SOW.docx
DOCX document 1 MB Posted
- Attached to
- USCG Station Destin Gate/Fence Repair
- Solicitation number
- 70Z02924QNEWO0001
About this file
This document is a Statement of Work (SOW) for the replacement of a front gate opener and fence repairs at the U.S. Coast Guard Station in Destin, Florida. The key details are:
The contractor shall provide all labor, parts, and materials necessary to remove the old gate opener assembly and keypad, and install a new gate opener and keypad. The contractor shall also make repairs to approximately 1,200 feet of degraded fencing, including the addition of new barbed wire. The work must be completed within 30 days of award. The government will provide access to utilities such as electricity, water, and restrooms. The contractor must coordinate closely with the government's point of contact to minimize impacts to Coast Guard operations. All work must be approved by the Contracting Officer's Representative. The contractor is responsible for maintaining a safe work site and providing a written safety plan.
The related federal contract opportunity is a Request for Quotation (RFQ) for the same gate and fence repair work at the U.S. Coast Guard Station in Destin, Florida. This is a small business set-aside with a 30-day period of performance. Quotes are due by 5:00 pm CST on July 12, 2024, and should be submitted to the email address provided.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SF-18.pdf | ||
| Construction Clauses Provisions FAC 2023-01 - Copy.doc | DOC document | |
| Wage Rates.txt | TXT text file |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Department of Homeland Security United States Coast Guard
Scope of Work For Replacement of Front Gate Opener and Fence Repairs At U.S. Coast Guard Station Destin, Florida
13 MAY 2024
United States Coast Guard
TABLE OF CONTENTS
| Section |
| Title |
| Page |
| 1 |
| General Contracting Guidelines |
| 3 |
| 2 |
| Submittals and Outcome |
| 3 |
| 3 |
| Project Performance Timeline |
| 3 |
| 4 |
| Location |
| 3 |
| 5 |
| Point of Contact |
| 3 |
| 6 |
| Lease Agreement Terms |
| 4 |
| 7 |
| Work Phasing/Scope of Work |
| 4 |
| 8 |
| Availability of Utilities |
| 5 |
| 9 |
| Coordination |
| 5 |
| 10 |
| Contractor Use of Premises |
| 5 |
| 11 |
| Laydown Area |
| 5 |
| 12 |
| Storm Protection |
| 5 |
| 13 |
| Environmental Protection |
| 6 |
| 14 |
| Delivery and Storage |
| 6 |
| 15 |
| Receipt of Materials |
| 6 |
| 16 |
| Cleanup |
| 6 |
| 17 |
| Utility Outages |
| 6 |
| 18 |
| Security |
| 6 |
| 19 |
| Quality |
| 7 |
| 20 |
| Warranties |
| 7 |
| 21 |
| Final Inspection and Acceptance |
| 7 |
| 22 |
| Safety |
| 7 |
| 23 |
| Photos |
| 8 |
| 23 |
| Site Plan/Drawing |
| Enclosed |
1 General Contracting Guidelines:
1.1: For the execution of this contract, contractor shall provide all labor, parts, and materials not described in this Scope of Work. Government Furnished materials will be outlined in this scope of work and will be defined as GFM.
1.2: Contractor shall make all reports to the Contracting Officer/On site supervisor in regards to progress of the scheduled work log. If there are questions or concerns regarding the scope of work and/or the work log, the contractor shall not proceed further without guidance from the Contracting Officer.
1.3: Contractor shall provide all necessary documentation for all employees (Valid State ID, Drivers Licenses, etc.). As well any vehicle brought on board any Coast Guard/Military Facility shall have valid state registration and insurance.
1.4: Contractor shall execute the contract IAW this Scope of Work. The contractor is not authorized to deviate from this Scope of Work without written authorization from the Contracting Officer.
1.5: The contractor shall provide a list of all employees that will be working on Coast Guard property to the Contracting Officer prior to the scheduled work days.
2 SUBMITTALS AND OUTCOMES
2.1 The Contractor shall submit a work schedule including all milestones immediately following contract award.
2.2 Submit removal and application procedures for all building surfaces.
3 PROJECT PERFORMANCE TIME
The contractor must make notification to the Contracting Officer and MKC Flanigan inventory availability and estimate time of arrival for required equipment.
4 LOCATION
All work shall take place at:
U.S. Coast Guard Station Destin 2000 Miracle Strip Pkwy Destin, FL 32540
5 POINT OF CONTACT
The Government Point of Contact (POC) for this work is BMC Nathaniel Lawellin (850) 224-7147, Nathaniel.m.lawellin@uscg.mil.
Onsite support/supervisor is MKC Daniel Flanigan (315) 406-2736, daniel.p.flanigan@uscg.mil. All work shall be coordinated through both POC’s to minimize operational impacts to the unit during the execution of the work.
6 LEASE AGREEMENT TERMS
N/A
7 WORK PHASING/SCOPE OF WORK
Work shall be completed as expeditiously as possible; Contractor shall coordinate with the POC’s to coordinate phasing and job sequencing. Contractor shall submit construction schedule for Government review and approval prior to commencing in any work to be performed.
7.1 SCOPE OF WORK
A. Contractor shall provide ALL labor and materials necessary to complete the project.
B. Contractor shall comply with submittal requirements if applicable.
C. Contractor shall remove old gate opener assembly along with old keypad.
D. Contractor shall install new gate opener assembly as well as a new keypad.
E. Contractor shall make repairs to top of fencing where current fence is degraded to include new barbed wire for approximately 1200 feet.
F. Contractor shall be responsible for the removal of all trash and debris from project area upon completion.
G. All work must be approved by the Contracting Officer’s Representative.
8 AVAILABILITY OF UTILITIES
Reasonable amounts of the following utilities will be made available to the Contractor without charge.
+ Electricity (if available at the job site) + Potable Water + Restroom facilities
9 COORDINATION
The Contractor shall coordinate with the POC to minimize interference with Coast Guard operations or personnel. All work shall be coordinated with other trades involved in the project and carefully laid out in advance.
10 CONTRACTOR USE OF PREMESES
The Contractor will be working on a Coast Guard operational military installation. Become familiar with and obey installations’ fire, traffic, and security regulations. Personnel shall not stray from the immediate area of work nor direct avenues of ingress and egress unless authorized in advance by the Government.
11 LAYDOWN AREA
The Contractor will be provided with an uncovered lay-down area in the immediate vicinity of the work. The Contractor shall be responsible for restoring the area to its original condition at the completion of the work. The Contractor shall be responsible for repair of any damage incurred to buildings, vehicles, boats, equipment, or pavement as a result of storage activities.
12 STORM PROTECTION
Should warnings of extreme weather (such as high waves, storm surge, wind of gale force) be issued, the Contractor shall take every practicable precaution to minimize danger to personnel, the work and adjacent property. Precautions shall include, but not be limited to, relocating equipment, closing all openings, removing all loose materials, tools exposed locations, and removing or securing fencing, scaffolding and other temporary work.
13 ENVIRONMENTAL PROTECTION
All Federal, State and local laws must be strictly adhered to. Demolition and construction debris shall be disposed of at a permitted facility.
14 DELIVERY AND STORAGE
Contractor will be responsible for the delivery and storage of all items pertaining to the job, any damaged items shall be replaced at the vendor’s expense. Coast Guard will provide an area/location to store all items while the job is in process.
15 RECEIPT OF MATERIALS
Shipment of equipment, materials, and supplies shall be addressed to the Contractor - not the Government. The Contractor must be on hand to accept shipments; the Government will not accept shipments.
16 CLEANUP
The Contractor shall keep the work area, including storage areas, free from accumulations of waste materials on a daily basis and comply with all federal, state and local regulations pertaining to the storage, transport and disposal of wastes. The Contractor shall not use Coast Guard waste disposal facilities including garbage cans, trash piles or dumpsters.
17 UTILITY OUTAGES
Before interrupting or shutting down any utility, make a request for the interruption to the POC’s at least two (2) working days before the anticipated interruption. Identify the utility, reason for interruption, proposed time of interruption, and duration of interruption. Do not interrupt utilities until authorized by the POC.
18 SECURITY
18.1 Working Personnel List.
The Contractor shall provide the Contracting Officer and Onsite supervisor with a list of names of all personnel who will be working on the site. The Contractor may submit a revised list at any time during the project. Only personnel on the approved listing will be allowed on the site.
18.2 Personnel Identification
All personnel shall carry proper identification (ID) when on site. Proper ID is defined as either the individual’s driver’s license, or a company issued ID. The identification must be laminated, and show facial picture of the individual. Individuals without proper ID will be escorted off the Coast Guard premises.
19 QUALITY
Quality of Contractor Furnished Material. Materials supplied by the Contractor shall be of a quality conforming to applicable Federal specifications.
20 WARRANTIES
All warranties and/or guarantees, either implied or expressed, for individual equipment shall be endorsed to the Government.
21 FINAL INSPECTION AND ACCEPTANCE
When the work is complete and ready for final inspection, submit a written request to schedule final inspection to the Government. Prior to such requests, all submittals must be complete and approved. Such requests shall allow a minimum of two (2) days’ notice prior to final inspection date.
22 SAFETY
22.1 General
The Contractor is solely responsible for work site safety. The Contractor shall implement a safety program that protects the lives and health of personnel in the construction area, prevents damage to property and avoids work interruptions. The Contractor shall provide appropriate safety measures including, but not limited to barricades, signs and signal lights as well as complying with the requirements of all applicable Federal, State and Local safety laws, rules and regulations.
22.2 Compliance
The Contractor is specifically required to comply with the requirements of the U. S. Army Corps of Engineers "Safety and Health Requirements Manual" (EM 385-1-1, latest version available) and the “Accident Prevention” clause (FAR 52.236-13). Once accepted, this safety plan shall become part of the contract requirements. Note: This review/acceptance does not in any way relinquish the Contractor from responsibility for work site safety nor the obligation to comply with the OSHA regulations found in 29 CFR 1910 & 1926 or any other State or Local safety law, rule or regulation applicable to the contract work. The Coast Guard will cooperate fully with the Department of Labor (Occupational Safety and Health Administration) in their enforcement of OSHA regulations.
22.3 Safety Plan
The Contractor shall submit a written safety plan immediately following contract award. At a minimum, this plan shall describe the Contractor's general safety program and identify specific safety provisions for hazards incidental to the contract work such as elevated working surfaces, working over water, working from floating work platforms, overhead crane operations or similar conditions of the work. This Safety Plan shall be approved prior to commencing any work on site.
GATE OPENER
INSIDE COMPONENTS
KEYPAD
BROKEN BARBED WIRE
image1.png image2.jpeg image3.jpeg image4.jpeg image5.jpeg
File details come from the government source that posted it. Updated .