SOW.1.docx
DOCX document 1 MB Posted
- Attached to
- Replace Water heater in Multi building
- Solicitation number
- 3032826Q0000013
About this file
This is a Statement of Work (SOW) for the replacement of water heating systems at United States Coast Guard Station Grand Isle, located at 453 Admiral Craik Dr, Grand Isle, LA 70358. The contractor shall replace two existing water heaters with on-demand replacements meeting minimum specifications for current system demands, install a replacement hot water circulation pump, and install a commercial neutralization tank with natural gas fuel source featuring thermal efficiency of no less than 80 percent and a recovery rate of 193.8 U.S. GPH minimum. The contractor must also install proper piping insulation and brackets for all exhausts, discharges, inlets, and existing related piping. Prior facility inspection is mandatory, with a pre-award conference to be held before work commences.
The base bid scope requires identification of necessary heater replacements, provision of a work schedule to the Contracting Officer's Representative (MKC Bryan Wilson, Bryan.D.Wilson@uscg.mil, 409-539-1313), completion within 60 days of award, removal of existing heaters, installation of new units, proper bracing and bracketing of all hot water piping, leak testing of natural gas connections in the presence of the COR, and operational testing in the presence of the COR. Hot water outage shall not exceed 12 hours to prevent disruption to facility operations. Work must be scheduled during normal operating hours (8:00 AM to 4:00 PM, Monday through Friday, excluding federal holidays) unless otherwise approved. The contractor must provide one week advance notice before work commences and comply with OSHA safety standards, federal and state disposal regulations, Coast Guard facility regulations including daily flag ceremonies, facility security protocols (U.S. citizens and permanent resident aliens only), utility verification procedures, and weather preparedness requirements. All contractor personnel must wear company identification and provide a consolidated list of workers with valid government-issued identification numbers prior to the notice to proceed date.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Question from Mark Jenkins.docx | DOCX document | |
| water heaters.pictures..pdf | ||
| Constructions.Solicitation.docx | DOCX document | |
| SF1442-14b.solicitation.offer.and.award.docx | DOCX document | |
| Construction Clauses.docx | DOCX document | |
| la38.txt | TXT text file |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF HOMELAND SECURITY
UNITED STATES COAST GUARD
STATION GRAND ISLE
SPECIFICATIONS
FOR
STA Building Water Heaters Replace
General: United States Coast Guard Station Grand Isle is accepting proposals for qualified individuals or firms to complete Replacement of stations main building’s 02 water heaters. Contractor shall replace both hot water heaters with suitable on demand replacements meeting the minimum specifications necessary for demands and currently installed systems, replacement of hot water circulation pump, install of commercial neutralization tank with a Natural gas fuel source with a thermal efficiency no less than 80 and a recovery/recuper of 193.8 U.S. GPH minimum. Contractors must install proper piping insulation and brackets for exhausts, discharges and inlets of water heaters as well as the remainder of existing piping located in the space that relates to the heaters. Prior to submitting a quote, it is mandatory to examine the scope of work, and it is highly recommended to visit the facility to take field measurements, evaluations, etc., and become familiar with existing conditions under which the work will be performed. After the award of contract, a pre-conference will be held prior to starting the work at Coast Guard Station Grand Isle.
Location:
United States Coast Guard Station Grand Isle.
453 Admiral Craik Dr, Grand Isle, LA 70358
I. Continuity of Facilities Operation: Schedule work to minimize interference with the facility’s normal operations. Normal operating hours are from 8:00am to 4:00pm Monday thru Friday except federal holidays. Any work during other hours unless otherwise instructed or permitted shall be scheduled and approved with the Contracting Officers Representative.
II. Notification of Start and Completion of Work: The Contractor shall notify Coast Guard one week prior to start of work.
III. Coast Guard Contracting Officers Representative: The Contractor shall contact the COR to coordinate all construction efforts onboard Coast Guard Facilities.
| MKC Bryan Wilson |
| Bryan.D.Wilson@uscg.mil |
| 409-539-1313 |
IV: Recycling and Disposal of Refuse: All disposals shall be done in accordance with federal, state, and local laws and regulations. All bulk waste, to include old drywall, deteriorated frame wood, screws, etc shall be disposed of in contractor provided dumpsters.
V: Safety: During the execution of this contract, the Contractor shall conform to the rules and regulations as set forth by OSHA Safety and Health Standards, 29 CFR Part 1926 - Safety and Health Regulations for Construction. The contractor shall have a written safety plan as required in FAR 5.236-13. The plan shall unequivocally assign responsibility and authority for safety to the superintendent by name. Immediate notification to the Contracting Officer’s Representative of lost time due to accidents is required. Provide two copies of workman’s compensation accident reports by noon of the day following the accident. The Coast Guard reserves the right to bar any workers or supervisors from the premises should they be documented as violating set safety standards and regulations.
VI. Inspection: The Contracting Officer’s Representative has the right to reject defective workmanship or materials or work not performed as per the project specifications. Only the Contracting Officer or his/her representative may accept work performed by the contractor.
VII. Operations and Storage: The contractor is to take whatever steps necessary to ensure that their materials are protected. The Coast Guard has no responsibility for receipt, storage, or protection of contractor’s materials. All equipment, materials and supplies shall be addressed to the contractor. The Coast Guard or its members will not accept shipments. The contractor is responsible for the protection of existing structures, utilities, work and vegetation that may be in and around the work sites. Any damage shall be repaired at the contractor’s expense.
VIII. Contractor Identification: The contractor and subcontractor personnel shall, at all times, wear company identification.
IX. Existing Utilities: The Contractor shall field verify all utility locations before commencing work. This shall include, but not be limited to, the use of visual, sonic, electronic or magnetic detection devices. Contractor shall be responsible for repairing any utilities damaged during demolition or work throughout the project at no additional cost to the Government.
X: Regulations while onboard Coast Guard Station Grand Isle:
1. Daily colors and the raising/lowering of the American flag will take place every morning at 0800 and every evening at sunset. All personnel on Base will face the main flagpole & maintain silence and all vehicles & equipment will halt during these brief events.
2. The work site shall be maintained in a clean condition at all times. This includes daily clean-ups of the work and storage areas. The site shall be well lit and well barricaded/cordoned off as appropriate.
3. Absolutely no firearms or weapons of any kind are allowed onboard Station Grand Isle.
4. Only American citizens and permanent resident aliens are allowed onboard Station Grand Isle Facilities. Absolutely no foreign nationals are permitted on the premises.
5. Notice shall be given to the Coast Guard’s representative 1 week in advance of any planned power, water, and sewage or lighting outages.
6. The contractor shall provide a consolidated list of all contracted personnel including their driver’s license numbers (or other valid gov’t issued ID number) who will be working on Facilities either the day of or prior to the notice to proceed date.
7. Should warnings of gale force or stronger winds, or other inbound natural disasters be issued, the contractor shall take every practicable precaution to minimize the danger to persons, to the work, and the adjacent property. These precautions shall include closing all openings, removing all loose materials, tools and equipment from exposed locations, and removing or securing scaffolding, securing field trailers, and other appropriate equipment and other temporary work.
8. No personnel other than the contracting officer has the authority to alter the terms of any contract or to issue any change orders.
9. All contractor vehicles, equipment and gear onboard Coast Guard properties are subject to search at all times. Additionally at all times due to security and operational needs, the contractors are subject to orders to evacuate the property at any time.
10. Due to the nature of operations & support functions ongoing on-board Station Grand Isle, all efforts within reason to minimize the size and footprint of the contractor’s lay down area shall be taken. The boat ramp, government vehicles, and small boats shall not be obstructed or blocked.
VIII: SCOPE OF WORK: All materials are subject to COR approval prior to execution. The contractor shall discuss plans to complete the project with COR to create a schedule of areas to be worked on to minimize disruption of operations. The contractor shall provide all labor, materials, and equipment necessary to complete the following unless noted below:
A. Base Bid
1. The contractor shall Identify necessary replacement of current heaters.
2. Provide schedule of work to COR.
3. Hot water shall not be down for more than a 12-hour period as to not effect unit operations.
4. Remove existing water heaters.
5. Install new water heaters.
6. Install proper bracing and brackets for all hot water piping in the space of installation.
7. Conduct leak testing on all Natural gas line connections in presence of COR.
8. Conduct operational tests of heaters in presence of COR.
9. Required delivery 60 days after award.
10. Contractors shall protect all equipment and merchandise in work locations.
11. All work must be approved by the Contracting Officer’s Representative.
B. Option Items
Reference Pictures:
image10.jpg image20.jpg image4.jpg image1.jpg image2.jpg image3.jpg image5.png image4.png image6.png image50.png
File details come from the government source that posted it. Updated .