Scope of work does not include Mechanical Room 108 and Electrical Room 109.

4. PERIOD OF PERFORMANCE:

Work must be completed in 21 days to support the duties of 174 ATKW personnel and safety of the mission.

5. MATERIALS & EQUIPMENT:

5.1. Construction materials must meet relevant code specifications and the New York State building code for northern construction.

5.2. SUBMITTALS: The contractor shall submit to the Contracting Officer (CO) for approval all items listed on attached Material Submittal Schedule (AF Form 66) within 10 calendar days of the notice to proceed (NTP). Alternatively, the contractor may within 10 calendar days of the NTP, provide the CO with a schedule indicating when each material submittal shall be submitted for approval.

5.2.1. Use an AF Form 3000 for transmitting material submittals.

5.2.2. Ensure that any disapproved submittal will not impact the approved project execution schedule, as a disapproved submittal shall not be considered grounds for a time extension.

5.2.3. Allow for a minimum of 5 working days for the Government’s processing of submittals.

5.2.4. The contractor shall not order, deliver, nor install any materials and/or equipment without CO’s approval or remove any materials on site that have not been properly approved.

6. GENERAL CONDITIONS:

6.1. Contractor and all personnel shall comply with the Standard Industry of New York State Codes and the Unified Facilities Criteria. Contractor shall work within the time line specified by COR.

6.2. All work performed under this SOW shall be conducted in accordance with all applicable state and federal laws and regulations, Department of Defense (DoD) policies and regulations including the Unified Facilities Criteria (UFC).

6.3. Contractor shall field verify all site conditions, quantities, measurements, and project requirements.

6.4. Contractor shall protect and barricade all work areas at all times to protect workers, base personnel, and the public from injury.

6.5. Contractor shall protect all structures, utilities, vegetation, sidewalks and vehicles from damage at all times. Replace all damaged materials with new materials to the satisfaction of the Government, at no additional cost to the Government.

6.6. SCHEDULE: The schedule is the basis for determining contract earnings during each update period and therefore the amount of each progress payment.

6.6.1. No later than 10 calendar days after the contract award, the contractor shall provide to the COR a Contract Progress Schedule (AF Form 3064 or other format agreed to by COR).

6.6.2. The contractor shall provide to the COR a Contract Progress Report (AF Form 3065 or other format agreed to by COR) every 2 weeks after the NTP (or other time period agreed to by COR).

6.6.3. In the event that the CO directs schedule revisions and those revisions have not been included in subsequent Project Schedule revisions or updates, the CO may withhold 10 percent of pay request amounts from each payment period until such revisions to the project schedule have been made.

7. DIFFERING SITE CONDITIONS:

Bring any unforeseen project conditions to the attention of the CO immediately. Differing site conditions, which may alter the scope of work, shall be approved by the CO prior to such work being performed.

8. GOVERNMENT WORKING HOURS:

Work hours shall be Monday thru Friday 0700-1530 hours, with the exception of Federal holidays. Contractor must have prior, written CO approval to work outside these hours.

9. UTILITIES:

9.1. The Government shall provide at no cost to the contractor reasonable amounts of water and electricity to support the contract. Hook up will be to existing outlets and will be the contractor’s responsibility.

9.2. Water outlets without a suitable backflow prevention device already installed must have one provided by the contractor prior to use. The backflow prevention device must be submitted to the CO for approval before installation or use. Section 5 submittal instructions apply to backflow prevention device approvals.

10. DISPOSAL OF MATERIALS AND CLEANUP:

10.1. Contractor shall clean up after each work period and dispose of all debris at the close of each day.

10.2. The contractor shall not use any government disposal bins, dumpsters or trash receptacles for any reason at any time unless otherwise specified in this SOW. The contractor shall provide appropriate disposal bins and/or trash receptacles. Approval of disposal bins/trash receptacles location(s) shall be coordinated through the COR.

10.3. The contractor shall not allow debris to leave the work area risking damage to aircraft engines and other government property.

10.4. All debris or trash shall be disposed of off base. All demolition debris shall be disposed of at a permitted landfill, with landfill authorization, unless other arrangements have been coordinated through the Environmental Management Office (EMO). Contractor shall coordinate with the base EMO prior to disposing any materials off base.

10.5. Provide documentation of all disposal and recycling of solid waste, such as landfill receipts; waste manifests, or weight tickets from the landfill that accepts the debris.

11. MATERIAL & EQUIPMENT ACCOUNTABILITY:

Notify the COR prior to delivery of any material or equipment to the site. The contractor shall ensure someone is available to receive delivered materials and able to store them safely in an area to be coordinated with the COR. Any materials delivered without prior coordination and without having someone to take receipt shall not be accepted and turned away.

12. FIRE & SECURITY:

12.1. Security Forces shall monitor the incoming and outgoing of work personnel during the duration of the project. All deliveries shall be coordinated with the COR to arrange for their entrance onto the base.

12.2. The contractor’s foreman or project manager shall attend a security briefing prior to the start of work.

12.3. All contractor (and sub-contractor) personnel shall have a minimum of 1 form of government-issued photo identification with them at all times.

12.4. If welding, torching, or any other high-temperature activities are required to complete this project, a burn permit must be obtained first from the Base Fire Department.

13. ENVIRONMENTAL:

13.1. The contractor’s foreman or project manager shall receive an environmental management system briefing at or before the pre-construction meeting.

13.2. HAZARDOUS MATERIALS:

13.2.1. A hazardous material (HM) is any item that is:

13.2.1.1. a health hazard or physical hazard as defined in 29 CFR 1910.1200(c) or

13.2.1.2. regulated in its disposal by the Environmental Protection Agency in 40 CFR or

13.2.1.3. hazardous as defined by Department of Transportation regulation in 49 CFR or

13.2.1.4. hazardous as defined by the Dangerous Goods Regulations of the International Air Transportation Association

13.2.2. If HM is required to complete this contract, the contractor must create a hazardous materials storage plan and account for HM quantities in accordance with the Hancock Field Hazardous Waste Management Plan. Submit the hazardous materials storage plan following instructions in Section 5.

14. ACRONYMS & ABBREVIATIONS

AFAir Force
ANGAir National Guard
ATKWAttack Wing
CFRCode of Federal Regulations
COContracting Officer
CORContracting Officer Representative
DoDDepartment of Defense
EMOEnvironmental Management Office
HMHazardous Material
NTPNotice to Proceed
O&MOperations and Maintenance
SOWStatement of Work
UFCUnified Facilities Criteria

File details come from the government source that posted it. Updated .