This statement of work outlines repairs and upgrades to be completed at the West Roxbury VA Medical Center in West Roxbury, Massachusetts under solicitation number 36C24123B0008 from the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 1. The repairs and upgrades include replacing damper and fan components, upgrading control systems, and installing variable frequency drives across 23 air handling units and rooftop units to improve energy efficiency as identified in a previously completed retro-commissioning assessment. The work must be completed within 180 calendar days of the notice to proceed.

View the file

Other files

File Type Posted
BID OPENING information.docx DOCX document
MA WD 7-21-23.txt TXT text file
Site Visit Sheet.pdf PDF
Updated MIL.xlsx XLSX spreadsheet
RFI answers.docx DOCX document
36C24123B0008 0002.docx DOCX document
36C24123B0008 0001.docx DOCX document
36C24123B0008_1.docx DOCX document
MA WD 6-16-23.txt TXT text file
01 00 00 GENERAL REQUIREMENTS.pdf PDF
01 35 26 SAFETY REQUIREMENTS.pdf PDF
01 33 23 SHOP DRAWINGS PRODUCT DATA AND SAMPLES.pdf PDF
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

VISN 1 RETRO-COMMISSIONING (RCx) REPAIRS AT WEST ROXBURY

PROJECT #523A4-22-011

This project will implement recommendations identified by previously completed retro-commissioning (RCx) activities as included as individual item repairs from a RCx Master Issues Log (MIL). This project will include equipment repairs, equipment replacement, and upgrading and/or optimizing Trane controls. All work will be done at the West Roxbury VA Medical Center in West Roxbury, Massachusetts. In general, work shall include all labor, material, equipment, and supervision to perform the required mechanical, electrical, and programmatic work discussed below.

All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.

The Period of Performance for this project is 180 calendar days from the Notice to Proceed.

The goal of this work is to make corrections to existing equipment and systems to improve energy efficiency. All issues within the scope of work are shown below as they were represented in the MIL.

MIL

Issue No.

Survey Date Equipment Name Equipment Building Location;

Room, Roof, or Wing;

and Area Served

Issue Description
Issue Resolution
11
2/16/2021
AC-1
3 - Outpatient

GD-103

Pharmacy/Lobby

The return fan variable frequency drive is essentially disabled as it has been manually set to 75%. This was done in an effort to circumvent an issue with the damaged drive. (Priority: 4 - Facility Improvement)
Replace the drive, place in AUTO mode, and verify the drive's functionality via point-to-point and functional performance testing.
16
2/17/2021
AC-11
3 - Outpatient

2B-106 Research

The outside air damper is stuck open at all times. When the unit was shut down during functional testing, the building automation system showed the outside air damper as being closed. The damper was observed as not physically moving. The actuator is not responding. This could lead to dangerous conditions for the coils during extreme weather conditions if the unit is shut down. (Priority: 1 - Health & Safety)
Replace the damper actuator. Run the actuator through point-to-point and functional performance testing to confirm normal damper operation.
27
11/16/2020
AC-3
3 - Outpatient

GB-111

Clinic/ Admitting

The building automation system displays the outside air damper as being 23% open, the chilled water valve as being 100% open, the outside air temperature as being below the supply air temperature setpoint, and the mixed air temperature as being 13.5˚F above the mixed air temperature setpoint. The outside air damper should open more to limit demand for cooling from the chilled water coil. (Priority: 3 - Energy Conservation)
Review the sequences of operation as it relates to the outside air damper and chilled water-cooling valve. Update the sequences of operation as necessary to optimize the demand for cooling from the chilled water coil.
32
2/18/2021
AC-351
1 - Patient Care

3B-109 3B-113 South x-ray

The return fan variable frequency drive was recently replaced but has not yet been connected to the system. (Priority: 4 - Facility Improvement)
Finish the installation of the drive. Program the drive. Run full point-to-point and functional performance testing.
34
2/16/2021
AC-4
3 - Outpatient

1C-117 Pathology Service

The outside air damper is stuck open at all times. When the unit was shut down during functional testing, the damper was observed as not closing. The damper did not modulate when directly commanded by the building automation system. This could lead to dangerous conditions for the coils during extreme weather conditions if the unit is shut down. (Priority: 1 - Health & Safety)
Replace the damper. Run the damper through point-to-point and functional performance testing to confirm normal operation.
45
2/16/2021
AC-5
3 - Outpatient

1D-100 Cafeteria

One of the actuator anchor bolts is missing. The actuator cannot operate through full range of motion. As a result, the damper cannot move to the 100% open position. (Priority: 2 - VA Guideline Conformance)
Replace the damper actuator. Run the actuator through point-to-point and functional performance testing to confirm normal damper operation.
60
2/16/2021
AC-9
3 - Outpatient

2D-104 Executive Suites

The return fan variable frequency drive does not work. (Priority: 4 - Facility Improvement)
Replace the drive, place in AUTO mode, and verify the drive's functionality via point-to-point and functional performance testing.
62
2/16/2021
AC-9
3 - Outpatient

2D-104 Executive Suites

The economizer damper(s) have been manually overridden to 10%, which is less than the minimum outside air damper position of 15%. The dampers have seized and are not functional. (Priority: 2 - VA Guideline Conformance)
Replace the damper(s). Run the damper(s) through point-to-point and functional performance testing to confirm normal operation.
65
2/17/2021
AHU-2 &

EAHU-2

21 - Research Roof Building 21

One of the outside air damper linkages is broken. The damper actuator responds to the building automation system. As a result, the damper is stuck open. This could lead to dangerous conditions for the coils during extreme weather conditions if the unit is shut down. (Priority: 1 - Health & Safety)
Replace the damper linkage. Run the damper through point-to-point and functional performance testing to confirm normal operation.
117
2/27/2021
OR-6

AHU-1B

2 - Patient Care Penthouse Roof

OR-6

The outside air damper is stuck closed at all times. The damper did not open when the unit was started up. The damper did not modulate when directly commanded by the building automation system. (Priority: 2 - VA Guideline Conformance)
Replace the damper actuator. Run the actuator through point-to-point and functional performance testing to confirm normal damper operation.
141
2/19/2021
S-4
2 - Patient Care

A-401 Patient Rooms

The outside air damper is stuck at 20% open at all times. The damper did not close when the unit was shut down. The damper did not modulate when directly commanded by the building automation system. This could lead to dangerous conditions for the coils during extreme weather conditions if the unit is shut down. (Priority: 1 - Health & Safety)
Replace the damper actuator. Run the actuator through point-to-point and functional performance testing to confirm normal damper operation.
157
2/17/2021
Spinal

AHU-1

1 - Patient Care Roof outside 2B-115 Spinal Cord

The outside air damper is stuck almost closed. The actuator did not respond to the building automation system. There were no changes observed on the building automation system when the damper was directly commanded to modulate. (Priority: 2 - VA Guideline Conformance)
Replace the damper actuator. Run the actuator through point-to-point and functional performance testing to confirm normal damper operation.
158
2/17/2021
Spinal

AHU-1

1 - Patient Care Roof outside 2B-115 Spinal Cord

The return fan variable frequency drive is essentially disabled as it has been placed in HAND mode. (Priority: 4 - Facility Improvement)
Replace the drive, place in AUTO mode, and verify the drive's functionality via point-to-point and functional performance testing.
161
6/3/2021
CT AHU-3
1 - Patient Care

Outside of GC-111 CT Equipment Room GB104

This unit lacks a variable frequency drive for the supply fan. Variable frequency drives can reduce energy used by the fan by lowering the fan speed in situations where less airflow is required. (Priority: 3 - Energy Conservation)
Install a variable frequency drive for the supply fan, program the drive, and run full point-to-point and functional performance testing to confirm normal operation.
162
6/3/2021
Dietetics

AHU-1

1 - Patient Care 2C-117 Dietetics

This unit lacks a variable frequency drive for the supply fan. Variable frequency drives can reduce energy used by the fan by lowering the fan speed in situations where less airflow is required. (Priority: 3 - Energy Conservation)
Install a variable frequency drive for the supply fan, program the drive, and run full point-to-point and functional performance testing to confirm normal operation.
163
6/3/2021
Dietetics

AHU-2

1 - Patient Care Kitchen Dietetics

This unit lacks a variable frequency drive for the supply fan. Variable frequency drives can reduce energy used by the fan by lowering the fan speed in situations where less airflow is required. (Priority: 3 - Energy Conservation)
Install a variable frequency drive for the supply fan, program the drive, and run full point-to-point and functional performance testing to confirm normal operation.
164
6/3/2021
GI Clinic

RTU-1

1 - Patient Care Roof outside 2B-115 GI Clinic

This unit lacks a variable frequency drive for the supply fan. Variable frequency drives can reduce energy used by the fan by lowering the fan speed in situations where less airflow is required. (Priority: 3 - Energy Conservation)
Install a variable frequency drive for the supply fan, program the drive, and run full point-to-point and functional performance testing to confirm normal operation.
165
6/3/2021
Angio

RTU-1

2 - Patient Care Roof between Bldg 1 & 2 Angio

This unit lacks a variable frequency drive for the supply fan. Variable frequency drives can reduce energy used by the fan by lowering the fan speed in situations where less airflow is required. (Priority: 3 - Energy Conservation)
Install a variable frequency drive for the supply fan, program the drive, and run full point-to-point and functional performance testing to confirm normal operation.
167
6/3/2021
Locomat

RTU-3

2 - Patient Care Roof between Bldg 1 & 2 Locomat

This unit lacks a variable frequency drive for the supply fan. Variable frequency drives can reduce energy used by the fan by lowering the fan speed in situations where less airflow is required. (Priority: 3 - Energy Conservation)
Install a variable frequency drive for the supply fan, program the drive, and run full point-to-point and functional performance testing to confirm normal operation.
168
6/9/2021
MRI AHU
1 - Patient Care

GB-177

MRI

While the unit is in heating mode the hot water valve is 100% open and the chilled water valve was noted as being 40% open. The chilled water valve should be locked out when the unit is in heating mode. (Priority: 3 - Energy Conservation)
Review the sequences of operation as it relates to the cooling and heating valves. Update the sequences of operation as necessary to optimize the demand for cooling.
170
6/9/2021
OR-6

AHU-1B

2 - Patient Care Penthouse Roof

OR-6

Diagnostic monitoring trend data indicates heating capacity is greater than zero when the unit is in cooling mode. Heating should be locked out when the unit is in cooling mode. (Priority: 3 - Energy Conservation)
Review the sequences of operation as it relates to the cooling and heating valves. Update the sequences of operation as necessary to optimize the demand for cooling.
174
6/9/2021
AC-2
3 - Outpatient

GA-157

Exam Rooms

While the unit is in cooling mode the chilled water valve is 100% open and the steam valve was noted as being 100% open. The steam valve should be locked out when the unit is in cooling mode. (Priority: 3 - Energy Conservation)
Review the sequences of operation as it relates to the cooling and heating valves. Update the sequences of operation as necessary to optimize the demand for cooling.
193
8/24/2021
AHU-4B
20 - Research

Outside, Ground Level East Section Building 20

Diagnostic monitoring trend data indicates cooling capacity is greater than zero when the unit is in heating mode. Cooling should be locked out when the unit is in heating mode. (Priority: 3 - Energy Conservation)
Review the sequences of operation as it relates to the cooling and heating valves. Update the sequences of operation as necessary to optimize the demand for cooling.

The Contractor shall assume responsibility for all temporary measures adopted during the construction period, to maintain operation of the hospital. This shall include but not be limited to temporary heating/cooling/ventilation, coordinating with the COR to relocate personnel, and/or ensuring that adequate facilities are provided, where deemed necessary.

The West Roxbury VA Medical Center utilizes Trane as the building automation system vendor.