This is a Statement of Work (SOW) for fence repair and replacement services at the United States Coast Guard Academy in New London, Connecticut. The contractor must furnish all labor, materials, equipment, transportation, and supervision to service, repair, reset, and replace damaged or deficient fence components. Work is limited to replacing only those fence posts determined to be loose, damaged, rotted, bent, broken, or otherwise unable to adequately support the fence, with replacement posts matching existing specifications in type, size, material, and finish. Scope includes removing damaged posts, excavating failed concrete footings, installing new galvanized posts set in concrete, replacing damaged chain link, top rail, bottom rail, bracing, tension wire, barbed wire, hardware, caps, bands, ties, and clamps, and restoring all repaired sections to plumb, aligned, stable, properly tensioned, and fully functional condition. Specific work areas include the tennis court fence (12 feet high), the perimeter fence, U-Lot (6 sections), and the track fence (59 posts, 4 feet high).

Work must be performed at the Coast Guard Academy, 15 Mohegan Drive, New London, Connecticut, between 7:30 a.m. and 4:00 p.m. Monday through Friday, excluding Federal Holidays, with all scheduling coordinated through Technical Advisor Jason Askew (Jason.M.Askew@uscg.mil). The government will furnish electricity (120vac @ 20 amps) and water at no cost; contractors must arrange additional connections and remove all equipment and debris daily. All work is subject to inspection and acceptance by the Contracting Officer or Technical Advisor, with unsatisfactory work corrected at no additional government cost. Site visits are encouraged prior to bidding, and contractors must adhere to Coast Guard Academy smoking policies and minimize interference with military operations. Removed materials become contractor property and must be disposed of offsite in accordance with applicable federal, state, and local laws; metal scrap may be disposed of at the dumpster behind Johnson Hall.

View the file

Other files

File Type Posted
Combined Synopsis Solicitation_Fence.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Scope of Work United States Coast Guard Academy New London, Connecticut Service fence around Academy

Part 1 – GENERAL

1.1 Project Description:

The contractor shall furnish all labor, material, equipment, and transportation, to service numerous sections of fence, Coast Guard Academy, New London, Connecticut.

1.2 Contractor Qualifications and Personnel Requirements:

The contractor and all contractor personnel performing work under this contract shall possess the qualifications, experience, and certifications, if applicable, necessary to perform fence repair and replacement work in accordance with applicable federal, state, and local requirements, industry standards, and the terms of this contract. The contractor shall provide a primary point of contact, including name, telephone number, and email address, for coordination throughout contract performance.

1.3 Technical Advisor:

All work performed by the contractor is subject to inspection and acceptance by the Contracting Officer or the Technical Advisor during and after the completion of each visit. Unsatisfactory work shall be corrected at no additional cost to the government. The Technical Advisor for site visits and technical support is Jason Askew who may be reached at Jason.M.Askew@uscg.mil. TA are not authorized to issue changes to the contractor or resolve contractual disputes.

1.4 Location of Work:

All work shall be performed at the Coast Guard Academy, 15 Mohegan Dr, New London, CT 06320.

1.5 Site Visit:

Bidders are encouraged to visit the site to become familiar with existing conditions. Failure to do so will not relieve the successful bidder from furnishing all labor, materials, and equipment to satisfactorily complete performance of all required work. Bidders shall contact the primary TA to schedule a site visit.

1.6 Hours of Work:

All work shall be performed between the hours of 7:30 a.m. and 4:00 p.m. local time, Monday through Friday excluding Federal Holidays. Should the contractor desire to work outside these hours, the contractor shall submit a request to the primary TA no less than 48 hours in advance.

1.7 Scheduling of Work:

The contractor shall schedule all work with the TA.

1.8 Contractor’s Use of Premises:

The contractor will be working within an operational Coast Guard military installation. The contractor shall perform and conduct all work to minimize interference with Coast Guard operations.

1.9 Parking:

The contractor is authorized parking during the performance of work. Overnight parking is not authorized. Parking arrangements shall be made through the TA.

1.10 Inspection and Acceptance of Work:

The contractor shall keep the TA fully informed of contract operations throughout the performance of work. The contractor shall notify the TA upon completion of work. The contractor and TA shall perform a joint final inspection and the contractor shall correct any noted deficiencies.

1.11 Government Furnished Utilities:

The government will furnish electricity (120vac @ 20 amps), and water from existing building services will be provided at no cost to the contractor. Additional hookups or temporary connections shall be the responsibility of the contractor and shall be removed by the contractor upon completion of work.

1.12 Storage Facilities:

The government will not provide storage facilities.

1.13 Site Clean Up:

Upon completion of daily work, the contractor shall remove and properly dispose of site debris and rubbish. Contractor equipment shall be removed from Coast Guard Academy premises unless otherwise authorized by the TA.

1.14 Disposal of Removed Materials:

All materials and equipment removed by the contractor shall become the property of the contractor and shall be disposed of offsite in accordance with all applicable federal, state and local laws and regulations. Under no circumstances shall materials be placed in government-owned or leased refuse containers.

1.15 Smoking:

The contractor shall strictly adhere to the Coast Guard Academy’s smoking policy which limits smoking to 4 designated locations. The TA will provide smoking area locations upon request.

Part 2 – SCOPE OF WORK

2.1 General:

The Contractor shall replace only those fence posts determined to be loose, damaged, rotted, bent, broken, or otherwise unable to adequately support the fence. Fence posts that remain structurally sound and securely anchored shall not be replaced.

Replacement posts shall:

· Match the existing post type, size, material, and finish unless otherwise approved by the Contracting Officer or COR.

· Be installed plumb, properly aligned, and spaced to match the existing fence configuration.

· Be securely set in accordance with manufacturer recommendations and industry standards using appropriate concrete footings or anchoring methods.

· Reattach and properly tension all existing fence fabric, rails, brackets, hardware, and accessories impacted by the post replacement.

· Restore the fence to its original alignment and structural integrity.

Upon completion, the Contractor can utilize the scrap metal dumpster behind Johnson Hall for dispose of metal. The completed fence shall be fully functional, stable, and free of loose sections or misalignment.

Fence replacement:

Posts and Footings
•Remove damaged line posts.
•Remove damaged terminal, corner, and end posts.
•Excavate failed concrete footings.
•Install new galvanized posts.
•Set posts in concrete.
•Verify posts are plumb and properly spaced.
•Backfill and restore disturbed areas.
Top Rail and Bracing
•Replace damaged top rail sections.
•Replace bottom rail (if applicable).
•Install or replace rail sleeves.
•Replace brace rails and truss rods.
•Tighten existing brace assemblies.
Hardware Replacement
•Replace tension bars.
•Replace tension bands.
•Replace brace bands.
•Replace rail ends.
•Replace post caps.
•Replace loop caps.
•Replace nuts, bolts, and clamps.
•Install new fence ties.
Wire Components
•Replace bottom tension wire.
•Tighten existing tension wire.
•Replace damaged barbed wire (if applicable).
•Replace barbed wire arms.
•Install new clips and fasteners.

Fence at Tennis Courts: Replace posts. Fence height 12’

Perimeter Fence: Reset posts (5)

Replace posts, chain link, barb wire: U-Lot, 6 sections.

Replace 59 posts around track: 4’ fence image1.jpeg image2.jpeg image3.jpeg image4.jpeg image5.jpeg image6.jpeg image7.jpeg image8.jpeg image9.jpeg