W912WJ-21-Q-0130

Replace Fuel Storage Tanks

Cape Cod Space Force Station, Bourne, Massachusetts

Construction Solicitation and Specifications

JULY 2021

REPLACE FUEL STORAGE TANKS

CAPE COD SPACE FORCE STATION

BOURNE, MA

STATEMENT OF WORK

Solicitation Number: W912WJ-21-Q-0130

July 2021

A. General Description of the Work to be Performed

The general description below is given to indicate the approximate scope of this project only. It does not limit the work required under this statement of work and associated contract drawings.

The proposed project consists of replacing the three (3) existing aboveground diesel fuel tanks. The area of concern is located in Cape Cod Space Force Station (SFS). The project includes the removal of the three (3) existing tanks including existing concrete pads and the installation of three (3) new double wall diesel fuel tanks on new concrete pads including all work necessary to install the new fuel tanks and connect to the existing fuel lines and electrical feeds. The installation of three (3) new concrete pads shall be according to fuel tank manufacturer guidance and the detail shown on the contract drawings.

a. Tank 1 (Base Bid Item 0001): The existing 1,000 gallon tank is located behind Building 58 on the south-west side (Photo 1) and feeds both a 80 KW back-up generator (Photo 2), and the building’s furnace (Photo 3-5). There is currently no remote monitoring of the fuel tank. There is approximately 20 ft of clearance between the building and the tree line, and there is good access from the parking area directly to the south.

b. Tank 2 (Optional Bid Item 0002): The existing 1,000 gallon tank is located beside Building 50 on the south side (Photo 6) and feeds the building’s furnace (Photo 7). There is currently no remote monitoring of the fuel tank. The tank is approximately 7 ft from the transformer and 8 ft from the secure perimeter fence for the adjacent facility (Photo 8). Access from the front/side of the building is limited by the transformer as well as anti-vehicle boulders and other possible underground utilities (Photo 9). There is a dirt/gravel road behind the building that could possibly be used for access (Photo 10 and 11).

c. Tank 3 (Optional Bid Item 0003): The existing 1,000 gallon tank is located behind Building 10 on the south-west side (Photo 12) approximately 5 ft-10in from the building, and feeds a furnace (Photo 13).

There is currently no remote monitoring of the fuel tank. The fuel lines for the tank run through a trenched line to the building (Photo 14).

Any part of the work required under this statement of work that is not described nor shown on the contract drawings which is ancillary, necessary, or normally required as a part of such work, or is necessary or required to make such installation satisfactorily and legally operable, shall be performed by the Contractor as incidental work at no additional cost to the Government.

B. Project Location

The project site is located at the Cape Cod SFS Bourne, approximately 2 miles off Massachusetts 6A (MA-6A), 24 miles off Interstate Highway 495 (I-495) and approximately 55 miles (i.e.PL south-southeast) of Boston Massachusetts. See Photo 15 for directions to get on base.

C. General Project Requirements

1. Contractor’s Responsibility. The Contractor shall provide all supervision, labor, plant, equipment, materials, quality control, safety, and mobilization and demobilization and carry out all operations as necessary to accomplish the work of this project as described in this document and on the contract drawings.

2. Clean Up and Waste Disposal: The contractor shall keep the work area free from accumulation of waste materials. Any and all disturbed areas resulting from contractor activities shall be restored by the contractor to the satisfaction of the Point of Contact.

3. Personal Protective Equipment: It is the contractor’s responsibility to furnish and supply personnel with the proper personal protective equipment and fall protection necessary for performing the work.

4. Schedule. Work shall be performed Monday through Friday 0730 to 1630 unless otherwise approved by the Technical Point of Contact. No work shall be done on weekends or Government holidays. The contractor shall submit an initial project schedule. An updated schedule showing actual progress shall be submitted monthly or with each pay request.

5. Commencement, Prosecution and Completion of Work. The Contractor shall commence work under this contract within 10 days after the date of receipt of the Notice to Proceed, shall prosecute the work diligently, employing ample personnel and sufficient equipment, and shall complete the entire work ready for use not later than 240 working days after the date of receipt of the Notice to Proceed. The time included for completion shall include final cleanup of the project site. Additional restrictions concerning the prosecution and completion of work are as follows:

A. The Contractor shall attend a Preconstruction Conference prior to the start of on-site construction work (see paragraph entitled "Preconstruction Conference", below).

B. The Contractor shall have all tanks (existing and new) in place and operational for heating season needs (mid-November thru mid-April).

C. The Contractor shall coordinate installation of tanks with projected weather with COR prior to installing tanks during this time frame.

6. Preconstruction Conference – Prior to the start of any work, the Point of Contact will schedule and conduct a “Preconstruction Conference”. The Contractor’s Project Manager and Quality Control Personnel will attend this meeting. This conference will be held at the time and location agreeable to the government and contractor. No work may be performed under this contract prior to this conference. The purpose of the conference is to enable the Technical Point of Contact to outline the procedures that will be followed by the Government in its administration of the contract, and to discuss the performance that will be expected from the Contractor. This conference will allow the Contractor an opportunity to ask questions about the Government’s administration and inspection of contract work or obtain other pertinent information that might be required. At the Preconstruction Conference the contractor shall provide to the name of the project superintendent with a telephone number for project coordination.

The following is a general list of items for discussion during this Preconstruction Conference:

i. Authority of the Technical Point of Contact and Quality Assurance Inspectors.

ii. Contractor’s Safety Program (including sub-contractors).

iii. Abbreviated Accident Prevention Plan and Activity Hazard Analysis (Submitted & accepted prior to start of work on site)

iv. Safety Meetings (Documented on NED Form 251)

v. Accident Reporting (ENG Form 3394)

vi. Safety Data Sheet (SDS) requirements

vii. Correspondence, Communication and Administrative Procedures.

viii. Invoice and payment.

ix. Security Verification

7. Permits – The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses, permits, and letters of certification. The Contractor shall comply with any applicable Federal, State, County, and Municipal laws, codes, and regulations in connection with the performance of the work specified under this contract.

8. Damage to Government and Private Property – The contractor shall be responsible for restoring all Government facilities or structures damaged as a result of the firm’s operation. The contractor shall also be responsible for any damage to private property or injury to any person as a result of the firm’s operation.

The contractor shall notify the Project Manager immediately of damage to Government and private property and injury to any person resulting from the firm’s operation.

9. Omissions – This contract may not cover all specified activities, steps, and procedures required to supply the contract product. In case of omission, the normal industry, state, or federal standards, practices, specifications, and/or guides shall prevail. In no instance shall an omission be reason to produce less than an acceptable product.

10. Quality Assurance – The contractor is responsible for the quality control of the contract work. The Government has the right to inspect and test all items called for by the contract, to the extent practicable at all times and at all places during the term of the contract.

11. Other Contracts - The Government may undertake or award other contracts for additional work not related to this contract, and the Contractor shall fully cooperate with other Contractors and Government employees.

The contractor shall not commit or permit any act, which will interfere with the performance of work by another contractor or by Government employees

12. Receiving and Storing Materials – The Government may provide a storage area and parking for contractor personnel. The contractor is responsible for protecting any stored material until it is placed in service. The contractor is responsible for receiving and unloading of delivered goods. Government employees will not receive material for supplies for the contractor and will not be responsible for damage to the contractor’s equipment or materials.

13. Contractor Conduct –Contractor and employees must comply with CFR 36 Rules and Regulations.

14. Payment – Payment shall be made on a per job basis. After final inspection and acceptance by the Government, the Contractor must submit an invoice to the Technical Point of Contact. The invoice shall include the invoice date, contract number, dates of service, description of work, quantities, process, and total amount due per line item. For jobs greater than 30 days the contractor may request progress payment.

All invoices may be mailed to:

TBD during pre-construction conference.

15. Utilities –The Contractor shall provide and pay for its own water and electricity that may be required in the prosecution of the work. There will be no Government provided water or electricity at the project site. The use of portable generators will be allowed for use onsite. If the work occurs during the heating season, the Contractor shall make provisions to provide fuel for the heating systems during construction. If the work will be scheduled outside of the heating season, it will not necessary to provide fuel for the heating system.

16. Temporary Electrical Equipment and Connections –The Contractor, at his own expense and in a workmanlike manner satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines. All required temporary electrical equipment and lines shall be furnished, installed, connected, and maintained by the Contractor according to EM 385-1-1, Section 11.E, NFPA 241,and NFPA 70, Article 305-6(b), "Assured Equipment Grounding Conductor Program". All temporary equipment and lines shall be removed prior to final acceptance of the work. Materials and equipment need not be new, but must be in good repair and serviceable condition. Periodic inspections of systems and devices will be made by the Contractor at intervals not to exceed one week.

17. Environmental Protection –The Contractor shall minimize environmental pollution and damage that may occur as the result of construction operations. The environmental resources within the project boundaries and those affected outside the limits of permanent work shall be protected during the entire duration of this contract. Comply with all applicable environmental Federal, State, and local laws and regulations. Any delays resulting from failure to comply with environmental laws and regulations will be the Contractor's responsibility.

a. Environmental Protection Plan: Prior to commencing construction activities or delivery of materials and equipment to the work sites, the Contractor shall submit an Environmental Protection Plan for review and approval by the Contracting Officer. The purpose of the Environmental Protection Plan is to present a comprehensive overview of known or potential environmental issues which the Contractor must address during construction. Issues of concern shall be defined within the Environmental Protection Plan. The Contractor shall address each topic at a level of detail commensurate with the environmental issue and required construction task(s). The Environmental Protection Plan shall be current and maintained onsite by the Contractor.

b. Temporary Erosion and Sediment Controls: The Contractor shall be responsible for providing temporary erosion and sediment control measures for storage and staging areas and other areas as appropriate for the work, in accordance with Federal, State, and local laws and regulations. The erosion and sediment controls selected and maintained by the Contractor shall be such that water quality standards are not violated as a result of the Contractor's construction activities. The area of bare soil exposed at any one time by construction operations should be kept to a minimum. The Contractor shall construct or install temporary and permanent erosion and sediment control best management practices (BMPs). BMPs may include, but not be limited to, vegetation cover, slope stabilization, sedimentation control barriers, sediment traps, and inlet and outfall protection. Any temporary measures shall be removed after the area has been stabilized and prior to the completion of construction.

c. Fuels and Lubricants: Storage, and fueling and lubrication of equipment and motor vehicles shall be conducted in a manner that affords the maximum protection against spill and evaporation. Manage and store fuel, lubricants and oil in accordance with all Federal, State, Regional, and local laws and regulations. Used lubricants and used oil to be discarded shall be stored in marked corrosion-resistant containers and recycled or disposed in accordance with State, and local laws and regulations. Storage of fuel on the project site is not allowed. Fuel shall be brought to the project site each day that work is performed. Storage and usage of lubricants and daily fueling of machinery and equipment shall occur at least 50 feet from any drainage inlets, water bodies (rivers, streams, lakes), environmentally sensitive areas (wetlands, vernal pools).

18. Waste –The Contractor shall provide on-site containers for the collection of demolition debris, waste materials, construction debris, and rubbish. The Contractor shall clean the project site on a daily basis to prevent the accumulation of waste materials and rubbish resulting from construction activities. The Contractor shall transport all solid waste off of the project site and dispose of it in compliance with Federal, State and local requirements for solid waste disposal. Upon completion of the construction work, the project site shall be returned to its pre-work condition.

19. Restoration of Staging and Storage Area –Upon completion of the project remove barricades, temporary utilities, sanitation facilities, construction vehicles, materials and equipment, temporary chain-link fencing, and any other temporary equipment, materials, or products from within and around the work areas and temporary staging and storage areas. Clean and repair damage caused by installation or removal of temporary materials, equipment, or utilities. Areas used by the Contractor for the storage of equipment or material, or other use, shall be restored to the original or better condition, including pavement repair, or topsoil and seeding as necessary. Gravel used to traverse grassed areas shall be removed and the area restored to its original condition, including topsoil and seeding as necessary. All seed mix shall be a conservation mix.

20. Contractor Use of Premises –Work shall be restricted to the areas requiring the work, access routes to the work site, and to staging and storage areas assigned to the Contractor under this contract. Access to the project site is currently available for construction traffic. The Contractor shall be responsible for providing and maintaining access necessary for its equipment and plant to and from the work site.

a. Superintendence by the Contractor. At all times during the performance of the contract and until the work is completed and accepted, the Contractor shall directly superintend the work or assign and have on the worksite a competent project superintendent who is satisfactory to the Contracting Officer and has the authority to act for the Contractor. The project superintendent shall maintain a physical presence at the site at all times and be responsible for all construction and related activities at the site, except as otherwise acceptable to the Contracting Officer. Failure to comply with these requirements shall be deemed as cause for a non-compensatory stoppage and suspension of work until the deficiency is remedied.

b. Security. The Contractor will comply with all established security policies at Cape Cod SFS. Due to periods of heightened security that may affect the access to the areas covered under this contract, the Government reserves the right to close any property or portion of property and reschedule and/or cancel any subsequent service. The Contractor shall be given at least 24 hour notice of any such closure. The contractor will verify all employees working project through the E-Verify website located at:

http://www.uscis.gov/e-verify . The Contractor will submit verification documents to the Technical Point of Contact prior to or during the Preconstruction Conference or prior to any new employees joining the current project.

21. Protection and Security –The Contractor shall comply with the provisions of AFI 31-101 USAF Physical Security Program and all security and law enforcement procedures established at Cape SFS. The Contractor shall provide escort personnel for Contractor personnel within the restricted area of Cape Cod SFS for the contract period. This includes all Contractor personnel who have not been the subject of a favorable National Agency Check (NAC). The Contractor will be required to provide, on a daily basis, their list of escort personnel. The Contractor shall implement necessary security controls as prescribed by the installation commander. The requirements for and responsibilities for escort personnel are addressed herein.

http://www.uscis.gov/e-verify http://www.uscis.gov/e-verify

a. Escorts requires only when the contractors without a secret security clearance working inside the restricted area. Only the Tank 3 for the Entry Control Point, Building 10, would require escorts. The escorts don't have to be AF personnel, as long as the employees have the security clearances, they will be allowed in the area. To get access through the SFS security gate, it is required a list of the contractors with full name and driver's license number. That information is used to create an Entry Authorization List for getting into the restricted area as well as verifying access through the gate. Vendors/deliveries shall be preannounced to get through the gate. If a delivery is required into the restricted area, then the name and driver's license information is needed as well. The background check isn't required. For the USACE staff, escorts would only be required in the restricted area if the staff member does not have at least a secret security clearance. A visit request is submitted in the Joint Personnel Adjudications System (JPAS) so the clearance information can be verified and they can receive badged into the restricted area.

If they don't have a clearance, they would need to be escorted in the restricted area.

b. The Contractor will supply the required number of escorts per day to adequately supply all construction operations and fulfill the station's security escort requirements. One escort is required for every six (6) Contractor personnel. However, in the event one of the individuals needs a break or must leave the area, the entire work crew must accompany them until they are clear of the restricted area or they are finished with their break. The recommendation is to use a minimum of two escorts. The Contractor is responsible for all costs associated with providing escort personnel. An average of approximately 20 minutes shall be anticipated each time an individual enters the restricted area. This is a routine matter during which the entry controller and escort official search vehicles and hand-carried items and check badges and credentials at the entry control points. Longer times will be experienced if Contractor employees must wait for an escort official. With proper planning and coordination with government project managers, entry into the restricted area IS NOT a time consuming process and rarely exceeds ten (10) minutes. Prior to entry into the restricted area, all visitors and their escorts must be approved by an escort official. It is the escort official that is ultimately responsible for any breach of security. The Contractor must ensure that entry requirements are arranged at least 5 work days in advance to ensure the availability of an escort official. Entry arrangements should be coordinated through the Civil Engineering Liaison, (508) 968-3276 or the Site Support Officer, (508) 968-3213. Any personal computers, laptop computers, cameras, cell phones, hand held radios or other recording type devices must receive prior approval of the installation commander. The Contractor shall submit the item(s) description, model number, and serial number seventy-two (72) hours prior to required entry.

Equipment authorization should be coordinated through the Civil Engineering Liaison, (508) 968-3276 or the Site Support Officer, (508)968-3213.

c. Security Escort Contractor Requirements USSF restricted areas are established to provide special security measures to deter and counteract espionage, sabotage, or theft of Space Force operational resources. The escort shall ensure all Contractor construction personnel comply with procedures established for circulation control of personnel and materials within the restricted area. Escorts shall not have other duties except escorting. Escort personnel will require unescorted entry into the restricted area. To be escort personnel or to be eligible for unescorted entry to a restricted area, personnel must be United States citizens and the subject of a favorable National Agency Check. Since a NAC is also a prerequisite for a secret clearance, personnel possessing a secret clearance for access to classified information meet the escort personnel and/or unescorted entry prerequisite. All Contractor escort personnel will enter the restricted area through the established entry control points. After entry to the restricted area, all Contractor escorts will display restricted area badges on their outer garments above the waist in a highly visible area. The restricted area badge shall be removed upon leaving the restricted area. Loss of a restricted area badge shall be reported to the security police at Cape Cod SFS. The station commander will deny entry into the restricted area to any Contractor escort personnel whose NAC is unfavorable or who pose a security risk or who can be considered harmful to national security interests. The deviation from established security procedures by Contractor escort personnel can result in confiscation of restricted area badges and denial of future entry into the restricted area by the station commander. The Contractor escort personnel shall ensure that they and all escorted construction personnel leave the restricted area when directed to do so by the station commander or his representative due to operational requirements or emergencies

d. The contractor shall supply escorts as outlined for the entire time they are onsite. The escorts may be from an agency of the contractor’s choosing, provided they meet all applicable guidelines or the contractor may choose to use escorts provided by Cape Cod Space Force Station. CCSFS individuals escort at the rate of $16/hour but shall be confirmed with the Civil Engineer Liaison at CCSFS prior to the start. All costs associated with the escorts shall the responsibility of the contractor.

22. Normal working hours at Cape Cod Space Force Station are from 0730-1630 excluding weekends and holidays. All federal holidays are recognized. A one week notice is required to work a weekend or holiday.

Work on a weekend or holiday is on a case by case basis.

23. Damaged Property –Work shall proceed in a manner which will minimize disturbance or risk of damage to structures and surrounding lands. The Contractor shall repair such items damaged in the course of carrying out the work at no additional cost to the Government. All repairs shall match similar existing items in all aspects. All replacements shall be in kind.

24. The Contractor shall coordinate with the SABER Project Manager/Inspector, facility security/occupants/users, CCSFS Environmental office, Communications Lead, Security Forces and JBCC Fire Department.

a. To receive direct contacts for any individual or agency the Contractor may request this information from the SABER PM

25. Contractor's Receipt of Supplies –The Contractor shall be responsible for all arrangements for the receipt of materials and supplies to the job site. Government personnel are not permitted to receive or sign for items delivered to the site.

26. Sanitary Facilities –In accordance with Section 2 of EM 385-1-1, provide, maintain, and make available to all workers provisions for sanitation. Maintain these provisions at all times without nuisance. Upon completion of the work, all sanitary provisions and facilities shall be removed from the premises by the Contractor, leaving the premises clean and free from nuisance.

In accordance with Section 2, Subpart 02.C of EM 385-1-1, provide, maintain, and make available to all workers an adequate supply of potable water for both drinking and personal cleansing. During hot weather, provide cool drinking water.

In accordance with Section 2, Subpart 02.E of EM 385-1-1, provide, maintain, and make available to all workers adequate minimum field-type portable toilets. Portable toilets shall be properly secluded from public observation in such a manner as required or approved by the Contracting Officer. Periodically remove waste to a commercial facility that accepts sanitary sewage. Include provisions for pest control and elimination of odors. Any penalties and/or fines associated with improper discharge of wastewater shall be the responsibility of the Contractor. Government toilet facilities will not be provided.

D. Safety

1. Accident Prevention Plan –The Contractor shall prepare an Accident Prevention Plan (APP) specific to the activities being performed. It shall include an Activity Hazard Analysis (AHA) as described in Paragraph "2" below. All work shall be conducted in accordance with the APP, the U.S. Army Corps of Engineers Safety and Health requirements Manual (EM 385-1-1, 2014 edition), and all applicable Federal, State, and local safety and health requirements. A copy of EM 385-1-1 can be accessed electronically at Headquarters USACE website under publications using the following link:

http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf The APP shall detail how safety and health will be managed during the project. The APP shall address the requirements of applicable Federal, State and local safety and health laws, rules, and regulations. The Contractor shall comply with Federal Acquisition Regulation Clause No. 52.236-13 for Accident Prevention, which is added by reference. Special attention shall focus on the requirements of EM 385-1-1, specifically Section 01.A.12 through 01.A.14; 01.A.16; 01.A.17; Figure 1-2 AHA, and Appendix A, (Minimum Basic Outline for Accident Prevention Plan). The APP shall be developed by a qualified person. The Contractor shall be responsible for documenting the qualified person’s credentials. Work shall not proceed until the APP has been reviewed by the Government Designated Authority (GDA) and deemed acceptable for use on the project.

The APP shall interface with the Contractor's overall safety and health program. Any portions of the Contractor's overall safety and health program referenced in the APP shall be included in the applicable APP element and made site-specific. The Government considers the Prime Contractor to be the "controlling authority" for safety and health of the subcontractors. Contractors are responsible for informing their subcontractors of the safety provisions under the terms of the contract, the penalties for noncompliance, and inspecting subcontractor operations to ensure that accident prevention responsibilities are being carried out.

The Contractor shall conduct a safety meeting at the project site on the first day of work, whenever a new activity or phase of work begins, or at least weekly during the progress of work. All safety meetings shall be documented. A copy of a suggested weekly safety meeting form will be provided by the Contracting Officer’s Representative (COR). Records of the safety briefings shall be submitted to the GDA weekly.

An Excavation/Trenching Plan and/or Activity Hazard Analysis (AHA) will be prepared by the Competent Person (CP) for Excavation or a Registered Professional Engineer (RPE), submitted and accepted by the GDA IAW EM 385-1-1 Section 25 prior to beginning operations.

Definition of Competent Person Excavation is as follows: Competent Person, Excavation/Trenching: A person meeting the competent person requirements as defined in the definitions of EM 385-1-1 Section 25 and 29 CFR Part 1926 who has been designated in writing by the employer to be responsible for the immediate supervision, implementation and monitoring of the excavation/trenching program, who through training, knowledge and experience in excavation/trenching is capable of identifying, evaluating and addressing existing and potential hazards and, who has the authority to take prompt corrective measures with regard to such hazards.

2. AHA –An AHA shall be submitted for each major phase of work. A major phase of work is defined as an operation involving a type of work presenting hazards not experienced in previous operations or where a new subcontractor or work crew is to perform the work. The analysis shall define all activities to be performed, identify the sequence of work, the specific hazards anticipated, and the control measures to be implemented to eliminate or reduce each hazard to an acceptable level. Work shall not proceed on a phase of work until the AHA has been accepted by the GDA. A preparatory meeting shall be conducted by the Contractor to discuss the AHA contents with all engaged in the activity. The preparatory meeting shall be conducted by the prime Contractor and shall include all subcontractors and Government on-site representatives. The AHA shall be continuously reviewed and revised to address changing site conditions or operations as appropriate.

3. Accident Reporting –All accidents and near misses shall be investigated by the Contractor. All work-related recordable injuries, illnesses and property damage accidents (excluding on-the-road vehicle accidents), in http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf which the property damage exceeds $5,000.00, shall be verbally reported to the GDA within 4 hours of the incident. Serious accidents as described in EM 385-1-1, Section 01.D., shall be immediately reported to the GDA. ENG Form 3394 (available from the Contracting Officer’s Representative) shall be completed and submitted to the GDA within five working days of the incident.

The Contractor shall complete the “USACE Contractor Monthly Summary Record of Injuries/Illness and Work Hour Exposure” (for prime and its subcontractors), an EXCEL spreadsheet available from the Contracting Officer’s Representative, and forward the completed form to the GDA no later than close of business on the 10th calendar day of the following month. The method of transmission by the prime contractor to the GDA shall be electronically.

4. Site Safety and Health Officer (SSHO) –The Contractor shall designate one individual as the SSHO.

Documentation of SSHO qualifications shall be submitted for approval prior to initiating work. The SSHO shall have the qualification detailed below:

A. Shall have a minimum of two to five years of experience in implementing safety and health programs at similar projects;

B. Shall have working knowledge of construction safety procedures as well as Federal and state occupational safety and health regulations;

C. Shall have 30-hour OSHA Construction Safety certification or as an equivalent, 30 hours of formal construction safety and health training covering the subjects of the OSHA 30-hour course;

The SSHO may act as the Contractor’s Site Quality Control Manager, but may not be the Contractor’s Site Superintendent.

5. Equipment –The Contractor shall submit to the Contracting Officer’s Representative (COR) a current written safety inspection for all heavy equipment proposed for use on this contract. The Contractor, upon award of the contract, will be required to make available for suitability and safety compliance inspection all equipment proposed for use to perform the work of this contract. Equipment shall be made available for inspection by the Government Representative five working days prior to the start of construction. Any additional equipment added during the prosecution of the work shall also be made available for inspection prior to its use on the project. The Contractor shall keep equipment available for inspection by the Contracting Officer’s Representative (COR) during the construction process. Equipment not accepted by the Contracting Officer’s Representative (COR) should be repaired or replaced by the Contractor.

E. General and Administrative Submittals Required

Items for Submission. The Contractor shall submit the items identified below for approval to the Contracting Officer. Government acceptance, as defined in EM 385-1-1, is required for safety related submittals (identified below with an “S” after the submittal name). The Contractor shall submit an electronic PDF copy and five paper copies of each submittal item (unless otherwise indicated) using a completed ENG FORM 4025-R cover sheet (a blank copy of this form is attached at the end of this document). The Contractor will be informed at the Preconstruction Conference to send all submittals to either the project Resident Office or to the project Area Engineer Office, or other office, as applicable.

Preconstruction Submittals: The following submittals shall be made by the Contractor and review action completed by the Contracting Officer prior to the commencement of work at the site.

Initial Project Schedule: In accordance with the contract clauses, the Contractor shall, within five days after receipt of Notice to Proceed (NTP), or as otherwise determined by the Contracting Officer, submit for approval a practicable Initial Project Schedule. When changes are authorized that result in contract time extensions, the Contractor shall submit a revised project schedule for approval by the Contracting Officer.

Accident Prevention Plan (S): The Contractor shall prepare an Accident Prevention Plan (APP) specific to the activities being performed. It shall include an Activity Hazard Analysis (AHA) for each major phase of work

SSHO Qualifications (S): Documentation of SSHO qualifications shall be submitted for approval.

Safety Inspection for all Heavy Equipment (S): The Contractor shall submit a current written safety inspection for all heavy equipment proposed for use on this contract

Work Plan (S): The Contractor shall submit a written Work Plan describing the methods and equipment required to accomplish the work and provide the required environmental and worker protection.

AF103 : The Contractor shall call DIG SAFE at 811 or 1-888-DIG-SAFE not less than 72 hours prior to the start of any excavation for verification of underground utility locations. Since DIG SAFE may not identify all below grade utilities on Government property, the Contractor shall engage the services of the Cape Cod Space Force Station and private utility locating companies for additional assistance with locating underground utilities. Contractor to provide completed AF103 prior to construction.

Environmental Protection Plan: The Contractor shall submit an Environmental Protection Plan for review and approval by the Contracting Officer

Other Submittals: The following submittals shall be made by the Contractor to allow sufficient time for review action to be taken by the Contracting Officer and to comply with the approved Project Schedule, as appropriate.

Accident Reports (S)

Monthly Summary Record of Injuries/Illness and Work Hour Exposure (S)

Periodic Schedule Updates: An updated schedule showing actual progress shall be submitted monthly or with each pay request.

As-Built Drawing: Hard copy and digital copy of as-built drawing in AutoCAD file format.

F. Technical Submittals Required

The Contract Drawings (see G-001, G-101, C-101, C-501) are intended to convey the overall design intent of and general performance criteria for the work. It shall be the Contractor’s responsibility to submit documentation of all materials and/or components meeting the performance criteria and satisfying the design intent. Submittals addressing the technical requirements of this project are described below. The Contractor shall follow the procedures outlined in Part E above when making technical submittals.

1. General: Provide product data documenting performance characteristics and manufacturer’s cut sheets.

Provide shop drawings indicating layout, configuration, materials and method of installation.

2. As required by the procurement documents the contractor shall submit for Government approval specific parts of the scope that require selection and/or detailed review. Government approval of any Contractor submittal does not relieve the Contractor of his responsibility and liability to meet the full requirements of the SOW and meet all applicable Unified Facilities Criteria (UFC), Space Force Instruction (AFI), and code requirements.

3. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment, and size, physical appearance and other characteristics of materials.

a) If information must be specially prepared for submittal because standard published data are not suitable for use, submit as Shop Drawings (see below), not as Product Data.

b) Mark each copy of each submittal to show which products and options are applicable.

c) Include the following information, as applicable:

• Manufacturer’s catalog cuts.

• Manufacturer’s product specifications.

• Standard color charts.

• Statement of compliance with specified referenced standards.

• Testing by recognized agency.

• Application of testing agency labels and seals.

• Certification

• Notation of coordination requirements.

• Availability and delivery time information.

d) For equipment, include the following in addition to the above, as applicable:

• Printed performance curves.

• Operational range diagrams.

• Clearances required to other construction, if not indicated on accompanying Shop Drawings.

e) Submit Product Data before or concurrent with Samples, as applicable.

f) Submit Product Data in the following format:

• PDF electronic file.

g) Submit Product Data on the following

Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.

Samples of warranty language when the contract requires extended product warranties.

h) Submit Certification on the following:

Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that product, system or material meets specification requirements shall be dated after award of project contract and clearly name the project.

Document required of Contractor, or of a manufacturer, supplier, installer or Subcontractor through Contractor, the purpose of which is to further qualify the orderly progression of a portion of the work by documenting procedures, acceptability of methods or personnel qualifications.

i) Submit Test Reports on the following:

Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements.

(Testing must have been within two years of date of contract award for the project.)

Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.

Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.

4. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data, unless submittal based on digital data drawing files provided by Contracting Officer is otherwise permitted.

a) Preparation: Fully illustrate requirements in the Contract Documents. Include the following information, as applicable:

• Identification of products.

• Schedules.

• Compliance with specified standards.

• Notation of coordination requirements.

• Notation of dimensions established by field measurement.

• Relationship and attachment to adjoining construction clearly indicated.

• Seal and signature of professional engineer, if specified.

b) Sheet Size: Except for templates, patterns and similar full-size drawings, submit Shop Drawings on sheet at least 8-1/2 by 11 inches, but no larger than 22 by 34 inches.

c) Submit Shop Drawings in the following format:

• PDF electronic file

If it is impracticable to submit Shop Drawings in PDF format, paper format will be allowed. Submit three opaque copies of each submittal. Contracting Officer will retain two copies; remainder will be returned.

G. Delivery, Handling and Storage

As appropriate, materials shall be delivered to the project site in the manufacturer’s original packaging with the brand and item identification reference clearly marked. Components shall be stored in a dry location that is adequately ventilated, free from dust, water, or other contaminants, and which is easily accessible for inspection and handling.

H. Material Warranties

The Contractor shall note that a Warranty of Construction is required for this project for a period of 1 year from the date of final acceptance of the work, in accordance with the Contract Clauses. In addition, manufacturer’s standard performance guarantees or warranties that extend beyond a 1-year period shall be provided.

I. Coordination Liaison with the U.S. Army Corps of Engineers, New England District, by the Contractor shall be maintained for the duration of the project by communication with the Contracting Officer’s Representative (COR) assigned to this project. All Contractor project related questions, comments, clarifications, etc. shall be directed to the (COR) for action.

J. Technical Requirements

J-1. References

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 241 (2019) Standard for Safeguarding Construction, Alteration and Demolition Operations

NFPA 30 (2018) Flammable and Combustible Liquids Code

NFPA 70 (2017) National Electrical Code

UNDERWRITERS LABORATORIES (UL)

UL-142 (2019) Standard for steel Aboveground Tanks for Flammable and Combustible Liquids

UL-2085 (1997, REV 2010) Standard for Protected

Aboveground Tanks for Flammable and Combustible Liquids

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM-385-1-1 (2014) Safety and Health Requirements Manual, U.S.

Army Engineering Manual

J-2. Products

Refer to Specifications in General at the end of this document.

J-3. Execution

General

1. Request any hot works permit, dig permits, environmental correspondence and/or other pre-demo notifications.

2. Drain and make safe all fuel tanks and associated fuel lines for removal.

3. Establish at the interior fuel filter location fuel line cut-in and splice point by meeting with Contractor, COR and Diesel maintenance team.

4. Cut existing fuel lines at agreed splice points.

5. Remove three (3) existing 1000 GAL above-ground fuel tanks

a. Properly dispose of removed fuel tanks and fuel lines off site, according to all local, state and federal environmental regulations

b. Provide documentation (Bill of Lading) of disposal to Cape Cod Environmental office.

6. Demolish and remove three (3) existing concrete pads and properly dispose of off site.

7. The new concrete pads shall be placed within the same vicinity of existing concrete pads while verifying a minimum of 5feet from its respective building to comply with NFPA 30.

8. Concrete pads shall comply with manufacturer’s specifications for dimensions and to contract drawings.

9. Install new fuel lines and connect fuel tanks to previously cut splice points at each site location.

a. Secure all fuel lines with fasteners and at intervals that are code-compliant

10. Test fuel lines, tanks, valves for leaks.

11. If there is any evidence of historic spillage found prior to or during construction, contractor to notify COR. Any and all spillage occurring during removal and replacement of tanks and lines shall be the responsibility of the contractor to clean according to all applicable federal, state, and local laws.

SPECIFICATIONS IN GENERAL

REPLACE FUEL STORAGE TANK CAPE COD SFS, BOURNE, MA

PROJECT TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 33 00 SUBMITTAL PROCEDURES

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

33 56 10 FACTORY-FABRICATED FUEL STORAGE TANKS

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1

SECTION 01 33 00 Page 1

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 33 00

SUBMITTAL PROCEDURES

PART 1 GENERAL

1.1 SUMMARY

1.1.1 Submittal Information

1.1.2 Project Type

1.1.3 Submission of Submittals

1.2 DEFINITIONS

1.2.1 Submittal Descriptions (SD)

1.2.2 Approving Authority

1.2.3 Work

1.3 SUBMITTALS

1.4 SUBMITTAL CLASSIFICATION

1.4.1 Government Approved (G)

1.4.1.1 Approval Codes

1.4.2 For Information Only

1.5 PREPARATION

1.5.1 Transmittal Form

1.5.2 Submittal Format

1.5.2.1 Format of SD-01 Preconstruction Submittals

1.5.2.2 Format for SD-02 Shop Drawings

1.5.2.2.1 Drawing Identification

1.5.2.3 Format of SD-03 Product Data

1.5.2.3.1 Product Information

1.5.2.3.2 Standards

1.5.2.3.3 Data Submission

1.5.2.4 Format of SD-04 Samples

1.5.2.4.1 Sample Characteristics

1.5.2.4.2 Sample Incorporation

1.5.2.4.3 Comparison Sample

1.5.2.5 Format of SD-05 Design Data

1.5.2.6 Format of SD-06 Test Reports

1.5.2.7 Format of SD-07 Certificates

1.5.2.8 Format of SD-08 Manufacturer's Instructions

1.5.2.8.1 Standards

1.5.2.9 Format of SD-09 Manufacturer's Field Reports

1.5.2.10 Format of SD-10 Operation and Maintenance Data (O&M)

1.5.2.11 Format of SD-11 Closeout Submittals

1.5.3 Source Drawings for Shop Drawings

1.5.3.1 Source Drawings

1.5.3.2 Terms and Conditions

1.6 QUANTITY OF SUBMITTALS

1.6.1 Number of SD-04 Samples

1.7 INFORMATION ONLY SUBMITTALS

1.8 PROJECT SUBMITTAL REGISTER

1.8.1 Submittal Management

1.8.2 Preconstruction Use of Submittal Register

SECTION 01 33 00 Page 2

1.8.3 Contractor Use of Submittal Register

1.8.4 Approving Authority Use of Submittal Register

1.8.5 Action Codes

1.8.5.1 Contractor Action Codes

1.8.6 Delivery of Copies

1.9 VARIATIONS

1.9.1 Considering Variations

1.9.2 Proposing Variations

1.9.3 Warranting that Variations are Compatible

1.9.4 Review Schedule Extension

1.10 SCHEDULING

1.11 GOVERNMENT APPROVING AUTHORITY

1.11.1 Review Notations

1.12 DISAPPROVED SUBMITTALS

1.13 APPROVED SUBMITTALS

1.14 APPROVED SAMPLES

1.15 WITHHOLDING OF PAYMENT

1.16 STAMPS

PART 2 PRODUCTS

PART 3 EXECUTION

-- End of Section Table of Contents --

SECTION 01 33 00 Page 3

SECTION 01 33 00

SUBMITTAL PROCEDURES

1.1 SUMMARY

1.1.1 Submittal Information

The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections. Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.

Units of weights and measures used on all submittals are to be the same as those used in the contract drawings.

1.1.2 Project Type

The Contractor's Quality Control (CQC) System Manager are to check and approve all items before submittal and stamp, sign, and date indicating action taken. Proposed deviations from the contract requirements are to be clearly identified. Include within submittals items such as:

Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals (including parts list); certifications; warranties; and other such required submittals.

1.1.3 Submission of Submittals

Schedule and provide submittals requiring Government approval before acquiring the material or equipment covered thereby. Pick up and dispose of samples not incorporated into the work in accordance with manufacturer's Safety Data Sheets (SDS) and in compliance with existing laws and regulations.

1.2 DEFINITIONS

1.2.1 Submittal Descriptions (SD)

Submittal requirements are specified in the technical sections. Examples and descriptions of submittals identified by the Submittal Description (SD) numbers and titles follow:

SD-01 Preconstruction Submittals

Submittals that are required prior to or at the start of construction (work) or the next major phase of the construction on a multiphase contract.

Preconstruction Submittals include schedules…