SOW.pdf
PDF 791 KB Posted
- Attached to
- Gravel Supply and Delivery BPA
- Solicitation number
- 12444126Q0058
- Issued by
-
Department of Agriculture Forest Service
About this file
This is a Statement of Work (SOW) for an Aggregate Blanket Purchase Agreement (BPA) with the National Forests in North Carolina for road maintenance at Croatan National Forest. The project involves hauling and tail-spreading 5,060 tons of Aggregate Base Course (ABC) along NFSR 766 Bender Rd and NFSR 122 Briery branch Rd to address existing potholes, washout, and low-lying road sections. The work is located in Croatan National Forest in North Carolina, with contract execution scheduled for 08 June 2026. The contractor must contact James Mixson (252-617-9231) to coordinate specific scheduling and spreading locations.
The contractor is responsible for supplying all materials, labor, tools, equipment, cranes, vehicles, supplies, supervision, and safety measures to complete the project. Work hours are restricted to between sunrise and sunset, any day of the week, with no potable water, electrical power, or toilet facilities available at project sites. All work must comply with FP-24 specifications, product manufacturer specifications, OSHA requirements, and contract plans. Contractor-furnished products include NCDOT ABC and #4 aggregate, Class A Rip Rap per NCDOT standards, and traffic control devices compliant with MUTCD standards for low-volume roads. Key execution requirements include providing vendor mill stamps or compliance letters upon delivery, coordinating with government to minimize operational interruptions, providing certified flaggers (ATSSA, National Safety Council, or state DOT certification), performing daily tire laceration hazard inspections with magnets, locating and protecting utilities, and maintaining temporary traffic control devices to acceptable standards with replacement of marginal devices within 48 hours and unacceptable devices immediately. Aggregate compaction must achieve at least 95 percent of maximum density per AASHTO T 99 or approved alternative methods.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFQ BPA Call 12444126Q0045.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work (SOW)
Aggregate Blanket Purchase Agreement NFSR 136 South Flybus Rd
Croatan National Forest National Forests in North Carolina
08 JUNE 2026
Existing Conditions
Several roads in the Croatan National Forest have potholes, washout, and low-lying sections. These areas need constant maintenance and additional aggregate to sustain the road prism that is existing.
General.
This BPA calls involves:
Hauling and tail-spreading 5060 tons of Aggregate Base Course (ABC) along NFSR 766 Bender Rd and NFSR 122 Briery branch Rd.
Contact James Mixson (252-617-9231) to communicate schedule and actual locations to spread along the NFSRs.
1. The contractor shall supply all material, labor, tools, equipment, cranes, vehicles, supplies, incidentals, supervision, and safety measures to complete the project.
2. The contractor shall be responsible to verify the necessary quantities of materials to be supplied and volumes of materials required to execute project requirements as described in the plans.
3. Hours of work shall be any time after sunrise and before sunset any day of the week. Potable water, electrical power, and toilet facilities are not available at the project sites.
4. All work shall be done in accordance with FP-24, product manufacturer specifications, plans, OSHA and this document.
Terms, Format, and Definitions
These specifications are generally written in the imperative mood. In sentences using the imperative mood, the subject, “the Contractor,” is implied. Also implied in this language are “shall,” “shall be,” or similar words or phrases. In material specifications, the subject may also be the supplier, fabricator, or manufacturer supplying material, products, or equipment for use on the project.
Wherever “directed,” “required,” “prescribed,” or other similar words are used, the “direction,” “requirement,” or “order” of the Contracting Officer is intended. Similarly, wherever “approved,” “acceptable,” “suitable,” “satisfactory,” or similar words are used, the words mean “approved by,” “acceptable to,” or “satisfactory to” the Contracting Officer.
The word “will” generally pertain to decisions or actions of the Contracting Officer.
When there is no pay item in the Schedule of Items, no direct payment is made. Activities not explicitly described are considered incidental to the task.
The first four digits of the pay item number in the Schedule of Items correlate with the specification which is a section or subjection of the FP-14 with Forest Service Supplemental Specifications written in where it supersedes the FP-14. The digits following the first four digits identify individual line items.
Whenever these abbreviations are used in the specifications, they represent the following:
(a) Acronyms AA – Aluminum Association AASHTO – American Association of State Highway and Transportation Officials ADA – Americans with Disabilities Act AFPA – American Forest and Paper Association AGC – Associated General Contractors of America ANSI – American National Standards Institute ASTM – American Society for Testing Materials CFR – Code of Federal Regulations 5 CO – Contracting Officer and all representatives COR – Contracting Officer’s Representative ER – Engineering Representative FHWA – Federal Highway Administration FICA – Federal Insurance Contributions Act FLH – Federal Lands Highways FSS – Federal Specifications and Standards FUTA – Federal Unemployment Tax Act GSA – General Services Administration ITE – Institute of Transportation Engineers LS – Lump Sum MSHA – Mine Safety and Health Administration MUTCD – Manual on Uniform Traffic Control Devices (for Streets and Highways) NESC – National Electrical Safety Code NFPA – National Forest Products Association NIST – National Institute of Standards and Technology OSHA – Occupation Safety and Health Administration PVC – Polyvinyl Chloride PW – Public Works SAE – Society of Automotive Engineers SF – Standard Form SI – International System of Units STA – Station TS – Timber Sale 6 UL – Underwriter’s Laboratory U.S. – United States USC – United States Code USGS – United States Geological Survey USPS – United States Postal System
(b) Symbols d — daytime h — hour time min — minute time s — second time mp — mile post location ppm — parts per million quantity º — degree plane angle ‘— minute plane angle “— second plane angle
(c) Slope notation (vertical: horizontal). For slopes flatter the 1V:1H, express the slope as the ratio of one unit vertical to a number of units horizontal. For slopes steeper than 1V:1H, express the slope as the ratio of a number of units vertical to one unit horizontal.
The following definitions apply to this contract:
Adjustment in Contract Price – “Equitable adjustment” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.
Award – The written acceptance of a bid by the CO.
Backfill – Material used to replace or the act of replacing material removed during construction. Material placed or the act of placing material adjacent to structures.
Place excavated material in a manner that will not impede water flow or potentially increase sedimentation of waters. Shape inslopes and backslopes to promote revegetation and soil stabilization. Slopes of 1.5:1 or flatter are preferred if terrain permits. Compact fill material to reduce entry of water, increase load carrying capacity and minimize settling. Deposit excess material in stable locations away from streams, lakes, wetlands, and seasonal ponds. Shape and stabilize borrow pits and excess material. Limit the area excavated to that which can be properly shaped and compacted within a day, with provisions for storm drainage and sedimentation control.
Base – The layer or layers of material placed on a subbase or subgrade to support a surface course.
Bidder – Any individual or legal entity submitting a bid.
Bid Guarantee – A form of security assuring that the bidder will not withdraw a bid within the period specified for acceptance and will execute a written contract and furnish required bonds.
Change – “Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.
Commercial Certification – See subsection 106.03.
Construction Limits – The limits on each side of the project that establish the area disturbed by construction operations and beyond which no disturbance is permitted. Typically, the construction limits are the same as the clearing limits, except when additional clearing is required.
Contract – The written agreement between the Government and the Contractor setting forth the obligations of the parties for the performance of and payment for the prescribed work.
Contracting Officer (CO) – An official of the Government with the authority to enter into, administer, and terminate contracts and make related determinations and findings. The term includes certain authorized representatives of the CO acting within the limits of their authority as delegated by the CO.
Contractor – The individual or legal entity contracting with the Government for performance of prescribed work. In a Timber Sale Contract, the Contractor is the “Purchaser.”
Contract Time – The specified time allowed for completion of all contract work.
Cross Section – A vertical section of the ground or structure at right angles to the centerline or baseline of the roadway or other work.
Danger Tree – Any tree or its parts that will fail because of a defect and cause injury to people.
Forest Service – An agency of the United States Department of Agriculture managing public lands in national forests and grasslands.
Government – The Government of the United States of America.
Layer – See “Lift.”
Lift – Defined as follows:
When placing and compacting soils and aggregates, a lift is any single continuous layer of material that receives the same compaction effort during a single work operation.
When installing culvert pipe less than or equal to 48 inches in diameter, the backfill material placed on both sides of the pipe is considered to be contained in the same lift when the material is placed to the same elevation on both sides of the culvert, the compaction effort applied to one side of the culvert is the same as that applied to the other, and the compaction effort is applied to both sides of the pipe in a continuous operation.
Unless the culvert is a ditch relief and when installing culvert pipe less than or equal to 48 inches in diameter, the backfill material placed on both sides of the pipe is considered to be contained in a slope determined lift when the material is placed to different elevations the compaction effort applied to the road side of the culvert is the same as that applied to the slope slide, and the compaction effort is applied to both sides of the pipe in a continuous operation with variances applied due to depth changes.
Material – Any substance specified or necessary to satisfactorily complete the contract work.
Maximum Particle Size – The smallest sieve opening through which all particles in the material will pass. Measurement – The process of identifying the dimensions, quantity, or capacity of an item. See section 109 for measurement methods, terms, and definitions.
Pavement Structure – The combination of subbase, base, geotextiles, and surface courses placed on a subgrade to support and distribute the traffic load to the roadbed.
Pay Item – A specific item of work for which a unit and price is provided in the contract.
Payment Bond – The security executed by the Contractor and surety or sureties and furnished to the Government to ensure payments as required by law to all persons supplying labor or material according to the contract.
Performance Bond – The security executed by the Contractor and surety, or sureties furnished to the Government to guarantee completion of the contract work.
Pioneer Road – Temporary construction access built along the route of the project.
Plans – The contract plans furnished by the Government showing the location, type, dimensions, and details of the work.
Production Certificate – See subsection 106.03
Professional Engineer – Engineers who hold valid State licenses permitting them to offer engineering services directly to the public, who are experienced in the work for which they are responsible, who take legal responsibility for their engineering designs, and who are bound by a code of ethics to protect the public health.
Profile Grade – The trace of vertical plane intersecting a particular surface of the proposed road construction located as shown on the plans, usually along the longitudinal centerline of the roadbed. Profile grade means either elevation of gradient or trace according to the context.
Project – The specific section of the highway road or other property on which construction is to be performed under the contract.
Purchaser – The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.
Protected Streamcourse – A drainage shown on the plans or timber sale area map that requires designated mitigation measures.
For all culverts, ensure that the bottom is either surface-flush and allows for unrestricted hydrological flows, and is safe, sound, and feasible for the long-term operability and function of the culvert; Or that riprap or other materials designated and approved by the CO are placed in a way that is flush with the bottom of the pipe to allow for the unrestricted passage of wildlife through the entirety of the culvert. Install drainage structures as construction proceeds. Install culverts at grades 2% more than the ditch grade and angled at least 30 degrees from perpendicular to the flow of water to improve inlet efficiency. Provide adequate drainage for road grades during construction to minimize erosion of unconsolidated materials.
Retain out slope drainage and minimize berms on the outside edge during construction operations, except those intentionally constructed for protection of road grade fills. Provide temporary cross-drainage structures (such as water bars) during construction where needed. Install siltation barriers, such as silt fences and straw bales, during construction in sites where roads and water have close contact for extended periods. See Culvert Standard Specifications.
Right-of-Way – Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.
Road – See figure 101.1 Illustration of road structure terms.
Roadbed – The graded portion of a road prepared as a foundation for the subsequent layers of structure and shoulders.
Road Order – An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.
Roadside – All area within the right-of-way excluding the traveled way and shoulders.
Roadway – A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) real property necessary for the project, including roadway, buffer areas, access, and drainage areas.
Roadway Prism – The volume defined by the area between the original terrain cross section and the final design cross section multiplied by the horizontal distance along the centerline of the roadway.
Avoid creating a corridor of debris. Do not leave jackstrawed or overturned stumps in immediate foreground. Reduce height of dozed clearing debris during road construction. See Diagrams Defining The Road Prism.
Schedule of Items – A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, unit price, and amount.
Shoulder – The portion of the roadway contiguous to the traveled way for accommodation of stopped vehicles, for emergency use, and for lateral support of the pavement structure.
Specifications – The written requirements for performing work.
Standard Forms – Numbered forms issued by the General Services Administration for use as contract documents.
Standard Plans – Detailed plans approved for repetitive use and included as part of the plans.
Station – (1) A measure of distance used for roads and other linear features. A station is equal to 100 feet. (2) A precise location along a survey line.
Structures – Bridges, culverts, catch basins, drop inlets, retaining walls, cribbing, manholes, endwalls, buildings, sewers, service pipes, underdrains, foundation drains, and other constructed features that may be encountered in the work.
Subbase – The layer or layers of material placed on a subgrade to support a base.
Subcontract – The written agreement between the Contractor and an individual or legal entity prescribing the performance of a specific portion of the work.
Subcontractor – An individual or legal entity with which the Contractor sublets part of the work. This includes all subcontractors in any tier.
Subgrade – The top surface of a roadbed upon which the pavement structure and shoulders are constructed. Substantial Completion – The point at which a project is complete such that it can be safely and effectively used without further delays, disruption, or other impediments.
Suitable Material – Rock or earth material that will provide stable foundations, embankments, or roadbeds, and is reasonably free or organic matter, roots, muck, sod, or other detrimental material. Suitable material may require drying or adding water, root picking, and other methods of manipulation before use. Suitable material includes the classifications of materials for which the project was designed.
Superintendent – The Contractor’s authorized representative in responsible charge of the work.
Surety – An individual or corporation legally liable for the debt, default, or failure of a Contractor to satisfy a contract obligation.
Surface Course – The top layer or layers of a pavement structure designed to accommodate the traffic load and resist skidding, traffic abrasion, and weathering.
Thousand Board Feet (Mbf) – 1,000 board feet based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job. For glued laminated timber, 1,000 board feet based on actual width, thickness, and length of each piece actually incorporated in the job. (One board foot equals 1 inch by 12 inches by 12 inches.)
Timber Sale – A Government issued contract for the removal of timber from National Forest System lands.
Traveled Way – The portion of the roadway designated for the movement of vehicles, including curve widening, exclusive of shoulders.
Unsuitable Material – Material not capable of creating stable foundations, embankments, or roadbeds. Unsuitable material includes muck, sod, or soils with high organic content.
Utilization Standards – The minimum size and percent soundness of trees described in the PLANS to determine merchantable timber.
Work – The furnishing of all labor, material, equipment, and other incidentals necessary to successfully complete the project according to the contract.
Products.
1. Government furnished property: None.
2. Source of Supply and Quality Requirements: Select sources and provide acceptable material. Notify the CO of all proposed sources before delivery to the project to expedite material inspection and testing. Do not incorporate material requiring submittal into the work until approved. Material may be approved at the source of supply before delivery to the project. Approval does not constitute acceptance. If an approved source does not continue to supply acceptable material during the life of the project, further use of that source may be denied.
3. Contractor furnished products: All. Including but not limited to the following:
a. NCDOT – ABC and #4
b. NCDOT Class A Rip Rap
Location
Execution: Contractor coordination.
1. The Contractor shall provide vendor mill stamps or letter of compliance with material specifications upon delivery.
2. The Contractor shall coordinate with the Government to minimize interruptions of public and private operations.
3. The Contractor shall provide traffic control service and markers compliant with MUTCD for low volume roads.
4. The Contractor shall locate and protect all utilities during construction.
5. The Contractor shall locate, protect, or perpetuate any survey monuments or property corners within the construction limits of the jobsite.
6. The Contractor shall coordinate with the Government to have any vehicles moved which may hinder contractor operations.
7. The contractor shall police for tire laceration hazards with a magnet daily.
Execution: Culverts, Gates, Objects, & Roads Installation, Maintenance, & Removal.
Performance standards are as follows:
ITEM
NUMBER
DESCRIPTION
15100 Section 152. MOBILIZATION WITH TEMPORARY TRAFFIC CONTROL Requirements
151.01 Mobilization This work consists of moving personnel, equipment, material, and incidentals to the project and performing all work necessary before beginning work at the project site. Mobilization includes the obtaining of permits, insurance, and bonds. Do not disturb material, drainages, and vegetation outside the road prism limits.
635.01 Temporary Traffic Control. See section 63500
106.00 All equipment proposed to be used for performance of the work must be of the size, type, number and in such condition to properly pursue the requirements of this contract. Grading equipment must be capable of cutting, crowning and shaping operations necessary to meet the requirements of Activity Codes applicable in the technical (performance standards) requirements and Typical Section Drawings.
The Contractor's proposed equipment must be made available for inspection prior to award of the contract. If at any time during the course of this contract the equipment is deemed unsatisfactory, the CO may order removal and may require a satisfactory replacement, at Contractor's expense. Replacement equipment, if ordered, is to be onsite and working within 48 hours.
Any movement or transportation of equipment to or from work areas required to pursue the work on designated roads, to repair or replace equipment, or for the Contractor's convenience must be at the Contractor's expense.
Speed Limit. An operating speed limit for all equipment operating or performing operations of any kind other than movement for transportation, will not, at any time, exceed 5 miles per hour.
Work conducted by vehicles moving over 5 miles per hour will be considered as unsatisfactory.
Moreover, any damage caused by vehicles or workers are the responsibility of the Contractor.
Failure to comply with the speed limit will be considered a safety violation and the final measures of enforcement will be issued by the CO.
Worker Safety Training. An extremely important safety strategy. The type and amount of training depends on job duties and responsibilities of assigned workers to tasks. Training is needed to operate most tools and machinery. Training should provide information on the use of personnel protection equipment, occupational hazards and health risks, and other pertinent topics.
Many resources are available to ensure that workers receive proper work zone safety training, including commercial training services and products. The National Work Zone Safety Information Clearinghouse has many training resources relevant to highway worker safety at http://www.workzonesafety.org/. These include a variety of free training resources developed through the national Work Zone Safety Grant program see at http://www.workzonesafety.org/fhwa_wz_grant. As part of the grant effort, the Roadway Safety Program+ is a valuable software training tool that can be downloaded free of charge.
In addition to all the topics listed above, it contains safety training modules on:
• excavation, equipment operation, and electrical work.
• runovers/back overs, falls, sprains/strains, struck/crush injuries; and
• health issues associated with outdoor working environments.
The FHWA also maintains a database of worker training programs available at:
http://ops.fhwa.dot.gov/wz/outreach/wz_training/worker_safety.htm.
Many unions and trade associations also offer highway work zone safety training.
Depending on the duties of the worker, training pertaining to the various worker safety training programs should provide instruction consistent with the requirements described in ANSI/ASSE A10.47-2009: Work Zone Safety for Highway Construction standard. The training should also be consistent with other national standards pertaining to highway work zone design and operation (e.g., the Roadside Design Guide, the national MUTCD, etc.).
Actions That Lead to Good Risk Management. Managing risk requires an initiative-taking approach. Below is a set of actions that may be taken to improve their risk management position.
• Requiring and implementing regular work zone traffic control inspections as a matter of policy.
• Moving in a timely manner to resolve any deficiencies in a reasonable and timely fashion, which may include notifying others and following up on their response.
• Installing signing or other notifications for a hazardous condition if an immediate resolution is not possible or is too expensive, and documenting how and why this decision was reached; and
• Demonstrating a priority list of actions on deficient conditions if fiscal constraints prevent immediate action.
Safe and Effective Work Zone Inspections. The key to a successful work zone inspection program can be summed up with four critical elements. The must have:
• Overarching policies that clearly spell out responsibilities and competencies for individuals involved in the work zone inspection program communicating from agency to project levels.
• A monitoring program that regularly evaluates the effectiveness of agency policies and project-level actions.
• A standardized procedure for program and project deficiency identification and follow-up; and
• A process that fold’s feedback on performance back into the program.
These guidelines should provide the practitioner with the necessary knowledge to accomplish the following objectives:
• Recognize the value of work zone inspections to:
o Increase safety for workers and motorists.
o Increase compliance with applicable design standards and Federal requirements.
o Improve mobility through the work zone; and o Serve as an agency risk management tool.
• Set up a program – by establishing inspection program elements at the project levels to help develop a comprehensive, initiative-taking, and effective work zone inspection program, or confirm and enhance elements currently in place.
• Make a program successful and maximize benefits – this is accomplished by proper training, effective policies, making the inspection program an integral part of doing business for the agency, and ensuring there is a feedback mechanism to fold performance analyses back into the inspection program.
• See the big picture – seeing how the various components of project-level inspections interrelate with the agency’s statement of objectives.
Measurement
151.02 Measure the Section 151 items listed in the bid schedule according to Subsection 109.02.
20910 209.10 Compacting. Determine optimum moisture content and maximum dry density according to AASHTO T 99, Method C. Adjust the moisture content of the backfill material to a moisture content suitable for compaction.
Compact material placed in all layers to at least 95 percent of the maximum density. Determine the in-place density and moisture content according to AASHTO T 310 or other approved test procedures.
Do not apply density requirements as measured by AASHTO T 310 to material incapable of being tested or compacted to maximum values determined by AASHTO T 99. For these material, fill the voids around the rock in each layer with earth or other fine material. Compact each layer until there is no visible evidence of further consolidation.
30105 301.05 Aggregate Surface Course. NCDOT ABC. Shape base course to desired template and finish elevation to allow designed depth of surface course. Emplace crushed aggregate to the width and depth specified in the plans. Match grades for smooth transitions to existing surfaces. Compact each layer full width. Roll from the sides to the center, parallel to the centerline of the road. Along curbs, headers, walls, and all places not accessible to the roller, compact the material with approved tampers or compactors.
Compact the aggregate using one of the following methods as specified:
Compaction A. Operating spreading and hauling equipment over the full width of the travelway.
Compaction B. Operate rollers and compact as specified in Subsection 204.11(a)(1).
Compaction C. Moisten or dry the aggregate to a uniform moisture content between 5 and 7 percent based on total dry weight of the mixture. Operate rollers and compact as specified in Subsection 204.11(a)(1).
Compaction D. Compact to a density of at least 95 percent of the maximum density, as determined by AASHTO T 99, method C or D.
Compaction E. Compact to a density of at least 96 percent of the maximum density, as determined by the Modified Marshall Hammer Compaction Method (available upon request from USDA Forest Service, Regional Materials Engineering Center, P.O. Box 7669, Missoula, MT 59807).
Compaction F. Compact to a density of at least 95 percent of the maximum density, as determined by AASHTO T 180, method C or D.
Compaction G. Compact to a density of at least 100 percent of the maximum density as determined by the Modified Marshall Hammer Compaction Method (available upon request from USDA Forest Service, Regional Materials Engineering Center, P.O. Box 7669, Missoula, MT 59807).
For all compaction methods, blade the surface of each layer during the compaction operations to remove irregularities and produce a smooth, even surface, When a density requirement is specified, determine the in place density and moisture content according to AASHTO T 310 or other approved test procedures.
63500 635.01 This work consists of furnishing, installing, maintaining, relocating, and removing temporary traffic control devices and services as ordered for the control and protection of public traffic through the project.
Advance warning arrow board, barricade, and warning light types are designated in the MUTCD.
Material
635.02 Conform to the MUTCD and the following Sections and Subsections:
Concrete barrier (temporary) 618 Delineator and object marker retroreflectors 718.08(b) Guardrail (temporary) 617 Retroreflective sheeting 718.01 Sign panels 633.05 Sign posts 633.04 Temporary plastic fence 710.11 Temporary pavement markings 718.16
Construction Requirements
635.03 Qualifications. Provide flaggers certified by ATSSA, the National Safety Council, a state department of transportation, or other acceptable organization. Use pilot car operators conforming to the qualifications of a flagger.
635.04 General. Furnish, install, and maintain temporary traffic control devices adjacent to and within the project as required by the MUTCD, traffic control plan, and Section 156. Install and maintain traffic control devices as follows:
(a) Furnish and install traffic control devices before the start of construction operations;
(b) Install only those traffic control devices needed for each stage or phase;
(c) Relocate temporary traffic control devices as necessary;
(d) Remove devices that no longer apply to the existing conditions;
(e) Immediately replace devices that are lost, stolen, destroyed, or inoperative;
(f) Keep temporary traffic control devices clean;
(g) Furnish and maintain traffic control devices that meet the "acceptable" standard described in ATSSA, Quality Standards for Work Zone Traffic Control Devices. Amend the ATSSA standards as follows:
(1) Repair or remove and replace "marginal" devices within 48 hours; and
(2) Repair or remove and replace "unacceptable" devices immediately;
(h) Remove temporary traffic control devices upon contract completion or when approved; and
(i) Furnish crashworthy temporary traffic control devices.
70502 705.02 Riprap This work shall consist of furnishing and placing erosion resistant and protective materials on the slopes of embankments, stream banks, on bottom and side slopes of channels, at bridge abutments and wing walls, at structure foundations and at other locations. Rip Rap shall be placed as staked by the Contracting Officer and/or IAW plans.