This document is a Statement of Work (SOW) for the removal of driftwood and debris around the upper pilings and mooring dock at the United States Coast Guard (USCG) Shore Side Detachment (SSD) facility in Owensboro, Kentucky.
The SOW specifies that the contractor shall provide all labor, materials, and equipment necessary to complete the work, which includes removing driftwood from around the upper pilings and mooring dock from a river barge. Only driftwood in the water may be moved, and any wood on the river bank must remain or be loaded onto the barge for disposal. The removed driftwood will be pushed free from the lodged area to float down the river. The work must be completed during the normal operating hours of the facility, and the contractor must coordinate with the Contracting Officer's Representative. The period of performance is June 17 through June 28, 2024, and the contract will be awarded as a Firm Fixed Price service order to the lowest priced qualified contractor. The associated federal contract opportunity is Solicitation Number 70Z02924QNEWO241.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 70Z02924QNEWO241.pdf | ||
| WD_2015_4685.pdf | ||
| FAR_Commercial_Supplies_Services.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF HOMELAND SECURITY
UNITED STATES COAST GUARD
SSD Owensboro, KY
SPECIFICATIONS
FOR
De Drift Mooring
Location: United States Coast Guard SSD Owensboro, KY
3301 East 4th street
Owensboro, KY 42303
I. Continuity of Facilities Operation: Schedule work to minimize interference with the facility’s normal operations. Normal operating hours are from 8:00am to 2:00pm Monday thru Thursday except federal holidays. Any work during other hours unless otherwise instructed or permitted shall be scheduled and approved with the Contracting Officers Representative.
II. Notification of Start and Completion of Work: The Contractor shall notify Coast Guard one week prior to start of work.
III. Coast Guard Contracting Officers Representative: Contact MKC Michael Putnam
(Michael.r.putnam@uscg.mil; (845) 417-1528 to coordinate all construction efforts onboard Coast Guard Facilities.
IV. Recycling and Disposal of Refuse: Minor refuse, excess or waste materials resulting from construction operations may be disposed of in base dumpsters. All disposals shall be done in accordance with federal, state, and local laws and regulations. All bulk waste shall be disposed of in contractor provided dumpsters
V: Safety: During the execution of this contract, the Contractor shall conform to the rules and regulations as set forth by OSHA Safety and Health Standards, 29 CFR Part 1926 - Safety and
Health Regulations for Construction. The contractor shall have a written safety plan as required in FAR 5.236-13. The plan shall unequivocally assign responsibility and authority for safety to the superintendent by name. Immediate notification to the Contracting Officer’s Representative of lost time due to accidents is required. Provide two copies of workman’s compensation accident reports by noon of the day following the accident. The Coast Guard reserves the right to bar any workers or supervisors from the premises should they be documented as violating set safety standards and regulations.
VI. Inspection: The Contracting Officer’s Representative has the right to reject defective workmanship or materials or work not performed as per the project specifications. Only the
Contracting Officer or his/her representative may accept work performed by the contractor.
VII. Operations and Storage: The contractor is to take whatever steps necessary to ensure that his materials are protected. The Coast Guard has no responsibility for receipt, storage, or protection of contractor’s materials. All equipment, materials and supplies shall be addressed to the contractor. The Coast Guard will not accept shipments. The contractor is responsible for the protection of existing structures, utilities, work and vegetation. Any damage shall be repaired at the contractor’s expense.
VIII. Contractor Identification: The contractor and subcontractor personnel shall, at all times, wear company identification.
IX. Existing Utilities: The Contractor shall field verify all utility locations before commencing work. This shall include, but not be limited to, the use of visual, sonic, electronic or magnetic detection devices. Contractor shall be responsible for repairing any utilities damaged during construction at no additional cost to the Government.
X: Regulations while onboard Coast Guard SSD Owensboro:
1. Daily colors and the raising/lowering of the American flag will take place every morning at 0800 and every evening at sunset. All personnel on Base will face the main flag pole
& maintain silence and all vehicles & equipment will halt during these brief events.
2. The construction site shall be maintained in a clean condition at all times. This included daily clean-ups of the construction and storage areas (FAR 52.236-12). The site shall be well lit and well barricaded/cordoned off as appropriate.
3. Traffic Regulations:
a) 10 mph speed limit
b) No use of cell phones is permitted while driving vehicles or operating heavy machinery
c) All personnel shall obey all marked traffic signals including stop signs & stop lights.
4. Absolutely no firearms or weapons of any kind are allowed onboard Base SSD
Owensboro.
5. Only American citizens and permanent resident aliens are allowed onboard SSD
Owensboro Facilities. Absolutely no foreign nationals are permitted on the premises.
6. Notice shall be given to the Coast Guard’s representative 1 week in advance of any planned power, water, sewage or lighting outages.
7. The contractor shall provide a consolidated list of all contracted personnel including their drivers license numbers (or other valid gov’t issued ID number) who will be working on
Base SSD Owensboro Facilities either the day of or prior to the notice to proceed date.
8. Contractors are welcome to utilize the restrooms on the 1st decks of SSD Buildings providing they are clean and do not track mud, dirt or any other debris into the restrooms.
9. Should warnings of gale force or stronger winds, or other inbound natural disasters be issued, the contractor shall take every practicable precaution to minimize the danger to persons, to the work, and the adjacent property. These precautions shall include closing all openings, removing all loose materials, tools and equipment from exposed locations, and removing or securing scaffolding, securing field trailers, and other appropriate equipment and other temporary work.
10. No personnel other than the contracting officer has the authority to alter the terms of any contract or to issue any change orders.
11. All contractor vehicles, equipment and gear onboard Coast Guard properties are subject to search at all times. Additionally at all times due to security and operational needs, the contractors is subject to orders to evacuate the property at any time.
VIII: SCOPE OF WORK: Contractor shall provide all labor, materials, and equipment necessary to complete the following:
1. All work will be completed onboard SSD Owensboro, KY.
2. SSD
a. SSD Dock
i. Remove drift wood from around upper pilings and mooring dock. Work shall be completed from a barge on the river.
ii. Only drift wood in the water may be moved, wood that is on the river back must remain, or be loaded on to barge for disposal.
iii. Drift wood removed from pilings and mooring will be pushed free from lodged area to float down river.
3. All work to be approved by the Contracting Officer’s Representative.