This is a Specification Sheet/Statement of Work for the procurement of electronic circuit breaker units and supporting components for the GoSWIFT (Goodrich Straightwing Flight Integration Test) project at NASA Armstrong Flight Research Center.
The primary deliverables consist of two Astronics 28Vdc Electronic Circuit Breaker Units (P/N 1448-113, quantity 2) and two Astronics 115Vac Electronic Circuit Breaker Units (P/N 1448-111, quantity 2), selected for their proven flight heritage on other NASA Armstrong aircraft and cost and schedule savings versus custom development. Supporting components include multiple connector plugs and receptacles (P/N 23-00123-001, 23-00121-001, 23-00123-003, 23-00121-006) and backshell cable clamps (P/N 20-00076-003, 20-00076-009, 20-00076-006) in specified quantities. All deliverables must meet NASA Quality Document Q1-B compliance requirements with no approved alternatives. Standard manufacturer's warranty is acceptable, though warranty may be voided upon NASA's workmanship inspection. Delivery is required by March 1, 2027, to NASA Armstrong Flight Research Center, Building 4876 Warehouse #6, Lilly Drive, Edwards, California 93524. If freight shipment is necessary, coordination must occur at least four business days in advance to facilitate proper entry procedures at Edwards Air Force Base, potentially requiring submission of an AFRC visitor request.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPEC SHEET/ STATEMENT OF WORK
1. Objective/Requirements Flight and spare Vdc and Vac Electronic Circuit Breaker Units (Astronics 1448-113 and 1448-111) have been selected to provide safe and controllable power distribution required for the GoSWIFT function. These parts have the form/fit/function required to both accomplish the GoSWIFT requirement as well as save schedule and costs vs building a custom powr distribution system. These parts have extensive flight heritage on other NASA Armstrong aircraft.
No alternates approved.
NASA Quality Document Q1-B compliance required
2. Characteristics, Scope, and Specs
Main equipment:
P/N 1448-113: 28Vdc Electronic Circuit Breaker Unit (qnty = 2) P/N 1448-111: 115Vac Electronic Circuit Breaker Unit (qnty =2)
Supporting connectors and backshells:
23-00123-001 connector, plug (qnty = 2) 23-00121-001 connector, rcpt (qnty = 2) 20-00076-003 backshell cable clamp (qnty = 4) 20-00076-009 backshell cable clamp (qnty = 2) 23-00123-003 connector, plug (qnty = 2) 23-00121-006 connector, rcpt (qnty = 2) 20-00076-006 backshell cable clamp (qnty = 2)
3. Place of Performance or Delivery Location NASA Armstrong Flight Research Center Bldg 4876 Warehouse #6, Lilly Drive Edwards, CA 93524
4. Period of Performance or delivery date/need by date required Needed not later than 3/1/2027
Warranty requirements? Standard manufacturer’s warranty OK. Warranty may be broken when we conduct workmanship inspection.
Broker import requirements, if applicable. N/A
Freight Delivery requirements, if applicable. – N/A
*If FREIGHT shipment is required, it needs to be coordinated 4 business days in advance to ensure the delivery driver has proper entry into Edwards Air Force Base. An AFRC visitor request may need to be submitted.