United States Fish & Wildlife Service
Design-Build Statement of Work Kīlauea Point National Wildlife Refuge, Main Entrance Road, Kīlauea, Hawaii
February 14, 2023
Table of Contents
1. Introduction
2. General Project Description
3. Schedule
4. FWS Contacts
5. Government Furnished Equipment and Materials
6. Scope of Work
6.1 General Requirements
6.2 Lines of Authority
6.3 Shared Electronic Platform
6.4 Pre-Construction Services
6.5 Task 1A: Site Investigation, DB Scoping, Data Collection and Schematic Design
6.6 Task 1B: Design Documents including Drawings, Specifications, Estimate, and Schedule
6.7 Task 1C: National Environmental Policy Act (NEPA) Documentation
7. Construction Services
7.1 Task 2A: Entrance Road & Parking
8. Construction Execution
8.1 General
8.2 Submittals
8.3 Permits
8.4 Daily Reports, Progress Photos And Documentation
8.5 Testing
9. Project Meetings
9.1 Project Kick-Off & Planning Meetings
9.2 Design Review Meetings
9.3 Pre-Construction Meeting
9.4 Construction Progress Meetings
10. Invoicing and Payment
11. Project Schedule
15. Element and Product Requirements
US Fish & Wildlife Service Kīlauea Point National Wildlife Refuge Page | 1
1. Introduction
Purpose: The purpose of this project is to design and construct the rehabilitation and stabilization of the entrance road and parking area at the Kīlauea Point National Wildlife Refuge (Kīlauea NWR) to enhance visitor safety and access. These areas incurred significant damage from storms in 2020 and 2021, including erosion, asphalt damage, drainage and runoff issues, and damage to the main water line that services the refuge.
Background: The Refuge is located on the northern-most point of the island of Kauaʻi on a portion of the former Kīlauea volcanic vent atop a 180-foot ocean bluff. The mission of the Refuge is to protect and enhance migratory seabirds and threatened and endangered species and their habitats, as well as to facilitate wildlife-dependent recreation opportunities. The Refuge is also home to the historic Kīlauea Point Lighthouse. Unique wildlife viewing and interpretative opportunities for the lighthouse makes the Refuge one of the most visited in the nation.
Project Location & Access: The project is located at the Kīlauea Point National Wildlife Refuge, 3500 Kīlauea Road, Kīlauea, HI 96754. The Refuge is currently open to the public from Wednesday to Saturday 10:00AM - 4:00 PM. All access will be coordinated with the Refuge Project Leader or site representative with available Monday thru Friday from 7:30 AM to 4:30 PM (Local Time), excluding Federal Holidays.
Availability outside the dates/hours shall be coordinated with the FWS at least two business days in advance.
FAR Price Range: For general project order-of-magnitude only. The anticipated cost of future construction services will be between $1,800,000 and $2,400,000.
2. General Project Description
The Design Build (DB) Contractor shall provide all labor, equipment, materials, and supervision to plan, design, and construct a complete project that fulfills the programmatic needs identified by the USFWS;
is safe; well-integrated into the landscape; relatively easy and low cost to operate and maintain; that is of high quality, durability, and functionality.
This DB project includes the following Pre-Construction Services:
• Task 1A: Site Investigation, Scoping, Data Collection and Schematic Design
• Task 1B: Design Documents including Drawings, Specifications, Estimate, and Schedule
• Task 1C: Environmental Permitting Assistance
This Design-Build project includes the following Construction Services:
• Task 2A: Construction of the project in accordance with the drawings and specifications.
• Task 2B: Construction of waterline replacement in accordance with the drawings and specifications.
3. Schedule
All design and construction work in this Request for Proposal (RFP) shall be completed within 365 days of contract award.
Kīlauea Point National Wildlife Refuge Page | 2
The DB shall submit an initial milestone schedule 14 calendar days after notice of award of the project.
Milestones should include significant events typical to a Design Build Contract.
Seasonal/Bio Species Constraints:
Contractor must adhere to any minimization and avoidance measures for all threatened and endangered species that occur onsite, as specified within the section 7 consultation under the Endangered Species Act (i.e., nesting buffers, avoiding take of individuals, etc.). Any ground disturbing or heavy equipment work should be scheduled outside of the breeding season for Newell’s shearwater from mid-April until November, whenever possible since these species occur in the direct vicinity of the project area. Any vegetation clearing along the road to prepare for construction should be accomplished in late February/early March to avoid disturbing nesting threatened or endangered bird species.
4. FWS Contacts
Project Manager and Contracting Officer’s Representative:
Monique Chase, Civil Engineer US Fish & Wildlife Service Division of Engineering, 911 NE 11th Avenue, Portland, Oregon 97232 503-706-5273 monique_chase@fws.gov
Technical:
Steven Minamishin, Facilities Manager U.S. Fish and Wildlife Service Kīlauea Point National Wildlife Refuge Complex 3500 Kīlauea Road; PO Box 1128, Kīlauea, HI 96754 Office: (808) 828-1413 ext. 201 steven_minamishin@fws.gov
Kauai National Wildlife Refuge Complex:
Heather Abbey Tonneson Jennifer Waipa Refuge Project Leader Visitor Services Manager 3500 Kīlauea Road; PO Box 1128 3500 Kīlauea Road; PO Box 1128 Kīlauea, HI 96754 Kīlauea, HI 96754 Office: (808) 828-1413 ext. 101 Office: (808) 828-1413 ext. 301 heather_tonneson@fws.gov jennifer_waipa@fws.gov
5. Government Furnished Equipment and Materials
The FWS will provide the following items related to this project:
ATTACHMENTS
mailto:monique_chase@fws.gov mailto:steven_minamishin@fws.gov mailto:heather_tonneson@fws.gov mailto:jennifer_waipa@fws.gov
Kīlauea Point National Wildlife Refuge Page | 3
Attachment Description
1 Kīlauea historical drawings, for information only 2 Kīlauea Hydraulics & Drainage Report 2012, for information only
3 DB General Engineering and Construction Requirements
NEPA Attachments Upon Request
• NPS Guidance on Focused and Concise EAs
• NPS Guidance on Writing Impacts Analysis for EAs and EISs
• EA Template
• FONSI Template
6. Scope of Work
6.1 General Requirements
The Owner’s Project Requirements are included in this contract as part of the Scope of Work (SOW) and the attachments. All work shall be in accordance with the tasks below and the USFWS/IR Regions 9, 10, 11 & 12 DESIGN/BUILD GENERAL ENGINEERING and CONSTRUCTION REQUIREMENTS, Revision: March 15, 2022 (Attachment 2).
The SOW is intended to provide the Design-Build (DB) Contractor with the general outline of the needs and desires for the project. This information shall be considered preliminary in nature and not construed as the preferred alternative needed for preparation of final construction documents. The DB shall evaluate, refine, and further develop the SOW collaboratively with the FWS team and project stakeholders.
The scope of work shall include all services needed for the full rehabilitation and stabilization of the entrance road and parking area to enhance visitor safety and access at the Kīlauea Point NWR. These items shall include, but are not limited to the following:
A. Widen dangerously narrow roadway that serves as the main entrance/exit
B. Address continual erosion along the sides of road
C. Provide safe pedestrian access from entrance gate with a dedicated pathway
D. Address storm water run-off
E. Routing of stormwater
F. Entrance gate modifications/upgrades as required by road rehab
G. Rust-resistant predator fencing from entrance along upper property line (~ 400ft)
H. Possible addition of retaining walls to address erosion and stormwater runoff
I. Upgrade turnaround near portable ranger station to accommodate school buses and commercial tour vehicles
J. Replace main waterline running along/under road and parking lot with limited disruption of water delivery.
Kīlauea Point National Wildlife Refuge Page | 4
K. Parking area repair.
L. Environmental Permitting Assistance.
6.2 Lines of Authority
The Owner shall communicate with the DB’s subcontractors, suppliers, and designer only through or in the presence of the DB. The Owner shall have no contractual obligations to subcontractors, suppliers, or the designer.
The DB shall communicate with the Owners and Stakeholders only through or in the presence of the CO and/or COR if the CO has delegated that duty to the COR in writing.
All inquiries requesting information should be in writing via email to the CO/COR.
6.3 Shared Electronic Platform
A shared electronic platform shall be agreed upon and set up by the DB for the purposes of hosting and managing project communication and documentation until Final Completion. All members of the Design-Build team shall have access including the DB and FWS team. The DB is responsible for setting up, managing, and archiving the project data. The site will be used for at least the following functions:
A. Project contacts B. Project correspondence C. Meeting agendas and minutes D. Owner’s Project Requirements Documentation E. Contract modifications documentation and logs F. RFI form and processing G. Task and issue management H. Photo documentation I. Baseline schedule, schedule updates and calendar management J. Budget Tracking K. Submittal form and processing L. Drawing and specification document hosting, viewing, and updating M. Online document collaboration N. Reminder and tracking functions O. Archiving functions P. Notification of submittal and RFI statuses and current responsible party
6.4 Pre-Construction Services
Refer to the DB General Engineering and Construction Requirements for more information on the documents to submit within 14 days following the issuance of the Notice To Proceed (NTP). These documents include:
A. Project Schedule B. DB Single Point-of-Contact C. List of Key Project Personnel D. List of Subcontractors E. Payment Schedule
Kīlauea Point National Wildlife Refuge Page | 5
Pursuant to a mutually agreeable schedule, the DB shall submit for FWS’s written approval, Design Development Documents and Construction Documents, based on the Contract Documents in existence at the time of the execution of this agreement or any further development of the construction documents that have been approved in writing by FWS.
FWS shall review and approve further development of the drawings and specifications as set forth in each Task below.
The DB shall schedule and facilitate weekly design meetings with the project stakeholders. The DB shall generate a weekly agenda and meeting notes for distribution to the group. Design meetings may be cancelled if mutually agreed upon by both the FWS and DB.
The DB shall perform Value Engineering throughout the Design and Construction Process. See the FAR section 52.248-3 of the solicitation for incentives processes.
Allow 2 weeks for FWS to review and provide comments after each submittal during the design phase. If needed, a collaborative meeting will be held to discuss the comments and agree on responses to move to the next design phase.
6.5 Task 1A: Site Investigation, DB Scoping, Data Collection and Schematic Design
Services in this category include the gathering, analysis and documentation of data required to further define the scope for project budget verification and design, and may include, but are not limited to:
A. Design Workshop Meetings/Charettes: After contract award and the Notice to Proceed has been issued the DB shall meet with the FWS team to discuss and resolve any remaining questions and issues generated from the proposal package. This is anticipated to be a virtual meeting over Microsoft TEAMS.
B. Project identification, including discussions of project location, history, functions, and scope.
C. Determination of feasible engineering solutions/alternatives which satisfy the project goals, objectives, budget, and user requirements.
D. Physical planning, including the conduct of topographic or engineering surveys including utility locations, and verification of as-built drawings.
E. Geotechnical Investigation if needed. DB to determine if additional investigation is needed for the project.
F. Planning to establish a project design and construction schedule.
G. Conceptual design(s), including access, site development, utilities, preliminary plans, elevations and details, design controls, preliminary specifications, and operation requirements.
H. Deliverables:
• Meeting Agendas and Minutes for all meetings
• Electronic Schematic design documents
• Project schedule
Kīlauea Point National Wildlife Refuge Page | 6
• Geotechnical analysis or soil investigation report as necessary
• A narrative describing the schematic design(s) characteristics.
6.6 Task 1B: Design Documents including Drawings, Specifications, Estimate, and Schedule
The DB shall promptly notify the COR and CO if the design begins to exceed or is likely to exceed the construction funding budget. Upon notification, the COR and CO will review the DB’s estimated cost of construction to determine the appropriate action(s) (e.g., de-scoping; creation of optional tasks).
Prepare Design Development Documents consisting of scaled drawings and an engineer’s opinion of probable construction cost. The Design Development Documents shall further define the Project including drawings and outline specifications fixing and describing the Project size and character as to site utilization, and other appropriate elements incorporating the structural, architectural, mechanical, and electrical systems. The DB shall indicate in writing (clouds and callouts) all material changes and deviations that have taken place form the Contract Documents in existence at the time of the execution of the Contract. Any changes in the Work contained in the Design Development Documents approved by the Owner shall result in a Change Order.
A. 35% Schematic Design (SD):
Consolidate the 35% design development documents into a single 65% submittal package.
B. 65% Design Development (DD):
This submittal package shall describe all the architectural and engineering design elements to be included in the final document package, including, but not limited to the following:
Site plans and details, plans, exterior elevations, sections, details, engineering design drawings, design calculations, material schedules, specifications, and cover sheet.
Deliverables:
Comments and Responses from previous phase Updates to Schedule Electronic pdf files for 65% design drawings and specifications
C. 95% Draft Construction Documents:
The Construction Documents shall set forth in detail the requirements for construction of the Work, and shall be based upon codes, laws, or regulations enacted at the time of their preparation. When the DB submits the Construction Documents, the DB shall indicate in writing (clouds and callouts) all material changes and deviations that have taken place from the Design Development Documents or the Contract Documents in existence at the time of the execution of the Contract. Any changes in the Work contained in the Construction Documents approved by the Owner shall result in a Change Order.
The DB will prepare 90% Draft Construction Documents consisting of drawings, specifications, and schedule updates. The DB will furnish review copies of the 90% Construction Documents to the FWS after receipt of comments concerning the 65% Construction Document submittal according to the project schedule.
Deliverables:
• Comments and Responses from previous phase (website)
Kīlauea Point National Wildlife Refuge Page | 7
• Updates to Schedule (website)
• Electronic pdf files (website) 90% design drawings and specifications
100% Final Construction Documents (CD):
After completing the response to the FWS 90% review comments, the DB will prepare Final Construction Documents consisting of Final Design Drawings, Technical Specifications, Final Design Calculations, Submittal Registry, and Schedule of Values
Deliverables:
• Comments and Responses from previous phase (website)
• Updates to Schedule (website)
• Electronic pdf files (website) 100% stamped design drawings, specifications, and calculations
• Submittal Register that includes a minimum listing of required submittals during construction
(website)
• Final Drawings in AutoCAD format with associated plot files (website)
• Final Schedule of Values (website)
As-Built Drawings:
The DB shall prepare and submit to the Owner final marked up as-built drawings in general documenting how the various elements of the Work including changes were constructed or installed.
Deliverables:
• Electronic pdf files (website) As-Built Drawings
• As-Built Drawings in AutoCAD format with associated plot files (website)
6.7 Task 1C: Permitting
This task is for assistance preparing documentation required for permitting.
Preparation of review documents under the provisions of the National Environmental Policy Act (NEPA).
FWS has determined that there are no agency or departmental Categorical Exclusions (CE) that exist for this work. A focused and concise (10-35 pages) Environmental Assessment (EA) with public Involvement to the extent practicable needs to be developed. The No Action and Proposed Scope Action alternatives will be evaluated in the environmental review. The draft EA will be published and available to the public for comment for a 30-day period.
The Service believes that the project may qualify for a Finding of No Significant Impact (FONSI) following preparation of an Environmental Assessment (EA) that satisfies NEPA. If, following consultation with stakeholders and preparation of the documentation, a significant impact is identified such that a FONSI will not likely occur and an Environmental Impact Statement will be needed, the DB shall notify FWS with a plan of action.
The DB will develop environmental review documents for the No Action alternative and the Action alternative identified in this SOW. DB services for this task will include, but not be limited to:
• Task A – Public Notification & Pre-Assessment Consultation
Kīlauea Point National Wildlife Refuge Page | 8
• Task B – Conduct Resource Studies and Evaluate Likelihood of FONSI
• Task C – Develop DRAFT NEPA Documents
• Task D – Develop FINAL NEPA Documents
An EA for the Kīlauea Point NWR related to the Comprehensive Conservation Plan for the refuge was completed and can be provided upon request to help with background and other information for the NEPA document for this project.
Guidance and templates for EAs can be provided upon request (NPS Guidance on Focused and Concise EAs & NPS Guidance on Writing Impacts Analysis for EAs and EISs).
A sample Legal Notice and a sample letter to interested parties can be provided upon request.
6.7.1 Task 1C.A – Public Notification & Pre-Assessment Consultation Hold an internal scoping meeting with the FWS project team for the exchange of local knowledge of the potential issues related to this project. Develop a list of all potential interested parties. The list shall include Federal, State, Local, community and neighboring landowners.
Prepare a 1–2-page notice to the public and other stakeholders stating an EA will be prepared and available for public comment. The notice shall include:
• Preliminary purpose and need, description of the proposed action, challenges to project completion (social, economic, physical); utilize documents developed in Task 1A.
• The FWS proposed process including when, and where the public scoping meeting will be held.
• The name and address of the designated individual(s) from the DB who can answer questions about the proposed action.
• DB Email address for public to send comments.
The notice shall be submitted to the local newspapers and electronic letters sent to all potential interested parties.
After publication of the notice, a public comment period of 30 days will be open, affording agencies, organizations, and individuals an opportunity to offer up their concerns.
The DB will facilitate the comment reception process and at the conclusion of the public comment period, the comment responses will be summarized for inclusion in the draft NEPA documents.
Deliverables:
• Public Notice (.pdf)
• Electronic Letters to Interested Parties (.pdf)
• All written comments received (.pdf)
6.7.2 Task 1C.B – Conduct Resource Studies and Evaluate Likelihood of FONSI Conduct resource studies for the EA necessary to evaluate the potential environmental impacts and the likelihood of a FONSI. Unless specifically mentioned otherwise in this SOW, all resources studies will rely on existing information from previous environmental documents and will not require a field survey.
Deliverables: Draft reports of resource studies (.pdf)
Kīlauea Point National Wildlife Refuge Page | 9
6.7.3 Task 1C.C – Develop DRAFT NEPA Documents and Public Meeting Prepare a preliminary Draft EA for review. DB and FWS will concurrently review the document.
Comments will be incorporated and the Draft EA will be finalized. The Draft EA will be made available for public comment for a 30-day period. The DB will draft responses to comments to be reviewed by FWS before being sent to commentor.
Deliverables:
• Draft EA for Review (.pdf)
• All spoken and written comments received (.pdf)
• Summarization of comments into categories for responses
• Responses to all comments received
6.7.4 Task 1C.D – Develop FINAL NEPA Documents
Prepare a final EA for review. Incorporate all comments received from the Draft EA as appropriate into the final EA. The FWS will review and sign the final EA and the DB will make the final EA available to the public.
If the EA determines a FONSI, the A-E shall prepare the FONSI. If a significant impact is identified such that a FONSI will not likely occur and an Environmental Impact Statement will be needed, the A-E shall notify USFWS and provide an estimate for the preparation of the EIS.
Deliverables:
• Final EA (.pdf)
• FONSI or EIS Estimate (.pdf)
7. Construction Services
7.1 Task 2A: Rehabilitation and Stabilization of the Entrance Road and Parking Area
This item consists of the construction of the rehabilitation of the entrance road and parking area and any auxiliary work in accordance with the final construction documents, this scope of work and Attachments. In the case of conflicts, the final construction documents shall take precedence.
Deliverables:
• Refer to Construction Requirements and the following Sections
8. Construction Execution
8.1 General
Refer to Attachment 2 – DB General Engineering and Construction Requirements.
If the Owner becomes aware of any error, omission, or failure to meet the requirements of the Contract Documents or any fault or defect in the Work, the Owner shall give prompt written notice to the DB.
Kīlauea Point National Wildlife Refuge Page | 10
Project work will be accomplished via the project-specific Work Statement to convey the unique aspects of the project.
The DB shall give all notices and comply with all laws and ordinances legally enacted at the date of execution of the Contract which govern the proper performance of the Work.
Federally listed illegal drugs and alcohol are not permitted on the jobsite or any Federal property, regardless of State laws.
8.2 Submittals
The Owner shall review construction submittals for compliance with the Construction Documents unless Owner approval has been indicated on a submittal.
The AE designer shall review all construction submittals and RFI’s.
See 48 CFR 52.236-21 (d), (e), (f), (g), “Specifications and Drawings for Construction”, for requirements of Shop Drawing submittals for (1) the proposed fabrication and assembly of structural elements and (2) the installation (i.e., form, fit, and attachment details) of materials or equipment.
Except as indicated below, transmit all submittals using the project’s shared electronic website or platform in Adobe.pdf.
All submittals shall be transmitted with Submittal Form FWS R1-67 as the cover sheet (Attachment 3)
8.3 Permits
In addition to the Permits and Responsibilities clause Federal Acquisition Regulation (FAR) 52.236-7, if work includes any ground disturbances meeting Stormwater Pollution Prevention Plan (SWPPP) requirements, DB shall prepare, submit, and obtain any permits for SWPPP.
8.4 Daily Reports, Progress Photos and Documentation
The DB shall keep such full and detailed accounts as may be necessary for proper financial management under this Contract. The Owner shall be afforded access to all the DB’s records, books, correspondence, instructions, drawings, receipts, vouchers, memoranda, and similar data relating to Change Order work performed based on actual cost. The DB shall preserve all such records for a period of three years after the final payment or longer where required by law.
The DB shall provide periodic written reports to the Owner on the progress of the Work on the project website in the following manner:
• DB shall prepare and submit to the COR a daily report for each day physical on-site work is accomplished. The report shall note days and durations of no-work on the project.
• DB shall label and submit to the COR a minimum of two photographs for each day of work, which represents work accomplished for that day. Photos shall contain a date stamp representing the day of work.
• The DB shall (during normal working hours throughout the duration of the contract) promptly furnish information and provide reasonable facilities & access for obtaining information respecting: the character of the materials, condition of the work-in-progress, number of workers employed, their pay rate, time worked, inspection reports and test results from sampling and testing laboratories, and similar information.
Kīlauea Point National Wildlife Refuge Page | 11
8.5 Testing
Third-Party Sampling & Testing: The DB shall provide and pay for the services of an accredited independent construction materials testing laboratory meeting the minimum requirements of ASTM E239-11c.
When work involves any of the below items, provide third-party Testing Lab Services:
• Soils classification, gradation, and/or compaction.
• Concrete strength, air-content, slump, and similar
• Structural welds
• Asphalt
• Pile-driving
• Other, as noted in other sections.
9. Project Meetings
The DB is responsible for arranging required meetings, providing agendas and meeting notes. Project meetings may be virtual or in-person depending on which type of meeting would be most productive.
9.1 Project Kick-Off & Planning Meetings
The purpose of these meetings is to further define the Owner’s Project Requirements and develop the scope of work and schedule for the project.
9.2 Design Review Meetings
Design Review meetings are required after each major submittal and after the Owner and Stakeholders have had a chance to review submittals and provide comments. Periodic design review meetings between submittals at 1 to 2-week intervals are desired to keep work progressing and communications open.
9.3 Pre-Construction Meeting
A Pre-Construction meeting is required on-site before construction is scheduled to begin. Attached is an example agenda that covers the requirements of this meeting. Many of the items will have already been addressed throughout the project. (Attachment 4)
9.4 Construction Progress Meetings
The DB shall keep the owner and stakeholders briefed weekly on the status of the construction. The purpose of these meetings is to report on project progress and any potential issues, which were encountered or continue to develop during construction and installation. The meetings can be virtual and should cover the following items at a minimum:
• Approval of minutes of previous meetings
• Submittal status
• Review of off-site fabrication and delivery
• Requests for Information (RFI’s) and issues
• Modifications
• Work in progress and projected (4-week look ahead)
Kīlauea Point National Wildlife Refuge Page | 12
• Schedule update (provide updated CPM schedule)
• Status of Project Record Drawings and O&M Manuals
• Other business relating to work
10. Invoicing and Payment
DB shall not invoice between September 20th thru October 25th, due to the seasonal financial system closure.
Invoices shall be made monthly in accordance with FAR Clause 52.232-10. Prior to submitting invoices into the Invoice Processing Platform (IPP), invoices shall be electronically submitted to the COR for review and approval. Once approved, the contractor shall upload the signed invoice into IPP, following the format of Paragraph (a) (2) of FAR Clause 52.232-26.
Prior to the final invoice, the DB shall coordinate COR approval stating all deficiencies have been corrected. Refer to Paragraph (d) of FAR Clause 52.232-10 for additional information related to the final invoice.
11. Project Schedule
The DB shall prepare, submit, and maintain a Schedule of Work for the Owner’s acceptance and written approval as to milestone dates on the project website. This schedule shall indicate the dates for the start and completion of the various stages of the Work, including the dates when information and approvals are required from the Owner. The Schedule shall be revised as required by the conditions of Work.
The Owner shall review the Schedule of Work, approve milestone dates set forth and respond to its obligations in a timely manner.
12. Element and Product Requirements
Major products selected by the DB for incorporation into the work shall be environmentally friendly, energy efficient, renewable, or with other improved sustainable characteristics. Submit manufacturer’s literature demonstrating sustainability.
During Design Development or Construction Documents Submissions:
• Where more than one product type is identified for a particular system, assembly, or element, the DB shall identify exactly which type will be used.
• For each product type, the DB shall identify descriptive or performance specifications; early submittals shall be brief specifications, but complete specifications shall be provided prior to completion of construction documents.
• For each product type, the DB shall identify at least three manufacturers that can be used.
• For major manufactured products that are commonly purchased by brand name, and any other products so indicated, the DB shall provide manufacturer's product literature on at least one actual brand name product that meets the specifications, including performance data and sample warranty.
Kīlauea Point National Wildlife Refuge Page | 13
During Construction:
• The DB shall identify actual brand name products used for every product, except commodity products specified by performance or description.
• Where a product is specified by performance requirements with test methods, and if so specified, the DB shall provide test reports showing compliance.
• The DB shall provide manufacturer's product literature for each brand name product.
• The DB shall provide the manufacturer's certification that the product used on the project complies with the contract documents.
Before End of Closeout:
• The DB shall provide copies of all manufacturer warranties that extend for more than one year after completion.
| 1. Introduction |
| 2. General Project Description |
| 3. Schedule |
| 4. FWS Contacts |
| 5. Government Furnished Equipment and Materials |
| 6. Scope of Work |
| 6.1 General Requirements |
| 6.2 Lines of Authority |
| 6.3 Shared Electronic Platform |
| 6.4 Pre-Construction Services |
| 6.5 Task 1A: Site Investigation, DB Scoping, Data Collection and Schematic Design |
| 6.6 Task 1B: Design Documents including Drawings, Specifications, Estimate, and Schedule |
| 6.7 Task 1C: Permitting |
| 6.7.1 Task 1C.A – Public Notification & Pre-Assessment Consultation |
| 6.7.2 Task 1C.B – Conduct Resource Studies and Evaluate Likelihood of FONSI |
| 6.7.3 Task 1C.C – Develop DRAFT NEPA Documents and Public Meeting |
| 6.7.4 Task 1C.D – Develop FINAL NEPA Documents |
| 7. Construction Services |
| 7.1 Task 2A: Rehabilitation and Stabilization of the Entrance Road and Parking Area |
| 8. Construction Execution |
| 8.1 General |
| 8.2 Submittals |
| 8.3 Permits |
| 8.4 Daily Reports, Progress Photos and Documentation |
| 8.5 Testing |
| 9. Project Meetings |
| 9.1 Project Kick-Off & Planning Meetings |
| 9.2 Design Review Meetings |
| 9.3 Pre-Construction Meeting |
| 9.4 Construction Progress Meetings |
| 10. Invoicing and Payment |
| DB shall not invoice between September 20th thru October 25th, due to the seasonal financial system closure. |
| Invoices shall be made monthly in accordance with FAR Clause 52.232-10. Prior to submitting invoices into the Invoice Processing Platform (IPP), invoices shall be electronically submitted to the COR for review and approval. Once approved, the contrac... |
| Prior to the final invoice, the DB shall coordinate COR approval stating all deficiencies have been corrected. Refer to Paragraph (d) of FAR Clause 52.232-10 for additional information related to the final invoice. |
| 11. Project Schedule |
| 12. Element and Product Requirements |