SOW Ejector Pump.pdf
PDF 276 KB Posted
- Attached to
- Sewage Ejector Pump Replacement Federal contract opportunity
- Solicitation number
- 697DCK-25-R-00268
About this file
This Statement of Work (SOW) details a sewage ejector pump replacement project for the Chicago Air Route Traffic Control Center (ARTCC) in Aurora, Illinois. The contractor must replace one of two sewage discharge pumps in mechanical room 12A-F, which involves installing a new pump with equal or larger capacity, reconnecting existing discharge piping and electrical connections, and sealing the sewage pit upon completion. The project has a 7-business day performance period from Notice to Proceed, with work potentially required outside normal business hours of 7AM to 4PM, given the facility's 24-hour operational status.
Key requirements include coordinating with the Contracting Officer Representative (COR) for shutdowns and system access, maintaining a clean work area, providing material safety data sheets for VOC materials, obtaining COR approval for welding and other potentially hazardous work, and adhering to OSHA requirements for confined spaces. The contractor must use the provided reference drawing (ZAU-GL-D-2837-EL01-CM) as a guide and field verify all dimensions. The project is located at 619 Indian Trail, Aurora, Kane County, Illinois 60506, and involves precise technical and safety protocols to minimize disruption to the facility's continuous operations.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 697DCK-25-R-00268 CON SOL.pdf | ||
| Wage Determination.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ZAU SEWAGE PUMP REPLACEMENT IN MECHANICAL ROOM 12A-F EQUIPMENT
NO.45
CHICAGO ARTCC
AURORA, ILLINOIS
SCOPE
Contractor shall provide all labor, supplies, materials, equipment and supervision to replace one sewage ejector pump located in the mechanical room 12A-F at the Air Route Traffic Control Center 619 Indian Trail Aurora, Kane County Illinois 60506. This Pump is one of two pumps that discharge raw sewage from Auto Wing. Work consists of the following:
1. The contractor must install a new ejector pump of equal or larger capacity to handle current discharge requirements.
2. Contractor must reconnect existing discharge piping and electrical and replace any damaged piping due to removal and replacement of discharge pump.
3. The contractor must seal the sewage pit upon completion of installation of the new pump.
Contractor shall:
1. Coordinate with the Contracting Officer Representative (COR) prior to any shutdowns and disconnects to the plumbing and system.
2. FAA personnel will operate all equipment, valves, and disconnects. Coordinate with the COR prior to equipment or system shutdown.
3. Maintain a clean working area and restore any damaged equipment and property to its original state.
4. Provide material safety data sheets for all materials containing volatile organic compound (VOC) to the COR for approval prior to delivery on site. When cleaning and preparing surfaces, proper vapor extraction and fresh air ventilation shall be provided for each area of activity and vapor shall be vented outside as directed by the COR.
5. Receive COR approval prior to any welding, brazing or soldering and grinding work to protect the facility and personnel. Proper vapor extraction and fresh air ventilation shall be provided, and the vapor shall be directed outside as directed by the COR personnel.
6. Due to the hours or operation required for this facility, the work schedule and hours of work activity would be discussed by the facility with the contractor who is doing the project.
7. Will abide by all Federal, State & local regulations along with the reference regulations below:
a. Confined Spaces shall be done in accordance with OSHA Requirements 29 CFR
1910.146 and 1926.21(B)(6).
PERIOD OF PERFORMANCE:
The contract shall complete all work within 7 business days from Notice to Proceed (NTP).
This facility is a 24-hour operation and normal business hours are from 7AM to 4PM but work may be required after hours or at night. The work schedule will be approved by the COR prior to the issuance of NTP.
REFERENCE DRAWING
• Provided is Drawing No ZAU-GL-D-2837-EL01-CM Facility Baseline Layout Basement Plan - Part 1 Chicago ARTCC “FOR REFERENCE ONLY.” Reference drawing must be used as a guide. Field verifies all dimensions.
(END OF STATEMENT OF WORK)