This document is a Statement of Work (SOW) for the replacement/repair of a Barker and Williams BWDS-90N antenna at the Connecticut Emergency Management and Homeland Security Division's FEMA National Radio System (FNARS) site.
The key details are:
- The contractor will remove the existing BWDS-90N antenna and install a new FEMA-furnished BWDS-90N-G antenna in the same location, anchoring it at two points on each end to prevent interference. The contractor will also untwist and remount the lower BWDS-90N antenna.
- The contractor will install new transmission lines, including RG-213 and LDF4-50A cables, from the antenna to the building's radio room, and will install a surge protector and cable markings.
- The contractor will document the installation, restore any disturbed areas, and perform VSWR and DTF sweeps to verify proper operation.
- The period of performance is 30 calendar days from the award date.
- The contractor must provide all labor, equipment, and certified personnel to complete the work safely and in accordance with federal, state, and local requirements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2.2.1 RFQ_sam.gov Package 1.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FEMA Office of National Continuity Programs FEMA National Radio System (FNARS)
Connecticut Emergency Management And Homeland Security Division
FNARS B&W BWDS-90N Antenna Replacement / Repair Statement of Work (SOW)
June 7, 2024
PREPARED BY:
Federal Emergency Management Agency Office of National Continuity Programs
Continuity Communications Division
Location:
Connecticut Emergency Management and Homeland Security Governor William A. O’Neill State Armory Building 360 Broad Street Hartford, CT 06105
Contracting Officers Representatives (COR): Douglas Meyer Technical Monitor (TM):
References:
Attachment A: State Armory Building (Arrow indicating tower) Attachment B: Closer view on antenna tower Attachment C: Multiple folded dipole antennas from tower Attachment D: Multiple folded dipole antennas from tower Attachment E: BWDS-90 Installation Manual (Double-Click to Open) Attachment F: FDMK Support Kit Attachment G: Two anchor points diagram Attachment H: Existing building conduit to roof Attachment I: Roof conduit to building interior Attachment J: Cable entry to grounding point Attachment K: Grounding panel with lightning protection Attachment L: From grounding panel to radio room run Attachment M: “FEMA HF” tags on existing cable
Specific:
1. Contractor will Identify and Remove existing Barker and Williams BWDS-90N antenna.
a. The FNARS BWDS-90N antenna is mounted from rooftop tower to roof snow guard rails. The roof is pitched. (Attachments A through D)
b. The tower is atop a building that is approximately 80’ tall. The FNARS antenna is the highest mounted B&W antenna from the tower.
c. There is access to the roof from the interior and tie-off/anchor points on roof.
2. FEMA will furnish, and Contractor install one new Barker and Williams BWDS-90N -G Antenna.
a. Contractor will install a FEMA furnished B&W model BWDS-90N-G antenna (includes FDMK Support Kit) in the “Sloper” configuration in accordance with the manufacturer’s specifications. (Attachments E and F)
b. Contractor will install the B&W antenna in the same place as the removed antenna. If mounting point adjustments can be made, without affecting orientation, to reduce the risk of coming into contact with the other antennas then they should be done.
c. Antenna will be anchored at two points on each end; to reduce the risk of twisting or flipping over itself. (Attachment G)
d. Contractor will untwist and remount the lower B&W antenna, with two anchor points at each end, to prevent potential interference issues with each other.
3. Install new transmission line.
a. Contractor shall remove and dispose of old transmission line (~150ft).
b. Contractor shall install FEMA provided RG-213 cable from antenna balun to the rooftop NEMA enclosure.
c. Contractor shall install FEMA provided LDF4-50A cable from NEMA enclosure through existing conduit to the lightning protection panel inside building.
(Attachment H, I, and J)
d. Contractor shall install FEMA provided NexTek SurgeGuard PTRONFONF80S on existing ground panel. (Attachment K)
e. Contractor shall install FEMA provided LDF4-50 cable from SurgeGuard to the radio rack (~30ft). (Attachment L)
f. Contractor will install FEMA provided UG-1185/U connector on the RG-213 run to the antenna balun, and UG-1186/U connector on the RG-213 in the NEMA enclosure.
g. Contractor will install FEMA provided Commscope L4TNM-PSA Type N Male connectors on the LDF4-50 from NEMA enclosure to SurgeGuard, and from SurgeGuard to Radio Rack.
h. Contractor will install FEMA provided transmission line ground kit at NEMA enclosure if ground is present; otherwise at the same grounding panel as the SurgeGuard.
i. All outdoor cable connections made shall be weatherproofed to industry standards.
j. Contractor shall utilize same paths for cable runs as previous run.
k. Contractor shall secure cable runs as per industry standards for conditions.
l. Contractor will provide and attach metal ID tags, stating “FEMA HF” to the transmission line near the balun, in the NEMA enclosure, at each side of the SurgeGuard, and near the Radio Rack. (Attachment M)
4. Document installation.
a. Contractor shall document installation to include antenna position, mounting points, cable paths, and cable markings. Documentation will include digital photographs in JPEG format.
5. Disturbed areas restoration.
a. All trenches, ruts or tracks created by equipment such as trucks, lifts, backhoes, or cranes shall be filled in, properly compacted, and raked back to the natural ground level. Any disturbed site areas must be restored to pre-construction condition.
b. Heavily reseed the disturbed areas with a grass seed mixture suitable for the region, and cover with straw or other suitable grass seed covering for the region/climate.
6. Testing.
a. The contractor shall perform a 2 to 30 MHz VSWR sweep along with a DTF sweep and document results on the newly installed antenna/transmission line.
b. All discrepancies in the installation of the antenna/feedline assemblies found to be outside manufactures specifications shall be resolved and the testing & documentation process repeated.
Deliverables:
1. Existing FNARS antenna removed, packed in a neat and orderly manner, and handed off to FEMA technical monitor.
2. One fully functional B&W model BWDS-90N-G antenna installed per manufacturer’s recommended standard and with two anchor points on each end. Lower B&W antenna untwisted and remounted as per SOW.
3. New transmission line installed and marked as per the SOW.
4. Document antenna system installation as per the SOW and submit to the COR electronically.
5. Ground that was disturbed by the installation brought back to original state. This will be included but not limited to grading (if necessary), spreading grass seed and straw.
6. The contractor shall perform a 2 to 30 MHz VSWR sweep along with a DTF sweep and document results on the newly installed antenna/transmission line. All sweep documentation shall be given to the FEMA TM electronically by email in JPEG format.
Completion Criteria:
This project will be considered complete when the tasks identified in the SOW have been completed, tested and the final documentation has been delivered to and accepted by the COR.
Period of Performance (POP): All work shall be completed by the contractor within 30 calendar days from the award date of the resulting order.
General Requirements:
1. The contractor shall provide all labor, personnel, equipment, tools, materials and supplies necessary for completion of this task.
2. Removal and installation may require personnel to climb. Maintenance personnel will be certified to climb towers and will adhere to all safety standards. Work to be performed under this SOW requires a minimum of two (2) tower and antenna certified people to be present at the job site. The Contractor shall provide all equipment and certified personnel associated with the entire project to operate in a safe manner and adhere to all Federal, State and local safety standards, including OSHA standards. The CO/COR or facility safety officer may require a copy of the certifications prior to the start of the project.
3. The contractor shall schedule a start date for the project within 5 calendar days of receipt award for this project. The contractor shall coordinate with the COR and/or the Technical Monitor (TM) in advance of commencing any work.
4. No deviation or substitution of materials specified shall be done without prior approval of the COR or Contracting Officer (CO).
5. The COR will work with the contractor to determine if any inspections and/or permits are needed.
6. Contractor will ensure that all site access requests are provided to the COR NLT 72 hours from the start of the project.
7. The Contractor shall establish that FEMA NCP is the owner of record of all materials procured for this project, such that FEMA NCP may exercise all warranty and technical support rights following final acceptance.
8. All data, software, equipment, analysis results, and reports/briefings generated are the property of the United States Government and may not be released to third parties without the express written consent of the Contracting Officer Representative (COR)/Contracting Officer (CO).
9. Environmental Issues: Contractor will coordinate with the COR before any work is started and/or equipment is set up on the site. Any known environmental issues will be disclosed to the Contractor prior to the start of the project. Any environmental issues identified by the Contractor will be reported to the onsite Technical Monitor or the COR.
10. Telephone: Telephone service should not be expected to be available onsite for the Contractor’s use. Contractors may use cellular phone devices onsite. Depending on the cell phone service, reception may or may not be present.
11. Restroom Facilities: There are normally no publicly accessible restroom facilities at most sites. The Contractor must provide their own restroom facilities.
12. Utilities: If the Contractor requires a generator(s) then the Contractor must provide one.
13. Contractor employees working onsite shall wear an identification badge that at minimum displays the Contractor name, the employee’s photo, and the employee’s name. All Contractor employees shall identify themselves as Contractors when their status is not readily apparent and display all identification and visitor badges in plain view above the waist at all times.
14. The Federal Government owns the hardware and associated systems. The contractor shall use only such equipment in support of requirements outlined in this SOW.
15. In accordance with this SOW, the Government shall exercise its right to review deliverables prior to formal delivery and acceptance.
16. The Contractor shall coordinate services, deliverables, and delivery schedules with the
COR or his/her designee, with the understanding that all work shall be within scope of this SOW. Contractor shall submit all deliverables to the COR for inspection and acceptance.
17. All cyber identity and cyber attribute data—including data at rest, data in transit, generated data, and metadata—will always remain the property of the United States Government. None of this data will be shared or distributed, other than within the operating parameters of the program, without prior written permission from FEMA. At the conclusion of the contract, the Contractor shall return all Government-owned data to
FEMA on an appropriate storage medium and will definitively purge all Contractor-owned equipment of Government-owned data.
18. Normal business hours shall be Monday thru Friday, from 8:00 a.m. to 4:30 p.m. No onsite work shall be performed outside these hours or on holidays unless prior approval is obtained from the CO or the COR. The Contractor shall coordinate with the COR to arrange access to the work site. The Contractor will be required to report to the appropriate facility and submit to (if required) vehicle searches before access will be granted. Contractor will be prepared to provide their employees’ personal information (Full Name, social security number, date of birth, place of birth, driver’s license number, and home address) to the COR 72 hours prior to beginning work so that information can be vetted with Security. For emergency work, information will be provided as soon as it is practical, but Contractors will not be able to access sites until vetting procedures are complete. Contractors will be escorted by a properly cleared/badged Government employee. The Contractor shall make the effort to cause a minimum damage to parking lots, other paved areas, items that need to be moved during the course of the project, and other areas not included in this SOW. Damage caused by the Contractor will be repaired at the Contractor’s expense.
19. All trash & debris generated during the installation including shipping containers, packing material, and removed feedline/conduit shall be collected, contained throughout the process and removed from the facility at the end of the install.
20. Contractor Required Insurance to Work on a Government Installation: The contractor shall, at its own expense, provide and maintain during the entire performance period of this contract at least the kinds and minimum amounts of insurance required in paragraph 3). below.
1). Five days after contract award, the contractor shall certify to the CO in writing that the required insurance has been obtained. The policies evidencing required insurance shall contain an endorsement to the effect that any cancellation or any material change adversely affecting the Government's interest shall not be effective (l) for such period (cont.) as the laws of the State in which this contract is to be performed prescribe, or (2) until 30 days after the insurer or the contractor gives written notice to the CO, whichever period is longer.
2). The Contractor shall insert the substance of this clause, including this paragraph 3)., in subcontracts under this contract that require work on a Government installation and shall require subcontractors to provide and maintain a copy of all subcontractors' proofs of required insurance and shall make copies available to the Contracting Officer upon request.
3). The following coverage is the minimum insurance required for work Under this contract:
(a) Workers' compensation and employer's liability. Contractors are required to comply with applicable Federal and State workers' compensation and occupational disease statutes. If occupational disease is not compensable under those statutes, it shall be covered under the employer's liability section of the insurance policy, except when contract operations are so commingled with a contractor’s commercial operations that it would not be practical to require this coverage. Employer's liability coverage of at least $100,000 shall be required, except in States with exclusive or monopolistic funds that do not permit workers' compensation to be written by private carriers.
(b) General Liability.
The CO requires bodily injury liability insurance coverage w ritten on the comprehensive form of the policy of at least $500,000 per occurrence.
Attachment A: State Armory Building (Arrow indicates tower)
Attachment B: Closer view of tower
Attachment C: Multiple Folded Dipole Antennas
Attachment D: Multiple Folded Dipole Antennas
Attachment E: BWDS-90 Installation Manual (Double-Click to Open)
Fdipole.pdf
Attachment F: FDMK Support Kit
Attachment G: Two anchor points diagram
Attachment H: Existing building conduit to roof
Attachment I: Roof conduit to building interior
Attachment J: Cable entry to grounding point
Attachment K: Grounding Panel with Lightning Protection
Attachment L: From grounding panel to conduit to radio room
Attachment M: “FEMA HF” tags on existing cable