SOW - Cistern Cleaning - Draft 6.12.26.pdf

PDF 192 KB Posted

Attached to
Cistern Cleaning Services
Solicitation number
NTIA0000-26-00235
Issued by

About this file

This is a Statement of Work (SOW) for cistern cleaning and replacement services at the Table Mountain Field Site operated by the National Telecommunications and Information Administration's Institute for Telecommunication Sciences under the U.S. Department of Commerce.

The contractor must inspect, clean, sanitize, and replace potable water cisterns at three building locations (I10C/A4, F2/T2, and B9) within a 360-day performance period beginning at contract award. Task 1 requires a thorough inspection of each cistern's structural integrity, interior/exterior surfaces, and associated components (lids, seals, vents, access points), with a written assessment report due within 10 business days identifying whether each cistern can be cleaned or requires replacement. Task 2 involves draining, removing sediment and debris, pressure washing and scrubbing interior surfaces, and disinfecting in accordance with American Water Works Association (AWWA) Standard C652 using only NSF/ANSI/CAN 60-certified chemicals; refilling and water quality testing must verify compliance with Colorado Primary Drinking Water Regulations. Task 3 addresses replacement of cisterns deemed beyond repair, requiring a detailed proposal with costs, removal of the old unit, installation of a new compliant cistern with secure plumbing connections, and initial disinfection and testing per Task 2 procedures.

Deliverables include: Cistern Assessment Reports (one per cistern within 10 business days of inspection with photographs and recommendations), Replacement Proposals (as needed), Service Completion Reports (within 5 business days of work completion detailing work performed, dates, chemicals used with Safety Data Sheets, and before/after photographs), Certificates of Sanitization (for each cleaned cistern), and certified Water Quality Test Results demonstrating compliance with Colorado potable water standards. The contractor must hold Colorado licensure and insurance for this work type, comply with OSHA confined space entry protocols and NSF standards NSF/ANSI/CAN 61 for system components, and meet all Colorado Department of Public Health and Environment regulations. Final acceptance requires COR verification of task completion, approval of all deliverables, successful visual inspection, and water quality test confirmation. The site location is NTIA - Table Mountain Field Site, 8600 N 39th Street, Longmont, CO 80503. The government will provide site access, a designated Contracting Officer's Representative, and water source access.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work (SOW)

Cistern Cleaning and Replacement Services U.S. Department of Commerce

National Telecommunications and Information Administration Institute for Telecommunication Sciences

1. BACKGROUND

The Institute for Telecommunication Sciences (ITS), as custodians of the Table Mountain Field Site and Radio Quiet Zone, requires Cistern Cleaning and associated services as part of its regular Operations and Maintenance (O&M) activities to ensure a safe and reliable supply of potable water for site facilities. This work is critical for maintaining health and safety standards and ensuring operational continuity.

2. OBJECTIVE

The primary objective of this contract is to acquire the services of a qualified contractor to inspect, clean, sanitize, and, if necessary, replace potable water cisterns at designated buildings located at the Table Mountain Field Site.

All work must be performed in accordance with industry best practices and applicable Colorado state standards for potable water systems.

3. SCOPE OF WORK

The Contractor shall provide all necessary labor, supervision, materials, tools, equipment, and transportation to perform the services outlined below for the cisterns located at the following buildings:

• I10C, A4

• F2, T2

• B9

The work shall be divided into the following tasks:

3.1 Task 1: Cistern Inspection and Assessment: The Contractor shall conduct a thorough inspection of each cistern listed above. The inspection shall:

• Assess the overall structural integrity of each cistern.

• Identify the presence of sediment, biofilm, debris, or other contaminants.

• Inspect all interior and exterior surfaces for cracks, leaks, corrosion, or other damage.

• Evaluate the condition of all associated components, including lids, seals, vents, and access points.

• Determine whether each cistern is a candidate for cleaning and sanitization or if it is damaged beyond repair and requires replacement.

3.2 Task 2: Cistern Cleaning and Sanitization: For all cisterns deemed suitable for continued use, the Contractor shall:

• Safely drain the cistern, managing the discharged water in an environmentally responsible manner.

• Remove all sediment, sludge, and debris from the interior of the cistern.

• Pressure wash or manually scrub all interior surfaces to remove scale, algae, and biofilm.

• Disinfect and sanitize the cistern in accordance with American Water Works Association (AWWA)

Standard C652 for the Disinfection of Water-Storage Facilities.

• Use only chemicals and compounds that are certified as meeting NSF/ANSI/CAN 60 standards for use in drinking water systems.

• Refill the cistern and conduct water quality testing to verify disinfection is complete and the water is safe for potable use, meeting the standards set by the Colorado Primary Drinking Water Regulations.

3.3 Task 3: Cistern Replacement: For any cistern identified in Task 1 as damaged beyond repair and approved for replacement by the Contracting Officer’s Representative (COR):

• The Contractor shall submit a detailed replacement proposal to the COR, including the cost of a new, appropriately sized cistern and all associated labor and materials.

• Upon approval from the COR, the Contractor shall safely disconnect and remove the old cistern from the site.

• Install a new cistern that meets or exceeds all current state and federal standards for potable water storage.

• Ensure all plumbing connections are secure, leak-free, and compliant with local codes.

• Perform initial disinfection and water quality testing on the new cistern as described in Task 2.

4. DELIVERABLES

The Contractor shall provide the following deliverables:

1. Cistern Assessment Report (10 business days after inspection): A detailed report for each cistern, including photographic evidence, outlining its condition, findings from the inspection, and a recommendation to either clean or replace.

2. Replacement Proposal (as needed): A formal proposal for any cistern recommended for replacement.

3. Service Completion Report (within 5 business days of work completion): A comprehensive report for each serviced cistern detailing the work performed, dates of service, chemicals used (with Safety Data Sheets), and pre- and post-service photographs.

4. Certificate of Sanitization: A certificate for each cleaned cistern, confirming that it has been sanitized in accordance with AWWA C652 standards.

5. Water Quality Test Results: Certified laboratory results for water samples taken from each cleaned or newly installed cistern, demonstrating compliance with Colorado’s potable water standards.

5. PERIOD OF PERFORMANCE

The period of performance shall be from the date of contract award and does not exceed 360 days. All on-site work must be completed within this period.

6. PLACE OF PERFORMANCE

All work shall be performed at the NTIA - Table Mountain Field Site, 8600 N 39th Street, Longmont, CO 80503.

Specific building locations will be provided to the contractor upon award by the COR.

7. GOVERNMENT-FURNISHED PROPERTY AND INFORMATION

The Government will provide:

• Access to the Table Mountain Field Site and the specific buildings listed.

• A designated COR to serve as the technical point of contact.

• Access to a water source for cleaning and refilling cisterns.

8. APPLICABLE STANDARDS AND REGULATIONS

All work performed under this SOW shall comply with the most current versions of the following standards, at a minimum:

• Colorado Department of Public Health and Environment (CDPHE), Water Quality Control Division Regulations: Specifically, Regulation 11, the Colorado Primary Drinking Water Regulations.

• American Water Works Association (AWWA) Standards:

• AWWA C652: Disinfection of Water-Storage Facilities.

• Other applicable AWWA standards for water system components.

• NSF International Standards:

• NSF/ANSI/CAN 60: Drinking Water Treatment Chemicals.

• NSF/ANSI/CAN 61: Drinking Water System Components.

• Occupational Safety and Health Administration (OSHA) standards for worker safety, including but not limited to confined space entry protocols.

9. CONTRACTOR QUALIFICATIONS

The Contractor shall demonstrate experience in potable water system maintenance and installation. The Contractor must be licensed and insured to perform this type of work within the state of Colorado.

10. ACCEPTANCE CRITERIA

Final acceptance of the work will be granted by the COR upon:

• Verification that all tasks described in 3 have been completed satisfactorily.

• Receipt and approval of all deliverables listed in 4.

• Successful visual inspection of the completed work.

• Confirmation through water quality test results in that the water in each cistern is safe for potable use and meets Colorado state standards.