SOW CW Rock Rev D 2024.pdf
PDF 115 KB Posted
- Attached to
- Crawlerway Rock Federal contract opportunity
- Solicitation number
- 80KSC024875773
About this file
This document is a Statement of Work (SOW) for procuring and delivering rock that meets the Kennedy Space Center (KSC) Crawlerway Rock specification to a KSC site designated by the contracting officer.
The work involves locating and delivering at least 500 tons per month of ASTM #4 river rock, with ASTM #3 river rock as an acceptable alternative if ASTM #4 is unavailable. Deliveries must be completed within five months after the Notice to Proceed. The DARCY site at KSC is the designated delivery location, open for deliveries on Tuesdays and Thursdays. The project completion date will be set to allow sequential rock deliveries to ensure 100% of the rock meets the specification. The associated federal contract opportunity is a Request for Information (RFI)/Sources Sought notice, with responses due by August 8, 2024. The NAICS code is 423320 - Brick, Stone, And Related Construction Material Merchant Wholesalers with a size standard of 150 employees.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Spec for CW Rock.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
CRAWLERWAY ROCK
Fiscal Year (FY) – 2024/25
DATE: July 23, 2024
NASA Contracting Officer’s Representative (COR): John Giles, LX-O3
NASA, Crawlerway Engineer: Rob Schroeder, NE-TG
NASA, Contracting Officer: Kristal Kerr, OP-ES
1. SCOPE
1.1. DESCRIPTION.
1.1.1. DESCRIPTION OF WORK
1.1.1.1. Summary of Work: The work to be performed consists of procuring and delivering rock that meets the KSC Crawlerway Rock specification to a KSC site designated by the contracting officer.
1.1.1.2. Detailed Description of Work: The work consists of locating and delivering rock that meets the KSC Crawlerway specification to the DARCY site located on the Kennedy Space Center.
The DARCY site is open for deliveries Tuesdays & Thursdays from 0730 to 1100 and 1200 to 1500. To ensure that all rock delivered meets the Crawlerway rock specification, the project completion date will be set so that rock deliveries can be spaced out sequentially over time to allow the contractor ample time to ensure 100% of delivered rock meets the specification.
A. Further Delivery Details: Rock deliveries shall be at least 500 tons per month and should be completed within five months after Notice to Proceed (NTP). The preferred size of rock is ASTM #4, but ASTM #3 is acceptable if not enough ASTM #4 is available. The procurement shall be filled with ASTM #4 River Rock, ASTM #3 River Rock may be supplied only if there is not enough ASTM #4 to fulfill the procurement order. See attached Specs for definition of ASTM gradation sizes.
Table 1 - SCHEDULE MILESTONES1
On or Before
Calendar Days
River Rock to be delivered in tons:
1st Delivery Requirement 30 Min: 500
Max: 1,000
2nd Delivery Requirement 60 Min: 500
Max:1,000
3rd Delivery Requirement 90 Min: 500
Max: 1,000
Progress Meetings As Required
| 1. SCOPE |
| Table 1 - SCHEDULE MILESTONES1 |