SOW_Final.docx

DOCX document 31 KB Posted

Attached to
Whole Body Radiation Contamination Monitor
Solicitation number
1333ND24QNB610660
Issued by

About this file

This document is a Statement of Work (SOW) for the procurement of two (2) whole body contamination monitors and associated software by the National Institute of Standards and Technology (NIST) Center for Neutron Research (NCNR).

The purpose of this procurement is to replace two older whole body contamination monitors used for radiation detection and safety at the NCNR facility. The requirements include providing brand name or equal Argos 5PAB whole body contamination monitors, with onsite installation, calibration, and user training. The monitors must be able to detect alpha and beta radioactive contamination, have integrated dosimeter readers, and include a frisking probe. The contractor must also provide the associated control software, which must allow remote monitoring and alarm notifications. Delivery is required within 120 days after award, and the software installation by November 30, 2024. A one-year warranty is required, including onsite support and software upgrades. NIST will perform operational testing within 30 days of delivery, with the contractor making any necessary repairs or adjustments. Payment will be made in full upon final acceptance of the delivered and tested system.

View the file

Other files

File Type Posted
1333ND24QNB610660 RFQ.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

Two (2) Whole body contamination monitors I. Background The National Institute of Standards and Technology (NIST), NCNR Health Physics Division is responsible for radiation protection and regulatory compliance matters for NIST’s radioactive materials license at the NIST Gaithersburg, NIST Center for Neutron Research (NCNR). As part of managing the radiation safety program, NCNR Health Physics is obligated to perform timely measurements of sample media during reactor and laboratory operations to ensure a safe environment and to provide test data accurately and quickly. To meet this requirement NCNR requires persons leaving specific areas of the NCNR need to be monitored for radioactive material. This can be performed by using whole body contamination monitors at the facility exits and requiring persons to use these when leaving the area. The NCNR currently has 3 of these whole-body contamination monitors, two of which are more than 15 years old. This purchase is to replace two of the older monitors.

II. Purpose The purpose of this procurement is to have the contractor provide two (2) Brand Name or Equal Argos 5PAB whole body contamination monitors along with associated equipment.

III. Requirements

Submissions with regularly sold “Off the Shelf” and “Turn key” systems are required. Onsite installation, calibration, and user training is required. All items must be new. Used or remanufactured equipment will not be considered for award. Experimental, prototype, or custom items will not be considered. The use of “gray market” components not authorized for sale in the U.S. by the proposer is not acceptable.

Line Item: Brand Name or Equal Argos 5PAB Whole Body Contamination Monitors Description: two (2) whole body contamination monitors and two (2) software program with computers to the NCNR.

Quantity: 2

1. Whole body contamination monitor type:

a. The personnel contamination monitor (PCM) shall be a microcomputer based, stand-and-count mode contamination monitor.

b. The PCM shall be able to detect the presence of alpha and beta emitting radioactive contamination using gasless plastic scintillation detectors.

c. The plastic scintillator detectors should be a minimum of 570 cm2 and a maximum of 600 cm2.

d. The whole-body count shall be accomplished in a two-step process whereby the user first positions himself to count 1/2 the body surfaces, then upon completion of this first count, the user repositions their self to count the remaining 1/2 of the body surfaces.

e. As a minimum, the following areas shall be monitored in the two step count:

i. head, face, bottom of feet, upper and lower arms, hands, upper trunk, lower trunk, sides of the body, thighs, and calves.

f. The unit also need to include a frisking probe as part of the unit with audible and visual alarming capabilities for checking tools, equipment, wheels on carts, and other items. The frisker should be alpha/beta smart probe.

g. The unit shall have an integrated electronic dosimeter reader. Capable of reading DMC dosimeters.

h. The contractor shall provide any associated manuals (2 hard copies and electronic) and/or accessories required to operate the systems.

i. The contractor shall set up the instrumentation at the NCNR.

2. User interface:

a. The PCM shall automatically sense the presence of the user and start the counting sequence.

b. The unit shall incorporate sensors/switches to ensure the user is in the correct monitoring position to optimize detection geometry.

c. Manual buttons or switches that must be pushed by the user will not satisfy this requirement.

d. At a minimum hand and foot position sensors are required.

e. The PCM requires the use of body position sensors.

f. The instrument shall incorporate a voice option to step personnel through the counting process. At a minimum this must help the user obtain the correct counting position, inform the user that the count has been completed, and inform the user whether they are clean or contaminated.

g. If the subject is contaminated, the instrument shall also provide a visual indication showing which detector(s) has alarmed.

h. The PCM shall also allow for an optional automatic hard copy printout when the count indicates contamination indicating the output count rates and detector(s) that alarmed.

i. The instrument shall have web remote installed and capable of communicating with Horizon Supervisory System software.

3. Instrument control system:

a. The PCM shall be computer based including a keyboard, Ethernet connection port, 2 USB ports, and a port for an additional monitor.

b. The PCM shall include an integrated display.

c. The PCM shall be able to be controlled and monitored with the software program included with this package.

d. The computer and all detector electronics shall be enclosed and mounted inside the cabinet so that there are minimal outside cables and connections except what is required for printers and IO devices.

4. System operation:

a. The PCM shall monitor the background using a rolling average.

b. The instrument shall compare the most recent background count to the rolling average.

c. The PCM shall perform channel summation for adjacent detectors. It shall compare the count results for each detector and summed channels to the background to determine if alarm points have been exceeded.

d. Alarms shall be visual, audible, and displayed through the software package.

e. The PCM will go out of service if there is a failure of any of the detectors, if any of the detectors become contaminated, or if there is a high background detected.

f. The unit shall return to service when background or fault conditions return to normal.

g. The user shall be able to disable a specific detector in order to place the PCM back into service as long as the other detectors are able to compensate for the missing detector.

h. The PCM needs to have a nonvolatile memory to preserve system parameters.

i. The system shall be able to produce data file reports and hard copy printouts to document QA testing and trends such as background and efficiency.

5. Setup and Calibration:

The units shall include a method for entry and selection of all operating and test parameters and shown on a video display. At a minimum this must include the following:

a. Adjustment and optimization of the high voltage (ie. it shall be computer controlled).

b. Calibration and maintenance utilities to permit the user to view background count rates, perform efficiency determinations, and generate calibration reports.

c. User selectable parameters for count time, false alarm rate, alarm confidence levels, and alarm points that can be different for each detector.

d. Count time must be selectable as either fixed or variable depending on the sensitivity desired.

e. A key switch or password shall prevent unauthorized entry to the test mode. If a key is used a minimum of 5 keys shall be supplied.

f. The setup functions must be available in the controlling program included with this package.

g. The PCM shall have a mode available to enable one person to use a source to alarm the detectors without the aid of any special holders or equipment.

h. The PCM shall be able to perform radon rejection.

6. Detector Specifications:

a. The detectors for the PCM shall be gasless thin plastic scintillators used for alpha and beta detection.

b. The detectors shall be protected by a steel mesh screen that is at least 75% open.

c. There shall be a minimum of 20 detectors. In addition to these detectors, the whole body PCM shall have a separate detection system designed for gamma radiation.

d. The 4-π detector efficiency, with protective screen in place, shall be greater than or equal to 10% for Pu-239 (alpha) and greater than or equal to 20% for Cl-36 (beta) for the hand or body detectors. The 4-π detector efficiency for the units with the gamma detection system shall be greater than or equal to 15% for Co-60.

e. The PCMs shall be able to detect 5000 dpm beta radiation in a 20 uR/hr background field in less than 12 seconds.

7. Physical Specifications:

a. The unit shall be operational with ambient temperature in the range of 50F to 100F.

b. The unit shall be operational with an ambient relative humidity range of 10 to 85 percent.

c. The unit shall be operable with a nominal power supply of 110-120 VAC, 60 Hz,

d. The unit shall be equipped with a power line noise suppressor and surge protector.

e. The unit shall be equipped with a power line noise suppressor and surge protector.

f. With the rear of the unit against a straight wall, it shall be possible to open any access panels to interior components without requiring movement of the unit, and it shall be possible to perform any routine, preventive or normal corrective maintenance without requiring movement of the unit.

8. Software:

a. Must be able to connect to the personnel contamination monitors provided in this contract via an internet connection.

b. Must be viewable through the internet by at least two individuals at once.

c. Must be able to connect to at least 15 devices.

d. Must be able to alert anyone via text message, email, and someone connected to the software program of an alarm or a failure on any of the connected devices.

e. Must be able to change settings for the connected devices such as the alarm set points.

f. Must be able to view logs for the connected devices such as the background reading for individual detectors.

g. Must be able to view the current status of the instrument such as the background reading, the efficiency, and any errors for each detector of the contamination monitors.

h. Must be able to view logs of alarms, errors, and other instrument values.

i. Must be able to view real time instrument data.

j. The computer must be at least Windows 10 with a 2TB hard drive and 32 GB of memory.

IV. Delivery and Installation Deliverable Two (2): Delivery shall be FOB DESTINATION and delivery will be made within 120 days after award receipt. The installation and setup of the software program shall be performed no later than November 30th 2024.

FOB Destination means: The contractor shall pack and mark the shipment in conformance with carrier requirements, deliver the shipment in good order and condition to the point of delivery specified in the purchase order, be responsible for any loss of and/or damage to the goods occurring before receipt and acceptance of the shipment by the consignee at the delivery point specified in the purchase order; and pay all charges to the specified point of delivery.

The contractor shall deliver both PCMs to:

The National Institute of Standards and Technology Attention: NCNR Health Physics, Avery Walton 100 Bureau Drive, Building 235 Room B1116 Gaithersburg, MD 20899-6100 V. Warranty The PCMs, software, computer server, including all components, shall be warranted for a period of not less than 365 days after final acceptance of the equipment by the Government. The warranty period shall commence only after the equipment has passed the performance tests and evaluations set forth by NIST staff. All parts, labor, travel, and other expenses required to repair any equipment shall be borne by the Contractor, and all repairs performed at no cost to the Government. Any repairs made by the Contractor to resolve any equipment problems discovered during the warranty period shall be warranted for an additional 365 days.Warranty shall include the following:

Warranty shall include onsite support if required. This technical support shall include any required software upgrades or patches without any additional cost.

VI. Performance/Operational Tests NIST staff will verify all functions are operational within 30 days of delivery. The Government reserves the right to perform such performance tests and evaluations as deemed appropriate by the Government to verify specified machine performance in accordance with the standards listed in this document within 30 days after final installation. Such tests and evaluations, if performed, will be conducted within the environment that the machine is to be operated. The Contractor has the right to be present during the tests and evaluations, if performed, at the Contractor’s expense.

VII. Failure of Testing/Evaluation The Contractor may make reasonable repairs and adjustments to the equipment should it fail any testing and evaluations. Repairs, adjustments, or modifications of the equipment shall only be made with the Government’s approval. The 30-day evaluation period mentioned in Section VI will restart after these repairs, adjustments, or modifications. The Government reserves the right to duplicate the tests specified above to determine acceptance.

VIII. Payment Schedule The Contractor shall be paid, in accordance with Net 30-day payment terms, upon receipt and acceptance of a proper invoice, in accordance with the following schedule:

1.100% after receipt and acceptance by the TPOC of fully delivered system.
2.The Government anticipates inspection will occur upon:
a.After the testing procedures set forth in this document have been complete

NOTE: Partial shipments and partial invoices will not be accepted, unless other-wise requested and accepted by the Contracting Officer prior to award offer. Proposed payment schedules shall be submitted with vendor’s response to the RFQ for consideration.

IX. Place of Performance

Not applicable for the manufacturing of the PCMs. The installation and setup shall take place at the NIST Gaithersburg campus, NCNR building 235.

X. Government Responsibilities

The government shall work with the vendor to coordinate a mutually agreeable time for the delivery and setup of the equipment within the required delivery dates.